|
C
Practice Exam I
|
Q1: Initiating the Project
1. You are the project manager for your organization and you’re working with your
supervisor to define the difference between projects and operations. You explain that
projects are unique while operations are the core business. Projects are typically
initiated for all of the following reasons except for which one?
A. Market demand
B. Organizational need
C. Ongoing manufacturing of equipment
D. Legal requirements
Answer: C
Hint: Projects are temporary.
Study Guide Objective: Conduct Project Selection Methods
C is correct. It describes operations—an ongoing function of an organization. Projects
have a definite ending, while operations will continue longer than the project’s duration.
A, B, and D are incorrect because they are legitimate reasons for projects to be initiated.
Q2: Initiating the Project
2. You are the project manager for your organization. Your management team is
determining which project should be initiated based on the present value of two projects.
Project A will be worth $750,000 in three years. Project B will be worth $478,000
in two years. What is the present value of Project A if the interest rate is 6
percent?
A. $630,000
B. $45,000
C. $710,000
D. Zero
Answer: A
Hint: Present value needs division.
Study Guide Objective: Conduct Project Selection Methods
A is correct. It uses the formula of FV/(1.06)3 to find the present value.
B, C, and D are all incorrect calculations for the present value.
Q3: Initiating the Project
3. A group of executives, subject matter experts, stakeholders, and managers that
convene to ask questions about a potential project, its value, and likelihood of success
to determine which projects should be initiated is called what?
A. A change control board
B. A project steering committee
C. A murder board
D. A technical review board
Answer: C
Hint: It’s the death of many potential projects.
Study Guide Objective: Conduct Project Selection Methods
C is correct. Murder boards are a method that management can use to determine which
project is most likely to succeed.
A is incorrect because a change control board evaluates proposed changes to an existing
project. B is incorrect because a project steering committee may be used to help the
project manager make decisions within an existing project. D is incorrect because
a technical review board, similar to a change control board, reviews technical changes
to an existing project.
Q4: Initiating the Project
4. As a PMP candidate, you should recognize the different methods an organization
can use to select projects. Benefits comparison is the most common approach to select
projects, but constrained optimization, a more specialized approach to project selection,
is also used by organizations. Which one of the following is an example of constrained
optimization?
A. Net present value
B. Future value
C. Benefit/cost ratios
D. Linear programming
Answer: D
Hint: It’s a mathematical model.
Study Guide Objective: Conduct Project Selection Methods
D is correct. Linear programming is a mathematical model—an example of constrained
optimization.
A, B, and C are incorrect. They are examples of benefit comparisons.
Q5: Initiating the Project
5. You are the project manager for the creation of a new warehouse in Knoxville,
Tennessee. You and the project team are creating the scope statement and are evaluating
the function, purpose, and activities that will take place within the warehouse to
help the project customer gather all of the requirements for the scope. This process
is an example of which one of the following?
A. Expert judgment
B. Product analysis
C. Work breakdown structure creation
D. Scope change control
Answer: B
Hint: You’re examining the deliverable.
Study Guide Objective: Define Scope
B is correct. Product analysis consists of product breakdown and functional analysis.
A is incorrect because expert judgment relies on experts to develop a portion of the
detailed project scope statement. C is incorrect because this is not an example of
the WBS creation. D is incorrect because the scope has not been created yet.
Q6: Initiating the Project
6. You are working with your project team to create the project scope for a web-based
application to gather information on clients. Henry says the web application can be
created with JAVA programming.
Marsha agrees, but insists the application can also be created with ASP technology.
This is an example of which one of the following?
A. Forcing
B. Expert judgment
C. Alternative identification
D. Team storming
Answer: C
Hint: There’s no storm here.
Study Guide Objective: Define Scope
C is correct. Henry and Marsha are proposing different approaches to completing the
project.
A is incorrect because forcing means one person is forcing the decision in their favor.
B is incorrect because Marsha and Henry are contributing ideas, not relying on someone
else to make the decision. D is incorrect because Marsha and Henry are not in a power
struggle for their solution to be selected.
