The purpose of this stage is to provide a detailed definition of how the programme is to be set up, the delivery strategy, the level of resources that delivery will require and the governance controls to be applied, collectively known as the programme delivery plan (PDP).
Approval of the programme business case authorises the appointment of the principal members of the programme management team, who will then develop the strategy and methodology for the execution of the programme, collectively documented in the PDP (see Figure 4.1).
Figure 4.1 Stage C: Definition.
During the Definition Stage, the elements discussed next must be addressed.
The vision statement and programme brief are reviewed in order to develop a greater understanding of each benefit. Benefit profiles are developed, which consider the following:
The benefit profiles are collated into a benefits realisation plan, which describes how and when benefits resulting from the programme will be obtained
Preparation of the benefit profiles will enable the development of a project list known as the ‘projects register’, which will be necessary to achieve the programme outcomes. Each identified project needs to be fully scoped, together with the criteria of output, cost and time established. Any across-project dependencies or external constraints need to be highlighted. Delivery strategies for the projects must be stated, along with the managerial resources required and an indication of where these resources will be sourced.
Scope definition is among the key critical success factors often cited by senior managers. These include:
Scope definition is fundamental to an effective programme control function in order to build the right organisation and set of policies, procedures and processes for delivery. It will guide the programme to:
It provides a comprehensive summary of a programme, detailing the scope, schedule, budget and risk based on a clear map of the work and how it is broken down in time and space using the WBS.1
A collectively developed, shared, understood and used WBS or activity schedule is at the heart of programme success.
Also needed is a network of activity that clearly sets out the overall strategy for breaking down the programme that can also be supported by a visual schematic geographical representation to show:
As programmes tend to be large and are generators of significant change, their influence has an impact on a wider scale than just one-off projects. Because of their nature, it is also likely that programmes have a higher visibility than do projects. It is therefore essential to the design stage that there is a detailed deliberation of the identification, interest and influence of stakeholders; it is likely the list of stakeholders will be substantial. The large impact of some programmes means there is likely to be higher degrees of opposition or dissatisfaction. As effective stakeholder analysis and management is critical to programmes, a full time stakeholder manager, or even a team, may be assigned to ensure this important aspect is dealt with successfully.
A detailed stakeholder analysis and a stakeholder management strategy will be developed from the initial considerations included in the programme business case. A ‘programme communication plan’ will be created that defines how each stakeholder will be dealt with and the nature, extent and frequency of communications within and outside of the programme team and stakeholders.
The programme mandate and brief will have identified a number of risks, issues, assumptions and constraints, and these are now revisited in light of further understanding of the programme that is emerging. This is an opportunity to take advantage of a wider consultation on these aspects.
Risks (circumstances that may occur or change, some identified and expected, others unknown and unexpected) will be analysed in a risk register, and a methodology will be adopted for their ongoing monitoring and management. Some financial contingency allowance needs to be calculated for the impact of the risks.
Similarly, issues (things that have already happened and need action) will be listed in an issue register and a methodology adopted for their ongoing monitoring and management.
Initial assumptions need to be reviewed to clarify likely impacts on the programme. Some assumptions may concern factors outside the direct influence of the programme, and these may need to be referred to the project sponsor who may in turn need to obtain further advice from a higher level in the sponsoring organisation. Any additional assumptions made during this stage also should be considered and included on the register. Where appropriate action plans are developed, a methodology for regularly reviewing assumptions also should be developed.
Any constraints need to be subjected to a similar approach. Consideration should be given to devising strategies that avoid major constraints. Constraints may be created by:
Based on the information contained in the programme brief; the benefit profiles; projects register and risks, issues, assumption and constraints registers, an overall delivery time schedule for the programme is produced. [Note: In common with other CIOB publications, to avoid confusion between terms, ‘schedule’ is adopted throughout this publication rather than ‘plan’ or ‘programme’.] The time schedule estimates anticipated completion of the programme, the anticipated duration and timing of individual projects, and identifies when benefits realisation are expected. It highlights dependencies between projects and any external dependencies. In situations where there is a complex pattern of dependencies it may be helpful to produce dependency charts.
It should be possible to identify the critical path sequence through the programme time schedule as this is helpful information when having to make decisions on resource priorities. It should be acknowledged that, at this stage, it may not be possible to identify all the projects that are required to achieve the programme’s objectives.
In addition to the overall programme time schedule, a more detailed start-up time schedule should be produced describing the timing of activities necessary to mobilise the next stage of the programme once approval to proceed has been obtained.
