The purpose of this stage is the initiation and execution of the various projects comprising the programme, including assessing performance of individual projects, managing the interfaces between projects, monitoring benefits realisation, managing financial expenditure and managing the introduction of any changes to the programme.
In this stage the physical activities of the programme are executed through a number of projects (see Figure 5.1). The focus of the programme management team is on ensuring the successful implementation of each individual project in accordance with the planned sequence and the delivery of the required outputs. At the commencement of the stage, the following tasks need to be actioned.
Figure 5.1 Stage D: Implementation.
Initiate projects
Performance monitoring and control
Reporting
Projects closure
The implementation stage marks the maximum effort and involvement of the full programme management team as there is a collective effort to deliver the outcomes of the programme in accordance with the proposals set out in the PDP. This effort is headed by the programme manager (PrgM) who, closely supported by the PMO, initiates, monitors and closes the projects which make up the programme. The business case manager, together with the benefits realisation manager, ensures that the required benefits are being progressively realised and that the new capabilities or facilities are being effectively introduced into the client’s organisation. (See Figure 5.2.)
Figure 5.2 Stage D: Implementation – organization structure.
The PrgSB continues its role as adviser and approver, fulfilling the following duties:
Continuing to be the interface between the programme and the client’s organisation, the PrgS maintains a check on the programme’s overall progress and keeps the client advised of this progress. Principal tasks include:
The business change manager (BCM) is focused on ensuring that the programme is achieving its planned objectives by:
Concerned with ensuring that the programme is delivering benefits in accordance with the PDP, the benefits realisation manager has the following responsibilities:
With full responsibility for the implementation of the programme, the PrgM has a wide range of tasks, including the following:
Throughout the implementation stage, the programme financial manager continues to manage the financial aspects of the programme. The tasks of the PrgFM will include:
The PrgMB continues to provide advice and support to the PrgM during programme implementation. The programme management board:
The stakeholder/communications manager continues to ensure interested stakeholders are identified and that there is a mechanism for maintaining their engagement in the objectives of the programme by doing the following:
The PMO is responsible for providing the technical functions that allow the programme to be managed and controlled, including the following tasks:
Within the PMO, functions with specific responsibilities include:
Each project that is carried out as part of the programme will need its own management and technical teams responsible for the execution of the project. These teams are likely to include the following:
At this phase of the programme cycle, the procedural and management activities as defined during the earlier stages will be put into use to monitor and control the implementation of the outputs and outcomes.
It is the responsibility of the PrgM to ensure that resources across the programme are managed effectively. This will include the utilisation of internal and external resources and resources that may be shared across projects and programmes. Furthermore, the enabler technology and tools as identified during earlier stages to support the implementation should also be made available. It is often advisable, particularly for large and complex programmes, to have core teams co-located or at least undergo team-building exercises to develop effective relationships and engender trust.
In addition to the core programme management activities identified later, the following activities, which are initiated during the early stages of the programme, need ongoing attention during the implementation phase to ensure desired delivery of the programme outcomes and benefits:
Managing the PDP during delivery is vital to ensure that as the programme progresses, projects remain integrated with each other and the programme. In practice, this means regularly reviewing the PDP with the PrgM, BCM or their representatives and the project managers. It is important to give project managers the opportunity to report progress and BCM the opportunity to report operational issues. One way of doing this might be by undertaking PDP review workshops.
Holding a workshop with all project managers and change managers present will ensure that the knock-on effects of changes or ideas in one project or business area are explored with respect to the PDP in its entirety.
The regularity of PDP workshops will depend on what has been agreed on during the definition phase, but as a minimum should be undertaken as each step change in the programme is implemented.
The results of the review will usually mean that the PDP has to be updated and signed off before the next step change can be planned.
Benefits need to be regularly reviewed during the implementation stage as:
The method of review has been determined during the Definition Stage.
The benefit profiles will need to be updated and the benefit realisation activities in the PDP amended to reflect any changes.
The business case is the basis upon which the implementation phase of the programme is commissioned. As delivery progresses, changes outside the control of the programme may mean that the assumptions and estimates upon which the business case was made change.
The business case should be kept up-to-date in response to any changes. It is the responsibility of the PrgSB during implementation to ensure that the business case is updated and, if the case is fundamentally affected, to explore changes to the PDP and benefits in order to maintain the case.
In the scenario where the business case is fundamentally no longer viable, it may be necessary to consider the termination of the programme.
Conversely, it is also possible that changed circumstances may lead to further strengthening of the business case. In practical terms, this will mean looking for opportunities to increase the benefits and to reduce the costs. In some cases, increasing the cost may facilitate greater benefits. However, this should be balanced against making too many changes that lead to unproductive use of resources or increased risk of not achieving the desired outcomes.
The amount and level of detail required for progress reporting varies widely from organisation to organisation and programme to programme. The approach to be taken, including the documentation to be used, was defined during the definition phase.