Q7: Initiating the Project
7. During scope definition, Robert, the CEO and stakeholder, demands that the
project obtain customer satisfaction to be successful. What is the danger in this
request?
A. Customer satisfaction is not quantifiable.
B. Customer satisfaction is not known until the project has been paid for.
C. Customer satisfaction is only achieved through measurable quality control metrics.
D. Customer satisfaction is never achieved through projects, but through operations.
Answer: A
Hint: Try to measure customer satisfaction first.
Study Guide Objective: Define Scope
A is correct. It’s the best choice because customer satisfaction is not a quantifiable
metric.
B is incorrect because customer satisfaction is a goal of every project. However,
customer satisfaction is not a quantifiable goal for the project. C is incorrect because
the metrics in themselves don’t achieve customer satisfaction. D is incorrect as customer
satisfaction can be achieved through successful project implementations. Consider
organizations that complete projects for others, such as carpenters and architects.
Q8: Initiating the Project
8. Jerry is the project manager of the NHQ Project for his company. He’s working
with the project sponsor to define the high-level scope statement of the project.
The project scope statement defines many things, including all of the following except
for which one?
A. Project boundaries
B. Product acceptance criteria
C. Project assumptions
D. Lessons learned
Answer: D
Hint: You work on this document once the project is in motion.
Study Guide Objective: Define Scope
D is correct. Lessons learned are not included in the project scope statement. Lessons
learned are created throughout the project to reflect what has, and has not, worked
well in the project.
A is incorrect because project boundaries are included in the project scope statement.
B is incorrect because the product acceptance criteria are included in the project
scope statement. C is also incorrect because project assumptions are included in the
project scope statement.
Q9: Initiating the Project
9. Beth is a project manager for her organization and she’s just been assigned
a new project. This project has a deadline of May 15 and a budget of $250,000. A project
with a budget that must not exceed $250,000 is an example of which one of the following?
A. Assumption
B. Risk
C. Management discretion
D. Constraint
Answer: D
Hint: It restricts.
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
D is correct. A constraint is anything that limits the team’s options. Note that the
deadline of May 15 is also an example of a constraint.
A is incorrect because an assumption is anything believed to be true, but not proven
to be true. B is incorrect because risk is a potential event that has a positive or
negative effect on the project’s outcome. C is incorrect because this team is not
applicable.
Q10: Initiating the Project
10. Stephen is the project manager of a construction project. He has written into
his project plan that the project work be completed during the summer months because
the weather is typically better for construction than in winter months. This decision
is an example of which one of the following?
A. Management reserve
B. Assumption
C. Constraint
D. Project risk
Answer: B
Hint: Can you prove it?
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
B is correct. An assumption is something that you cannot prove to be true, such as
the summer weather, but you believe it to be true.
A is incorrect because management reserve describes a portion of time allotted for
schedule overruns within the project work. C is incorrect because a constraint limits
the project team’s options. D is incorrect because a project risk is an uncertain
event that may have a negative or positive impact on the project’s outcome.
Q11: Initiating the Project
11. You and the project sponsor are working together to create a project scope statement.
The project sponsor has concerns about the demand for safety for the electrical requirements
for the project work. The concerns about safety should be documented as which one
of the following?
A. Initial risk
B. Cost of quality
C. Product requirement
D. Assumption
Answer: A
Hint: Shocking.
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
A is correct. The concerns surrounding the electrical work describe a risk. This is
an example of a pure risk because this dangerous activity can only have negative outcomes
if someone is injured. An investment, such as purchasing faster computer equipment,
is a business risk because it can have a positive or negative outcome.
B is incorrect because the cost of quality describes the expense to ascertain the
expected quality. C is incorrect because a product requirement describes the requirements
the project must adhere to. D is incorrect because an assumption is when something
is assumed but not proven. Assumptions can become risks, but this is not the best
answer in this scenario.
Q12: Initiating the Project
12. As a project manager, you have to document the constraints within your project
team. All projects have the Triple Constraints of Project Management, which is made
up of which three factors?
A. Time, cost, and scope
B. Time, cost, and quality
C. Cost, schedule, and stakeholders
D. Time, scope, and quality
Answer: A
Hint: It’s the Iron Triangle of project management.