At the point at which the delivery plan and delivery time schedule have been devised, it is possible to prepare a financial statement that collects all the costs that have been identified in relation to implementing the programme.
The financial statement should be compared with the financial information contained in the programme business case and any significant variances highlighted.
From the financial plan and the delivery time schedule the expenditure cash flow profile can be calculated. This is a critical document because it informs the funding commitment for the programme. It must therefore be presented, discussed and approved by a senior executive of the sponsoring organisation, such as a financial director, before it can be included in the PDP.
Compared with a project budget, there is a higher degree of uncertainty attached to determining programme budgets as the timescales involved are likely to be much longer and the exact number and scope of projects to be instructed may not be known until later in the implementation of the programme.
The high cost of many programmes creates a substantial risk to the financial standing of the sponsoring organisation; therefore, oversight of the financial aspects of programmes is a crucial function. The role, of programme financial manager must be undertaken by an experienced financial manager who has expertise in dealing with complex issues around tax liability, capital allowances and programme funding.
Prepared principally by the business change manager (BCM), a detailed strategy must be produced to describe the mechanism by which each project output is handed over and incorporated into the final enterprise. How this is achieved will vary depending on the nature of the undertaking. In some situations project outputs can be immediately put into a ‘business as usual’ state, but others may need an assembly of numerous ‘outputs’ from projects from different programmes.
The ‘transition plan’ will explain what management infrastructure must be in place from the new enterprise in order to take ownership of project outputs as they become available. The document should also set out the acceptance criteria for each of the deliverables.
Production of the documents discussed above, as identified earlier in Figure 0.2 and Figure 0.3 in the Introduction, collectively form what is referred to as the PDP. (See Figure 4.2.) The PDP is a detailed description of what the programme will deliver, how and when it will be achieved and the financial implications of its delivery.
Figure 4.2 Contents of the programme delivery plan.
The PDP is presented to the programme sponsor board (PrgSB) for their consideration and, providing it falls within the parameters established in the business case, their endorsement that the programme can proceed to implementation.
In situations in which the sponsoring organisation either has a complex structure or comprises a number of separate legal entities, or where stakeholders have a critical influence on or are significantly affected by, the programme, the PrgSB may require further consultation on, or consent to, the PDP prior to their being prepared to authorise implementation.
Stage C marks the commencement of the involvement of almost the full programme team as they collectively evolve the programme’s implementation strategy and fully plan how the programme will be executed. See Figure 4.3 for a structure diagram. Control of the progress of the programme, which up to this point has been with the programme sponsor (PrgS), moves to the PrgM, who now has prime responsibility for planning and designing the way the programme will proceed. Reporting to the PrgS, the PrgM is assisted by a range of personnel: a PrgFM, a programme stakeholder/communications manager and a team of specialists within a programme management office (PMO).
Figure 4.3 Stage C: Definition – organisation structure.
The BCM, working in conjunction with the PrgS and PrgM, continues with the function of ensuring at each stage that what is being proposed or delivered matches the requirements of the client. The business change manager takes responsibility for benefits management and for beginning to develop plans for the transition of the undertaking into its finished state.
In accordance with good management practice, the production of a roles and responsibilities matrix is a helpful device for assisting the determination of the level of structure and resource required.
The PrgSB have a number of key roles during this stage:
Having appointed a PrgM to take responsibility for this stage, the PrgS adopts a more strategic role and carries out the following:
During this stage, the BCM continues to focus on the benefits to be delivered and the final outcome of the programme by doing the following:
Depending on the size of the programme, it may be necessary to appoint a benefits realisation manager to support the BCM. The role of the benefits realisation manager during this stage is to:
Leading this stage, the PrgM has a number of key tasks:
The PrgFM has responsibility for ensuring that the programme budget determined during this stage aligns with the business case. The financial manager’s principal activities include:
The programme management board (PrgMB) comprises the senior managers of the programme management structure and provides advice and support to the programme manager. The PrgMB should meet regularly to review the programme’s progress and to highlight and resolve any issues that may be hindering it.