It is important that the information provided is complete, timely and accurate so that appropriate decisions can be made by the PrgSB. These decisions include the following:
Typically, PrgM will produce a programme highlight report which will form the basis of the review. An indicative template of this report is shown in Appendix T6.
Risk and issue management are ongoing programme management functions. The programme’s approach to risk and issue management will follow the process defined during the definition phase.
Risk and issues registers should be regularly maintained and monitored. The actions agreed either to mitigate the risk or resolve the issue should be included in the overall PDP or monitored alongside the PDP.
It is important to ensure that, where necessary, risks which look as if they are going to materialise and issues which cannot be resolved are escalated. Who to escalate to and when will be documented in the approach defined during the definition phase.
Risks and issues are often recorded in one or more closely related documents. Whichever method is used, it is important to recognise that managing risks and issues are two separate processes. Issues may arise that need to be resolved before formal risk and issue review meetings. It’s important that arrangements are put in place to immediately deal with issues as they arise. It is also possible that some issues may have an influence on the fundamental business case assumptions, in which case the PrgM should ensure that a considered resolution of the issue is undertaken.
The financial status of the programme should be monitored in accordance with the process defined during the definition phase. This monitoring will include:
Change control is the formal identification, evaluation and decision-making required for accepting or rejecting changes to aspects of a programme. Management of change during the implementation phase should follow the approach defined during the definition phase.
The principle is usually that if a change can be managed at a project level, then this should be the preferred way of managing a change.
Changes to the PDP, business case, benefits and budget will affect the overall programme and should be evaluated and approved at the level of the PrgSB.
The following type of information and signed-off documents should typically be subject to change control:
A change can have a positive as well as a negative influence on the business case, and unless managed appropriately, it may ultimately lead to detrimental effects towards the realisation of the benefits envisaged.
Appropriate information management arrangements should be put in place in accordance with the agreed approach defined during the definition phase. This will ensure that information is available when it needs to be, is current, and is compliant with the quality standards set for the programme.
During the delivery phase, it is essential to continue with planned engagement and communication activities with stakeholders as well as respond to unforeseen events.
The stakeholder engagement and communications plan should be regularly reviewed and adjusted to take into account any changes to planned delivery that need to be communicated.
The BCMs and PrgM should satisfy themselves that people with responsibility for engaging and communicating with stakeholders are doing so. Updates on progress can be included in the highlight reports.
Stakeholder engagement and communications is also a key part of the programme leadership function. The PrgSB and PrgS should champion the programme in day-to-day communication. They should also be sensitive to potential issues at a strategic level and respond accordingly where necessary with input from the PrgM.
The implementation phase of the programme ensures that the agreed method for assessing quality assurance and fitness for purpose as agreed during the definition phase is put into practice. This may include activities ensuring that for each project output or programme deliverable, acceptance or performance criteria are in place and are assessed, monitored and reported.
If part of the agreed quality or assurance checks is to undertake periodic reviews at key points in the programme’s implementation, these will need to be planned, organised and undertaken. Any findings and recommended actions would be fed into the overall PDP to improve performance.
The PrgM must ensure that when deciding quality and acceptance criteria for deliverables and project outputs, consideration is given to the practicalities of assessing them so that the assessment data can be tested for ‘fitness for purpose’.
The procurement and commercial management of programmes (and its components) will depend on the nature and type of the programme, its funding arrangements, and whether it is in the public sector or in private sector. In some instances, the procurement process may also include obtaining the services of an external PrgM and PMO.
Regardless of the type and approach, the procurement and commercial management processes at the implementation phase would need to consider the following:
At the implementation phase, the overall health and safety management plan, as prepared during the earlier phases, will be put into action. Typically, all the projects and activities undertaken during the implementation phase will adhere to the health and safety management plan requirements, particularly the targets and KPI’s that may have been set at the programme level. The highlight report for the programme may contain a summary of the health and safety performance of the projects and activities, reporting on the actual progress against the targets and KPI’s.
Project-level health and safety management will be a key element to ensure achievement of the overall programme targets. The Code of Practice for Project Management (5th ed) contains further guidance on management of health and safety at the project level.
The overall programme sustainability and environmental management parameters and targets will be set at the earlier phases. At the implementation phase, the processes and procedures, including overall programme targets and KPI’s, must be incorporated in individual projects and activities. Projects which may require planning permission will prepare environmental impact assessments that will also encompass the programme sustainability and environmental management aspirations.
Transition plans are necessary to successfully translate deliverables and outputs into outcomes that will enable realisation of benefits envisaged within the programme business case. These can be included as an update to the overall PDP. Transition plans set out the tasks needed to ensure that the new capability will be embedded into business as usual operations. They might include:
It is important to note that inadequate transition management may hamper the successful outcome of the programme even if the project outputs are delivered successfully.