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
A is correct. Time cost and scope are the Triple Constraints of Project Management.
B, C, and D are incorrect because none of these define the Triple Constraints.
Q13: Initiating the Project
13. You are the project manager of a home construction project. You are interviewing
the homeowners to determine their wants and needs for the home construction. You are
discussing, room by room, what they’d like in their home. This long process is called
what?
A. Risk analysis
B. Quality determination
C. Scope creation
D. Stakeholder analysis
Answer: D
Hint: You cannot do this alone.
Study Guide Objective: Identify and Perform Stakeholder Analysis
D is correct because the question describes stakeholder analysis. Interviewing the
project stakeholders is a common stakeholder analysis activity to promote stakeholder
engagement.
A is incorrect because risk analysis involves determining the impact of the risk events.
B is incorrect because this term is not applicable to the question. C is incorrect
because stakeholder analysis contributes to scope creation, but it is not scope creation
of itself.
Q14: Initiating the Project
14. Benjamin’s project is to build a new bridge over a small creek. The government
leaders want the bridge to be completed as soon as possible because of the economic
impact the construction will have on the businesses in the community. An environmental
group, however, has concerns that the bridge will disrupt the nature and ecological
factors surrounding the creek. The environmental group is demanding additional testing,
surveys, and analysis before the project can continue. The environmental group is
which one of the following in this instance?
A. Stakeholder
B. Positive stakeholder
C. Negative stakeholder
D. Risk owner
Answer: C
Hint: They are not risky.
Study Guide Objective: Identify and Perform Stakeholder Analysis
C is correct. The environmental group is a negative stakeholder because their concerns
may impede the success and progress of Benjamin’s project.
A is incorrect because it is too vague. A stakeholder is anyone who has an interest
in the project’s outcome and may be affected by the project work. B is incorrect because
a positive stakeholder wants the project to move forward as quickly as possible. D
is incorrect because a risk owner is a person that owns and is responsible for a project
risk.
Q15: Initiating the Project
15. You must identify and perform stakeholder analysis. Key project stakeholders
always include all of the following except for which one?
A. Project manager
B. Customer/user
C. Performing organization
D. Vendor
Answer: D
Hint: You don’t always have one of these.
Study Guide Objective: Identify and Perform Stakeholder Analysis
D is correct because projects don’t always have vendors. This is a good example of
a test question that doesn’t seem fair. Vendors can be key stakeholders in the project,
but you may not always have a vendor. You will always have a project manager, a customer
or user of the project’s outcome, and a performing organization. By process of elimination,
the only stakeholder you won’t always have is a vendor. Watch out for these types
of questions on your PMP exam.
A is incorrect because the project manager is always a key stakeholder. B is incorrect
because the customer/user is always a key stakeholder. C is incorrect because the
performing organization is always a key stakeholder.
Q16: Initiating the Project
16. Sarah, the CIO, wants to know why you have requested so many meetings with the
users of the software your project is creating. While she acknowledges that the users
are stakeholders, she doesn’t understand why you believe these stakeholders should
be involved so much during the initiation phase of the project. Why should the stakeholders
be involved now?
A. Involving the customers and other stakeholders improves project performance.
B. Involving the customers and other stakeholders is part of stakeholder engagement.
C. Involving the customers and other stakeholders reduces project risk.
D. Involving the customers and other stakeholders is needed to obtain project sponsorship.
Answer: B
Hint: Think customer buy-in.
Study Guide Objective: Identify and Perform Stakeholder Analysis
B is correct. Involving the stakeholders and customers will increase the probability
of shared ownership, deliverable acceptance, and satisfaction. This is an ongoing
component of stakeholder engagement and it aids in maintaining interest and support
of the project.
A is incorrect because there is no guarantee that it will improve project performance.
C is incorrect because stakeholder participation will not reduce project risk. D is
incorrect because stakeholder participation during initiation is not needed for project
sponsorship.