The PrgMB is likely to be composed of the following managers:
The stakeholder/communications manager’s role includes establishing an understanding of the programme’s stakeholders and a plan determining either their level of engagement or how they will be kept informed of the progress of the programme. This will involve the following:
In addition to requiring a PrgM, this stage requires that the core members of the PMO also be available. These include the head of the PMO and sufficient staff with the necessary technical expertise to carry out the functions required during this stage to develop the PDP and to establish the governance controls. The size and range of expertise required will depend on the nature and complexity of the programme. In some instances the input required from the programme team may be available from within the sponsoring organisation, but in many others it is likely that all the expertise will be externally sourced specifically for the programme. In addition to specialist input on matters such as legal aspects, property and finance, some sponsoring organisations may need to contract with organisations to provide all the programme management delivery capability. These positions include the following:
Apart from the stakeholders in Chapter 1, Section 1.7.5, a programme will often include other stakeholders that in one way or another may be affected by the programme. Common stakeholder groups include the following:
Any programme affects the environment that it operates in and at the same time is also affected by the environment. The external environment influences business strategy and the success of a programme.
It is therefore essential not only to identify external drivers in order to shape a strategic change and a programme, but also to identify, map and track programme stakeholders, as this will help develop support and manage programme communications. See the stakeholder map in Figure 4.4.
Figure 4.4 Stakeholder map.
Stakeholders include persons and organisations that have an interest in the strategy of the organisation and programme and have an impact on or are impacted by a programme. Stakeholders normally include shareholders, customers, contractors and vendors, staff and the local community.
Programmes and organisations need to be able to identify their stakeholders and judge the level of power they hold to affect the decisions and outcomes of the programme. A first step for this process will be to create a stakeholder map. This map will include all the stakeholders for his or her organisation with the programme at the centre. Stakeholders include:
During the definition stage, concurrent with the PDP being developed, work is underway on the assembly of a series of processes and procedures that will describe how the various management governance controls will be implemented for both the programme and individual projects. They provide all the programme participants with a consistent understanding of how the PrgS and PrgM, or indeed the sponsoring organisation, want the programme and projects to be managed.
Processes and procedures need to be developed for the areas discussed next.
In the context of programme management, scope for a programme relates to the collective objectives of all the component projects and activities. The responsibility for managing individual project scopes will stay with the project managers; however, the PrgM will be responsible for the overall scope management.
Scope for a programme is underpinned by three key components:
The delivery requirements collectively provide a view of the end state of the programme and must align with acceptance criteria to ensure that the project activities address and satisfy the specific requirements.
The programme initiation documentation outlines the current state and the vision for the future state; it is the scope that defines how the programme will enable the changes to ensure that the transition is effected from the current state to the desired future state.
Where the end state is well understood and has a tangible output (e.g. in construction and engineering), it is usual to define the scope as accurately as possible at the beginning. This potentially reduces the level of changes that may be required and keeps costs from escalating. It is also useful to define what is outside of the scope to avoid misunderstandings. Clearly defining what is in and out of scope reduces risk and manages the expectations of all key stakeholders.
Where the objective is less tangible or subject to significant change, for example, business change or some IT systems, a more flexible approach to scope is needed. This requires a careful approach to avoid escalating costs.
It is important to recognise that, particularly for large and complex programmes, it is most likely that initial scoping will be required to undergo changes as risks, issues, and changes in the wider landscape emerge. The programme design must enable a robust and effective change management process to deal with the scope variations and changes, and most importantly, must be capable of identifying and flagging where a change in scope occurs.
It is the responsibility of the PrgM to flag any changes to the scope (be it at project level or programme level) to the PrgS and all changes to scope must be authorised by the PrgSB.
In practice, the majority of scope change requests will be generated at the project level; it is critical that scope change approval is not done at the project level. Those involved in projects can see their own work, but they can’t see the interdependencies that exist between projects. Therefore, those working on the projects don’t have the right level of understanding as to the impact of scope change requests across the projects. This requires that project scope changes be escalated to the programme level for a decision.
Scope is typically managed both at programme and project level.
Managing programme and project scope change is one of the primary responsibilities of the PMO.
These methods are used to identify the activities that are necessary to achieve the programme’s objectives:
At this phase, it is necessary to define how benefits will be managed, from identification through to realisation, in alignment with the programme vision and the business case.
The key considerations at this phase will include the following:
The considerations and outputs generated at this phase must be subject to a change control process, and benefit profiles can be used to capture any changes or amendments. The benefit realisation activities in the PDP will also need to be amended to reflect any approved changes.
Risks will be identified, recorded, monitored and managed in the following ways.
As technical and commercial issues get more complex and financial metrics tend to proliferate, finance and programmes often end up measuring performance and risks in different ways, using various sources of information and, in many cases, using a different language. Risk assessment is not an exact science, and there are a number of different methods to measure or quantify risk.
Effective risk management begins with realism – seeing things as they are – and continues with a joined approach and common understanding at all levels of an organisation or programme. A strong corporate risk management culture and consistent risk-rating methodology are fundamental to the success of a programme in order to focus on the risks that matter.
The guidance below offers a structured common sense-based approach to risk management.
The key success factors are as follows:
Risks will generally fall under the following categories:
The objectives of effective programme risk management are as follows:
Risk is often defined as ‘an effect of uncertainty on the objectives2’. Risk can be categorised as the following:
An issue may be defined as:
It is imperative that all issues are recorded on the project issue log; however, an issue should be reported to the PMO only if the project team cannot resolve the issue or if the project manager determines that the issue impacts other projects that are outside the PMO’s scope of responsibility. The issue process implemented by the PMO is to ensure that the appropriate management team is engaged to help resolve problems.
At the portfolio level, risk management and change control is supported centrally, which brings together a set of essential functions to support the successful delivery of programmes and projects, including:
Quantitative risk assessments (QRAs) based on experiential understanding of the effect of uncertainty in relation to the programme out-turn cost (or anticipated final cost [AFC]) and schedule delivery will be performed at key stages of a programme. Certainty of outcome will become greater as the programme approaches its final stages. Probability management will store uncertainties as data in a model that is actionable, additive and auditable.
For this purpose, three-point estimating (as illustrated in Figure 4.5) can be used as a tool for estimating cost and schedule value and assessing overall risk.
Figure 4.5 Three- point estimate triangle.
The following areas will need to be considered during this process:
Given the number of estimates and activities on a programme, the three-point estimate can sometimes be misleading. Another estimating technique is to enter variances of the probability distribution around the most likely estimate. This technique is based on an integrated holistic understanding and current knowledge of the programme’s inherent risks. The estimation of uncertainty is illustrated in Figure 4.6.
Figure 4.6 Estimation of uncertainty: illustrative example.
A QRA undertaken on the programme will confirm the appropriate level of contingency (also known as ‘overall risk pot’) required to deliver the programme and shared between funding organisation, programme and projects. This includes the assessment of risks within individual projects in addition to cost and schedule risks across the programme.
The basis of the risk model should be an agreement of risk allocation between funders. The level of contingency proposed in the budget should represent those risks agreed to be under the influence and control of funders, programme and projects. The funders contingency relates to risk that does not sit with the programme and projects. The programme contingency relates to risks that do not sit within the individual projects and are not covered by project contingencies.
In summary, an s-curve will represent the likely exposure of the total risk across the programme (see Figure 4.7). Based on the agreed allocation of risk (at the 80th percentile), the contingency requirement, inclusive of VAT, will be estimated – that is, there is an 80% likelihood of not exceeding this contingency. The curve will also indicate that, from the analysis, an additional £xxxm would be required to secure a confidence at the 95% level.
Figure 4.7 S-curve detailing the cumulative contingency requirement.
The s-curve will indicate an upper limit that is significantly greater than the 80th percentile; to some extent this is influenced by the probabilistic model and the potential for uncontrollable acceleration costs or design risks. This suggests an increased maximum out-turn cost, albeit at a low level of probability. It is important that funders recognise increased exposure throughout the programme as it represents a substantially higher potential cost above the level at which the programme contingency is calculated.
There are other ways to represent risk and probability graphically as tornado diagrams or bar charts using Monte Carlo analysis and proprietary software for cost and time probability assessment.
It is apparent from programme delivery history that the risk of strategic misrepresentation remains high for complex programmes. Senior managers will need to consider the level of optimism biased (the tendency to overestimate the achievability of planned actions) for any programme. Benchmarking, due diligence, and historical local performance analysis will allow the programme to avoid blind spots and prepare the organisation for black or grey ‘swan events’ – low-probability high-impact risk (terrorism or major temporary design failure) or unknown unknowns (natural disaster).
Governance defines the structure, roles and responsibilities to set objectives and report and monitor performance in order to make decisions and to steer a programme towards its anticipated destination.
The Organisation for Economic Co-operation and Development (OECD) defines governance as a set of relationships between an organisation’s owners, its board, its management, and other stakeholders. This provides the structure through which the organisation’s objectives are set and the means of attaining those objectives and of monitoring performance are determined.3
The APM (Association for Project Management) defines governance of programmes and projects as follows: governance of programme management concerns areas of corporate governance that are specifically related to programme and project activities. Effective governance of programme management ensures that an organisation’s programme is aligned to the organisation’s objectives, is delivered efficiently and is sustainable. Governance of programme management also supports the means by which the board, and other major project stakeholders, are provided with timely, relevant and reliable information.