Q17: Initiating the Project
17. Eric is the project manager for his organization and he’s been working on drafting
the project charter. Beth Ann, a project team member, asks why Eric needs to create
the charter at all if everyone already knows this project is going to happen. What
is the purpose of the project charter?
A. It allows the project manager to assign the project team to work.
B. It assigns authority to the project manager.
C. It authorizes the project.
D. It identifies the constraints and autonomy of the project manager.
Answer: C
Hint: You can’t have a project without a charter.
Study Guide Objective: Develop Project Charter
C is correct. The project charter authorizes the project. Even in scenarios where
the project is going to happen, a project charter is needed to name the project manager,
authorize the project manager to use the project resources, and communicate the backing
and support of the project sponsor.
A is incorrect. The work authorization system allows the project manager to assign
the project team to work. B is not the best choice for the question. While the project
manager does receive authority over some of the project resources, the best choice
is that the project is authorized to exist in the organization. D is an incorrect
statement about the project charter.
Q18: Initiating the Project
18. Eric is the project manager for his organization and he’s been working on drafting
the project charter. In this case, Eric needs to define who will issue the project
charter since he’s the person writing it. Who issues the project charter?
A. The project manager
B. The project sponsor
C. The project customer
D. The project champion
Answer: B
Hint: It’s not the champ.
Study Guide Objective: Develop Project Charter
B is correct because the project sponsor issues the charter. The project charter is
signed and issued by an entity in the organization that has the power to authorize
the project manager to utilize the needed resources for the project to be successful.
A is incorrect. The project manager doesn’t issue the project charter. The project
manager doesn’t, in most cases, have authority over all of the resources (people,
facilities, equipment) the project will need. C is incorrect because the customer
may demand the project, but they don’t issue the charter. D is not a valid option.
The project champion is a stakeholder that may be “cheering” the project onward, but
often this person isn’t the project sponsor.
Q19: Initiating the Project
19. The project charter should always address all of the following except for which
one?
A. The project purpose
B. The assigned project manager and authority level
C. The summary budget
D. Project team members
Answer: D
Hint: It doesn’t exist just yet.
Study Guide Objective: Develop Project Charter
D is correct. Project team members are not identified in the project charter.
A is incorrect because the project charter does identify the project purpose. B is
incorrect because the project does identify the project manager and the authority
level. C is incorrect because the summary budget is identified.
Q20: Initiating the Project
20. You are the project manager of the GHQ Project for your company.
As part of project initiation, you need to identify and analyze the project stakeholders.
Management recommends that you utilize a salience model as part of this activity.
What three components are measured in a salience model?
A. Power, urgency, and legitimacy
B. Power, interest, and legitimacy
C. Power, impact, and legitimacy
D. Power, urgency, and impact
Answer: A
Hint: There’s power, but not impact.
Study Guide Objective: Obtain Project Charter Approval
A is correct. The salience model typically uses three circles to map out stakeholders’
power, urgency, and legitimacy in the project.
B is incorrect because the salience model only uses the characteristics of power,
urgency, and legitimacy over the project decisions and objectives. C is incorrect
because the salience model only uses the characteristics of power, urgency, and legitimacy
over the project decisions and objectives. D is incorrect because the salience model
only uses the characteristics of power, urgency, and legitimacy over the project decisions
and objectives.
Q21: Initiating the Project
21. Your organization completes projects for others. Which one of the following
documents serves as input to project charter creation and approval?
A. Project calendar
B. Project constraints
C. Contract
D. Risk matrix
Answer: C
Hint: You’re a vendor.
Study Guide Objective: Obtain Project Charter Approval
C is the best answer because contracts are needed when you’re completing projects
for other organizations. Contracts, also called agreements for internal projects,
should define all of the expectations for all parties involved in the contracted project
work. There are five inputs to consider for a project charter: project statement of
work, business case, agreements, enterprise environmental factors, and organizational
process assets.
A is incorrect because calendars are not an input to the project charter. B is incorrect
because constraints are not an input to the project charter. D is incorrect as the
risk matrix has likely not been created yet.