The governance of programmes will cover the following areas:
The terms of reference for a programme board will typically cover the following:
Optimal governance, programme change control, risk management and reporting of an approved baseline scope will allow a business to manage risk, deliver value and drive programme and project decision-making while saving time and efforts. See Figure 4.8 and Figure 4.9.
Figure 4.8 Change management, risk management and reporting.
Figure 4.9 Ability to impact and commitment to the change.
Establishing and implementing a measurement and reporting system is a complex and evolving process based on the simple business principle that what can be measured can be managed. ‘Too much data, not enough information’ is a common complaint among business managers who have to keep track of the status of programmes while relying on information that is incomplete, out of date, inaccurate, late or simply irrelevant.
Reporting requirements will change as projects and programmes move from inception through their life cycles. It is important that the reporting system is designed to focus on metrics that matter at the relevant stage.
The critical success factors that underpin the operation of effective reporting are the following:
The measures that matter for effective control should be simple and reliable.
Key performance indicator themes should be reported and agreed upon by each functional area or, in leading global organisations, across a portfolio of projects or a programme to deliver strategic objectives. The indicators are then aggregated into project, programme and executive board reports to assist in meeting the needs for information, control and governance. As the programme progresses through its life cycle, the quality and availability of key performance data available to the different functions will develop.
Performance measures should be based on the key performance indicators that are most commonly associated with the built environment and include key objectives such as cost, time and quality.
Organisations will also seek to measure and report other success factors that align with their strategic objectives, such as environmental sustainability and corporate social responsibility themes. The importance of these performance indicators and measures will change as the capital projects and programmes move through the various stages of their life cycle (investment planning, design, procurement, manufacturing, construction, commissioning and operations).
Once this process is in place and data and information are flowing more or less painlessly, it is then down to management to trust it and act on it, as there is often no worse decision than no decision at all – even a bad one.
This trust will undoubtedly be reinforced by a level of checks at all levels of the organisation, or integrated assurance.
As outlined in Section 4.4.3, issues management is an ongoing programme management function, akin to risk management. The programme’s approach to issues management must be clearly defined and endorsed by the PrgS, including the decision-making procedures.
The approach should include roles and responsibilities in relation to management of issues during the programme and may include the following:
Initial issues will have previously been recorded as part of the completion of the brief and the business case – the initial registers can be turned into the live issues register with assigned ownerships as the programme progresses.
In its simplest form, a schedule is a listing of activities and events organised by time. In its more complex form, the process examines all programme activities and their relationships (interdependencies) to each other in terms of realistic constraints of time, budget and people, that is, resources. In programme management practice, the schedule is a powerful planning, control and communications tool that, when properly executed, supports time and cost estimates, opens communication among personnel involved in programme activities and establishes a commitment to programme activities.
However, it is not always practical or realistic to prepare a time schedule for programmes – in many instances there may be additional constraints (e.g. output delivery dates may be set by parameters beyond the control of the delivery team or a target may be set for commencement of benefits realisation for certain outcomes); it is often the case that, especially for programmes with intangible deliverables, while a realistic time schedule can be prepared for individual projects and activities, the overall programme time scheduling remains a bit of an unknown until the commencement of the implementation phase. However, almost all business cases will allocate a certain time for any programme even if only for funding purposes, and it is the responsibility of the PrgM to ensure that a detailed programme schedule is prepared at the definition phase identifying each individual component and that it is regularly reviewed for any variance. The PrgSB will be made aware of the variances through the programme highlight report and should decide on the appropriate course of action.
Business today needs finance officers who understand how engineering and production processes are really managed to help with establishing:
Difficulties in aligning and reporting for business and programme purposes are not uncommon. Financial reporting normally spans a fiscal year, whereas programmes, due to their nature, may span a number of years. Additionally, financial and programme professionals do not necessarily talk the same language or have the same reporting needs.
Communication is the key aspect of prudent financial management. Opacity in budget allocation leads managers to make assumptions and decide on the basis of their current knowledge over time. Particularly on major programmes, it is of vital importance that meaningful and timely information is generated from the vast amount of data that would be available. Figure 4.10 sets out the individual roles of the key personnel in context of programme management at this stage.
Figure 4.10 Financial management roles and responsibilities.
Once funding arrangements, share of contribution, delegated authority and contingency allocation is apportioned and agreed upon to form a fund, a budget developed in parallel can be managed and its change controlled through the programme gates.
Budget, including contingency, can be represented by a WBS element using a tabular format or a bar chart as seen in Figure 4.11.
Figure 4.11 Programme budget for transport programme (example).
It is essential to capture baseline assumptions as part of a budget to allow for all parties to understand the associated risks. Assumptions will typically include: scope, design, construction, schedule, cost, inflation, currency, commercial, procurement, land and property, legal framework, operations, and asset management.
Changes and contingency management related to scope (schedule, cost and quality), including design development, valuation (value engineering), new scope, sequencing or acceleration cost (also known as de-risking in some programmes), cost savings or procurement and delivery model adoption (for example engineering procurement and construction as opposed to in-house delivery) can be identified and communicated using a waterfall or bridge diagram.
Waterfall charts4 are commonly used in business to show how a value changes from one state to another through a series of intermediate changes. Waterfall charts are often called bridge charts (particularly in financial jargon) because a waterfall chart shows a bridge connecting its endpoints.
Traditional cost and performance measurement systems often fail to distinguish between cost incurred and physical progress made. Under these systems, it is difficult to analyse separately cost variances and schedule variances. One answer to this is earned value management (EVM).
There are two key primary objectives of an earned value system: (i) to provide programme project managers with a reporting system that gives them better control over cost and schedule management and (ii) to provide customers a better picture of the status of work. See Appendix T5 for a Monthly Programme Report template.
Cost performance indicators (CPIs) and schedule performance indicators (SPIs) are gaining popularity as performance measurement systems in the construction industry and are acknowledged to make a positive contribution to the planning and overall control of a major construction project or programme. CPI = 1 and SPI = 1 means the programme is on track.
CPI and SPI are the two principal components of EVM (see Figure 4.12) and allow project and programme to:
Figure 4.12 Delivery/project performance – programme EVM summary.
There are several secondary objectives for measuring CPI and SPI on projects across a major programme. These include:
By integrating these measurements, EVM aims to provide consistent indicators to evaluate and compare the progress of programmes and construction projects. EVM compares the planned amount of work with what has actually been completed to determine if cost, schedule and work accomplished are progressing as planned. Work is ‘earned’ or credited as it is completed.
CPI and SPI are not absolute measures of progress and should not be viewed in isolation. The indicators should be viewed in conjunction with other progress reports and performance measures such as monthly milestone and variance reports. The information is processed and published in progress reports on a monthly basis and, in conjunction with other project progress information, can be used by both the client and supplier(s) to monitor performance and encourage a greater degree of control and proactive decision-making.
To make a positive contribution, the measurement system is dependent on two key factors:
Programmes will also report an annual spend forecast (Figure 4.13) or fiscal year performance and provide long-term projections (Figure 4.14) based against the approved baseline. This should be aligned and coordinated with financial reporting.
Figure 4.13 Programme fiscal year performance (annual spend forecast).
Figure 4.14 Four-year programme cost projection.
Although a source of many frustrations, integration, as illustrated in Figure 4.15, is key to programme and financial reporting alignment and will drive accurate reporting and inform decision-making.
Figure 4.15 Reporting integration.
One method is to set up the main accounting systems to track cost and billings by WBS line item. Most ERP (Enterprise Resource Planning) packages will track inventory movements by item type or by project code.
Project- and programme-oriented businesses need to be able to relate the use of material and labour to one key ‘manufacture’ or ‘procurement’ item number at a WBS level, allowing:
Best practice strategies for improved cost control include:
Finance will control the programme expenditure at year end and monitor actual against forecast (AFC) expenses and budget. Profit and loss and balance sheets will be also compiled for business-reporting purposes and will include programme cost to date and any other additional costs outside programme control. (See Figure 4.16.)
Figure 4.16 Full year programme expenditure example.
As the saying goes, the only constant is change. At the definition phase, it is critical to ensure that a robust change control and management procedure is designed to enable formal identification, evaluation and decision-making required for accepting or rejecting changes to aspects of the programme.
Procedures should be put in place to manage changes, both at programme level and project level. Changes to scope, PDP, business case, benefits and budget will affect the overall programme and must be managed at the programme level.
Programme level changes must be signed off by the PrgSB and be managed by PrgM.
Typically, programme highlight reports should contain a change register.
Process and systems to be used for managing and storing information include:
At the heart of a programme is information and how it is communicated. Information has to flow within a programme in a way that will allow management, project managers and project teams to achieve business objectives while transparently keeping all stakeholders informed.