Q22: Initiating the Project
22. The project management team is creating the project charter and they are relying
on several tools to help them. They want the project charter to be accurate to ensure
its approval. Which one of the following is not a tool or technique that should be
used when creating the project charter?
A. Project product analysis
B. Project selection methods
C. Project management methodology
D. Expert judgment
Answer: A
Hint: Not the thing.
Study Guide Objective: Obtain Project Charter Approval
A is correct because product analysis is not a tool or technique for the project charter
development.
B is incorrect because project selection methods are acceptable tools. C is incorrect
because project management methodology is an acceptable tool. D is incorrect because
expert judgment is an acceptable tool.
Q23: Planning the Project
23. You are the project manager of the BDS Project. Your project must be completed
by October 13 and cannot exceed $250,000. October 13 is an example of which one of
the following?
A. A constraint
B. An early finish for the project
C. A scheduled completion date
D. An assumption
Answer: A
Hint: You must.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
A is correct. The project must be completed by October 13th, so this date reflects a constraint on the project.
B is incorrect because the project may be able to finish earlier than October 13.
We do not have enough information to determine if this is the earliest the project
can be completed. C is incorrect because the project could be scheduled to finish
earlier than October 13. The constraint is that the project be finished by October
13. D is incorrect because an assumption is something believed to be true, but not
proven to be true.
Q24: Planning the Project
24. Mari, the project manager, has allotted two weeks for travel delays within her
project. She has no proof that travel days will happen. This is an example of what?
A. Change control
B. Constraint
C. Ineffective project management
D. Assumption
Answer: D
Hint: You can’t prove it.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
D is correct. Mari has made an assumption that there will be travel delays within
her project. Assumptions must be tested for their correctness. An assumption that
proves false can become a risk for the project success.
A is incorrect because this is not an example of change control. B is incorrect because
constraints are things that limit the project team’s options. C is incorrect because
this is an example of effective project management.
Q25: Planning the Project
25. You have scheduled your project team to work full-time on the project work of
building a brick wall during the week of August 16. You have allotted six hours of
labor per worker for each day of the week. The six hours of labor is considered what?
A. An assumption because you believe the project team will only contribute six hours
of labor each day to the construction.
B. An assumption because the labor union will allow the project team members to work
only six hours each day.
C. An assumption because you have historical information to base your estimate on.
D. An assumption because you know the building inspector will be onsite for two hours
each work day.
Answer: A
Hint: It’s your belief.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
A is correct because you believe the project team will only contribute six hours,
but you haven’t proven this to be true. The project team could work more, or less,
than six hours per day.
B is not a valid choice because if it’s true that the labor union will only allow
six hours of work, then it would be a constraint. C is incorrect because if you have
historical information to base your time estimate on, then it’s factual rather than
an assumption. D is incorrect because if you know the building inspector will be onsite
for two hours each day, this is a constraint.
Q26: Planning the Project
26. Assumptions must be identified and documented as part of project planning. Which
one of the following is an assumption?
A. The project must be completed by November 1.
B. The project must cost less than $250,000.
C. The project must be completed in the summer because the weather is better.
D. The project must be completed by the end of the year because of a new regulation.
Answer: C
Hint: Wait for the sunshine.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
C is the best choice because weather is a typical example of an assumption.
A is incorrect because this is an example of a time constraint. B is incorrect because
this is an example of a cost constraint. D is incorrect because this is an external
constraint.
Q27: Executing the Project
27. The project team is obviously struggling over who will be leading the project.
This happens in which phase of team development?
A. Forming
B. Storming
C. Norming
D. Performing
Answer: B
Hint: Boomers.
Study Guide Objective: Improve Team Performance
B is correct because storming is when the project team moves through power struggles
about who’s in charge of the project.
A is incorrect because forming happens when the team first meets. C is incorrect because
this happens once the project team settles into their roles. D is incorrect because
this happens once the project team focuses on getting the project work completed.
Q28: Planning the Project
28. You are the project manager for a new construction project. There are several
building codes that your project team must adhere to during the design and construction
phases of your project. The building codes are examples of which one of the following?
A. Standards
B. Government-imposed requirement
C. Quality management concern
D. Scope
Answer: B
Hint: You must adhere to the codes.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
B is the best choice because building codes are an example of a government-imposed
requirement.
A is incorrect. Standards are optional, regulations are not. C is incorrect. While
quality may be affected by adherence to the building code, B
answers the question more accurately. D is incorrect because scope does not answer
the question.
Q29: Planning the Project
29. The project scope statement includes constraints, assumptions, and requirements.
All of the following are examples of constraints except for which one?
A. A preset project budget
B. A project that has been completed before
C. A project due date as defined by management
D. A project that requires a mechanical engineer for the month of
January
Answer: B
Hint: It’s not a requirement.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
B is the best choice because this describes historical information rather than a constraint.
A is incorrect because a preset project budget describes a project constraint. C is
incorrect because a due date is an example of a project constraint. D is incorrect
because it describes a resource constraint for the mechanical engineer.
Q30: Planning the Project
30. You are the project manager of the XHG Project. Your manager has determined
that the project must be completed by January 31. In order to meet this constraint,
what will you and the project team likely need to do?
A. Work overtime
B. Add more project team members
C. Schedule backward from the completion date
D. Require additional funds
Answer: C
Hint: Start at the end.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
C is the best answer. An imposed completion date will likely require you and the project
team to schedule from the completion date.
A is incorrect. There’s no evidence you must work overtime to complete the project.
B is incorrect because there’s no evidence you will need additional labor to complete
the project by the schedule date. In addition, the work may not be affected by the
added labor (considered activities of fixed duration). D is incorrect. The scheduled
completion date doesn’t necessarily correlate to more funds to complete the project.
Q31: Planning the Project
31. It is important for the project manager to identify the organizational structure
she is operating within to better plan the project. Which organizational structure
provides the least amount of power for the project manager?
A. Functional
B. Weak Matrix
C. Strong Matrix
D. Projectized
Answer: A
Hint: It’s no “fun” for the project manager.
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
A is correct because the Functional structure provides the least amount of authority
for the project manager.
B is incorrect because the Weak Matrix provides more power than the Functional Structure,
but still limits the project manager’s authority. C is incorrect because the Strong
Matrix provides the project manager more power than the functional manager. D is incorrect
because the Projectized structure provides the most power for the project manager.
Q32: Planning the Project
32. Project managers may need to work with union labor as part of the project execution.
This requires planning and consideration of all the union agreements, rules, and restrictions.
A contract between the performing organization and a union is an example of which
one of the following?
A. Stakeholder
B. Collective bargaining agreement
C. Assumption
D. Management
Answer: B
Hint: More than just a stakeholder.
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
B is correct because the contract between the performing organization and the union
is called a collective bargaining agreement.
A is incorrect because the union is a stakeholder if they’re involved with the project
but their contract is not. C is incorrect because the contract may list constraints,
but not assumptions. D is incorrect because management is not a valid answer.
Q33: Planning the Project
33. You are managing a project in a matrix-structured organization. You would like
to create a chart that depicts each department’s contributions to the project. Which
one of the following can best accomplish this goal?
A. Work breakdown structure
B. Project network diagram
C. Text-oriented organization chart
D. Organizational breakdown structure
Answer: D
Hint: It organizes the work.
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
D is correct because the organizational breakdown structure shows the hierarchy of
the organization and lists each department’s contributions to the project.
A is incorrect because the WBS lists the deliverables of the project, not which department
will contribute to the creation of the WBS deliverables. B is incorrect because the
project network diagram shows the workflow of activities within the project. C is
incorrect because a text-oriented organization chart does not show department-by-department
contributions to the project work.
Q34: Planning the Project
34. You would like to create a matrix chart that shows each team member’s involvement
with each activity. What is this chart known as?
A. The RACI chart
B. The Pareto chart
C. The Roles and Responsibility Matrix
D. The HR Interaction chart
Answer: A
Hint: Race to the finish.
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
A is correct because a RACI chart depicts the roles of each team member as Responsible,
Accountable, Consult, and Inform.
B is incorrect because a Pareto chart shows categories of failure and is used with
quality control measures. C and D are incorrect because both of these terms are not
applicable.