Communication is the process of transferring information from one source to another. Effective communication is a two-way process in which technical information, analysis, commentary and comments are conveyed through reports, speech and other mediums to a specific audience so that the intended audience will be informed, perform an action, or reach a decision based on this information.
The fundamental purpose of information management is to communicate effectively and with consistency relevant and accurate data to project stakeholders at all stages of the programme life cycle and beyond using effective information systems and models – BIM. The provision of good quality, timely information is an essential deliverable for any programme. Systems and procedures should be defined to enable effective management of information through the life cycle of the programme from inception to the delivery of operational assets. An effective information management system should facilitate direct relationships with the relevant information enabling storage and ‘retrievability’ of the following:
Integration is the combination and co-ordination of multiple sources of related information so that sources work together and form an ‘integrated’ whole with the ability to provide a snapshot of progress status at any chosen reporting milestone. The integration process will allow for interdependencies and design, procurement, construction, commissioning, departmental, organisational and supply chain interface issues to be identified and addressed from a single source. Key information (variance, exception) will be captured, assessed and forwarded to the relevant authority for a decision to be made and implemented.
The level of integration will vary from loose to tight integration depending on the current programme stage, agreement of a common purpose, set of objectives and level of process and systems standardisation. Programmes are usually carried out by a project team under the overall direction and supervision of a PrgM. In practice, there will be many variants of this structure, depending on the nature of the programme, the contractual arrangements, type of project management involved (external or in-house) and client’s requirements.
As the programme evolves, it is essential to strive for an integrated information repository to manage increasingly detailed information. All integrated programme assets or documents should be coded and linked to a programme database. In the context of a physical asset programme, BIM is a powerful tool that will allow a programme to be integrated in a multidimensional model created for management purposes.
In summary, programme management systems need good quality sources of information on which to base their decision-making and manage operations post-delivery. Management reports, project summaries, reporting systems and data will include the following:
The process developed for communicating with the programme team and stakeholders may include:
A stakeholder management plan aligned to business and programme objectives can be designed in six steps to communicate effectively to the programme audience and gain support along the way.
Defining stakeholder segments starts during the strategy and programme definition phases.
Programmes and organisations need to be able to identify their stakeholders and assess the level of impact they will have in meeting the objectives and outcomes of the programme. A first stage for this process will be to create a stakeholder proximity map. This map will lay out different tiers of stakeholders according to their potential to affect the reputation or the progress of the project or organisation, with the programme at the centre.
Stakeholders will be identified, captured and mapped for proximity to the programme in terms of direct impact or interest, influence and control in the programme landscape, based on the following questions.
Once the stakeholder map and landscape is understood, a tracking tool articulating what reengagement activities are required for each stakeholder will allow tracking progress. The tracker will identify the stakeholder relationship owner in the programme – a person accountable for managing and directing the stakeholder relationship.
It is a common experience in a professional’s life to have the urge and necessity to communicate a message that, at that time, was thought to be right, needed to be communicated without delay and needed to be communicated to a group of colleagues and line managers. It is also fairly common, with the benefit of the hindsight, to think about an e-mail that has been sent and should not have been. If this communication is scaled up to a very large organisation and programme and the way this message communicated the message is considered, particularly in times of critical decisions, the importance of clear, efficient, effective and appropriate communication can perhaps be put in some context.
In simple terms, communication is the process of transferring information and knowledge from one source to another.
Effective communication of the relevant information is a two-way process in which data, evidence, analysis, commentary and feedback are conveyed through reports, speeches and other media to a targeted audience to perform an action or reach a decision based on this information
Once the stakeholder audiences are defined, it is paramount to define a set of key messages and positioning statements to address these audiences in their questions, concerns, and other key requirements. A series of pre-defined lines to adopt should also be prepared and ready to use, especially in cases of crises or issues. It is important that messages are continuously updated and aligned with the programme’s variables or changing milestones.
A good communication strategy and plan will ensure that the programme audience is informed in a targeted and timely manner.
Based on the stakeholder analysis, the communication plan will list the messages and interventions to be communicated to which audience group, when, how (medium), why and from whom.
Communication mediums can be categorised as high or low impact and commitment building and will include:
Key communication principles include the following attributes:
The method and responsibility for assessing the ‘fitness for purpose’ of the project outputs, outcomes and programme deliverables will need to be defined. This might be through specifying the acceptance criteria and/or the performance criteria. For programmes with tangible deliverables, for example, a new facility, it is relatively easier to define the quality acceptance criteria; where programmes include intangible deliverables, it may be necessary to rely on secondary assessment methods to quantify acceptance or performance criteria.