Q35: Planning the Project
35. A major component of project planning and management is the project’s work breakdown
structure. The smallest item in the WBS is called what?
A. A leaf object
B. A task
C. A work package
D. A deliverable
Answer: C
Hint: No rakes needed.
Study Guide Objective: Create the WBS
C is correct. The smallest item in the WBS is called the work package.
A is incorrect because this is not a valid term. B is incorrect because a task is
the actual work, not the smallest item in the WBS. D is incorrect because a deliverable
does not accurately define what the smallest item in the WBS is.
Q36: Planning the Project
36. What should be implemented when determining how detailed the decomposition of
the deliverables in the WBS should be?
A. The 8/80 rule
B. The law of diminishing returns
C. The priority of the project
D. The timetable to create the WBS
Answer: A
Hint: It is a heuristic.
Study Guide Objective: Create the WBS
A is correct because the 8/80 rule states that the work package should not equate
to less than eight hours of labor to create and no more than 80 hours of labor to
create.
B is incorrect because the law of diminishing returns describes the effect of added
labor and the return for that labor. C is incorrect because the priority of the project
doesn’t affect the decomposition of the project. D is incorrect because the timetable
to create the WBS does not dictate the level of detail required for decomposition
Q37: Planning the Project
37. Management would like for you to identify each deliverable within the WBS with
a number. The numbering system you should use with your WBS is called what?
A. Chart of accounts
B. Bill of materials
C. Code of accounts
D. WBS dictionary
Answer: C
Hint: It’s not a secret.
Study Guide Objective: Create the WBS
C is correct. The code of accounts is used to provide a hierarchical structure for
the deliverables identified in the WBS.
A is incorrect because the chart of accounts is an accounting tool for assigning predefined
costs for deliverables such as cost per square foot, cost per hour, or cost per unit.
B is incorrect because a bill of materials identifies all of the materials needed
to create the things identified in the WBS. D is incorrect because the WBS dictionary
defines what each work package in the WBS is and its associated time and cost estimate.
Q38: Planning the Project
38. The difference between what was planned and what was experienced in the project
is called a project variance. Project variances are often compared against the project
baselines, such as time, cost, and scope. What document serves as the scope baseline?
(Choose the best answer.)
A. The summation of the cost and time baselines
B. The WBS
C. The project charter
D. The project scope
Answer: B
Hint: Equates to the scope.
Study Guide Objective: Create the WBS
B is correct. The WBS is the scope baseline. Technically, the WBS, the WBS dictionary,
and the detailed project scope are the scope baseline.
A is incorrect because the time and cost baselines do not reflect the scope. C is
incorrect because the project charter does not capture all the deliverables the project
will create. D is incorrect because the project scope is decomposed into the WBS.
The WBS, in effect, reflects the entire project scope.
Q39: Planning the Project
39. Mary is the project manager of the GHQ Project. Her project is part of a program
in her organization. Thomas is the program manager,
while Joan is the project sponsor. Who creates the WBS?
A. The project manager
B. The project sponsor
C. The project team
D. The program manager
Answer: C
Hint: It’s not a solo activity.
Study Guide Objective: Create the WBS
C is correct. The project team creates the WBS.
A is incorrect because the project manager doesn’t complete the WBS alone. B is incorrect
because the project sponsor doesn’t complete the WBS. D is incorrect because the program
manager doesn’t create the WBS for the individual projects within the program. The
WBS creation is the responsibility of the project manager and the project team.
Q40: Planning the Project
40. The process of breaking down the project scope into the WBS is called what?
A. Progressive elaboration
B. Rolling wave planning
C. WBS composition
D. Work structure
Answer: A
Hint: No surfing.
Study Guide Objective: Create the WBS
A is correct because progressive elaboration means developing in steps and continuing
in increments, as in the WBS creation.
B is incorrect because rolling wave planning allows for ebb and flow in planning.
C and D are incorrect because both of these terms are not valid.