It is advisable to introduce periodic reviews of the quality management procedures at key stages of the programme life cycle to test the adequacy and the effectiveness and enable any changes or amendments as necessary.
Procurement is the process by which the resources (goods and services) required by a project are acquired. It includes the development of the procurement strategy, preparation of contracts, selection and acquisition of suppliers, and management of the contracts.
The benefits of contracts and procurement are that:
Effective procurement and contract management is core to a successful programme. The procurement policy, procedures and processes should be established to guide the procurement of a range of contracts and projects.
It is important for companies to develop purchasing policies and procedures that include the following:
Based on the above, managers will develop a ‘contract packaging’ approach which will break down the entire programme of work for delivery into suitable elements for procurement. This will be refined in discussion with the potential suppliers and contractors. To meet the programme objectives, on time and in the given budget, often managers will procure a large number of contracts and projects of varying size and value.
A robust, fair and transparent approach to procuring, managing and monitoring these agreements is essential, as is carefully managing the risks associated with the overall programme and related projects. A programme will often have to operate in the procurement framework set out by international procurement legislation and national regulations.
For major programmes, it is also recommended to give advance notice of contracts through a ‘future opportunities’ website – the equivalent of market building for supply chain members – and adopt e-tendering practices.
To operate effectively in the marketplace, programmes will use standard procurement documentation and contracts such New Engineering Contract (NEC)/Fédération Internationale Des Ingénieurs-Conseils (FIDIC) and CIOB’s.
Managers will award contracts according to broader objectives and values. Ahead of every contract competition, programmes will develop a ‘balanced scorecard’ of selection and award criteria that will inform companies of the commercial and technical factors their bids will be scored against. This should include time, quality, safety and security, equalities and inclusion, sustainability and legacy.
Appropriate criteria will be added and different weights applied to each criterion on a contract-by-contract basis, according to the nature of the goods, services or works being procured and best practice guidance from the Office of Government Commerce. To avoid costly and time-consuming disputes, the programme should seek to make clear agreements with all parties while agreeing and managing contracts.
Best practice suggestions to manage the risks in this area include:
Key performance indicators to measure the performance of the procurement or buying processes include:
Figure 4.17 illustrates an example of progress of procurement and commercial management presented graphically.
Figure 4.17 Invitation to tender (ITT) and signed outline contract (SOC) plus value of contract placed.
Managers need to ‘design’ their organisations and programmes to embrace change and deliver programmes effectively.
The following criteria will need to be considered in order to design and agree on resource profiles that are fit for their purposes and align with the delivery model so that the right level of resources are allocated to a programme at the right time:
The above criteria will depend on the delivery model adopted, but leading PrgMs focus on building an intelligent client organisation to lead delivery and maintain the right level of control. This is a key factor in successful cost management. It needs to be established at start of programme so that appropriate resources are allocated. Where necessary, certain elements may then be outsourced, subcontracted or bought according to a build or buy model.
Programmes will need to formulate health and safety management policies and procedures both at the project level and the programme level. It is the responsibility of the PrgM to ensure that at the definition phase the health and safety goals, requirements and procedures are set and that the processes are put in place to transfer these to the project levels as necessary. In some instances, specific key performance indicators or targets may be set to measure performances both at the project level and the overall programme level. It is advisable to also set specific review stages to assess whether the health and safety management policies and procedures are performing as desired across the programme.
It is often said that sustainability is essentially not a methodology but a dimension of thinking. The perception of sustainability is shaped by people’s values, behaviour, attitude, ethos and interaction with the wider environment. Programme management is concerned more with outcomes than outputs. With emergent input in a changing environment, a PrgM makes use of current information to identify options for comparison and decision. Once the decision is made, the PrgM will take over the project(s) where sustainability is a consideration. In other words, for sustainability in programme management, the PrgM emphasises the learning loop leading to the preferred options: the PrgM has to assess the suggested programme options in the dimensions of economic sustainability, environmental sustainability, and social sustainability before recommending the options. In most cases, the organisation commissioning the programme will have sustainability and environmental management policies at a wider level or, indeed, may have certain aspirations and targets specific to the programme. The PrgM must ensure that the goals and targets, as necessary, are defined and translated to procedural requirements at the project level.