Q41: Planning the Project
41. Holly Ann is the project manager of the GVF Project, which is similar to the
HGF Project she just completed. She and the project team are about to begin creating
the WBS for the GVF Project and she would like to use the WBS from the HGF Project
to create the current WBS. This is an example of which one of the following?
A. Top-down estimating
B. Historical information
C. Poor project management
D. WBS template
Answer: D
Hint: It’s like a cookie cutter.
Study Guide Objective: Create the WBS
D is correct because when Holly uses a previous project’s WBS to create the current
project’s WBS, she is using a template.
A is incorrect because she is not estimating at this point in the project. B is incorrect
because while this may be a loose example of historical information, WBS template
answers the question more accurately. C is incorrect because this is not an example
of poor project management.
Q42: Planning the Project
42. You are the project manager of the NHH Project and are working with your project
team to create the WBS. One portion of the WBS cannot be decomposed until later in
the project. You have decided to wait until more details become available about the
element and to decompose the deliverable at that point. This is sometimes called what?
A. The WBS template
B. Rolling wave planning
C. Iterative WBS creation
D. Scope creep
Answer: B
Hint: Surf’s up!
Study Guide Objective: Create the WBS
B is correct. This approach is sometimes called rolling wave planning.
A is incorrect because this is not an example of a WBS template. C is incorrect because
this term is not valid. D is incorrect because this is not an example of scope creep.
Q43: Planning the Project
43. In most projects, change is inevitable. Change for time, cost, scope, and even
contracts must be captured, analyzed, and incorporated into the project plan. What
system controls changes within a project?
A. Change control system
B. Change control board
C. Cost change control system
D. Change approval system
Answer: A
Hint: Read the question.
Study Guide Objective: Develop Change Management Plan
A is correct. The change control system controls changes to the project.
B is incorrect because the change control board may be used as part of the change
control system. C is incorrect because costs may be affected by the changes, but there
is no cost change control system. D is incorrect because this term is not valid.
Q44: Planning the Project
44. Which system is responsible for identifying and documenting the functional and
physical characteristics of a product or component that a project is creating?
A. The requirements gathering process
B. Stakeholder analysis
C. The planning process group
D. The configuration management system
Answer: D
Hint: It is a system.
Study Guide Objective: Develop Change Management Plan
D is correct. The configuration management system is responsible for identifying and
documenting the functional and physical characteristics of a product or component
that a project is creating.
A is incorrect because the requirements gathering process does not fully answer the
question. B is incorrect because stakeholder analysis does not complete this function.
C is incorrect because the planning process group is too broad to fully answer the
question.
Q45: Planning the Project
45. Because change can have a significant impact on a project’s success, there must
be a documented approach to change management for the project scope. Which plan documents
the project scope change control system?
A. The project management plan
B. The project scope management plan
C. The change control system
D. The risk response plan
Answer: B
Hint: Not risk.
Study Guide Objective: Develop Change Management Plan
B is correct. The Project scope management plan documents the project scope change
control system.
A is incorrect because it is too broad and does not answer the question as completely
as B. C is incorrect because this is the system for managing changes. D is incorrect
because this documents risk responses.
Q46: Planning the Project
46. You have hired another company to complete a project for you. You would like
to change some details in the project scope which will affect the contract between
you and the vendor. Which system would manage these changes?
A. The schedule change control system
B. The cost change control system
C. The procurement management system
D. The scope change control system
Answer: D
Hint: Control the project scope first.
Study Guide Objective: Develop Change Management Plan
D is correct. Even changes to the contracted work must flow through the scope change
control system.
A is incorrect because the schedule change control system is invoked if there are
changes to the schedule. The question does not define if the changes will affect the
schedule or not. B is incorrect because the cost change control system is invoked
if there are changes to the cost. The question does not define if the changes will
affect the costs or not. C is incorrect because it does not fully answer the question.
Q47: Planning the Project
47. A change has been proposed to the project scope. You have routed the change
through the change control system as planned. You need to examine cost, time, quality,
human resources, communications, risks, and procurement when examining the proposed
change. Your manager wants to know why all of these areas must be examined. In regard
to the proposed change, what are you doing by examining each project area?
A. Configuration management
B. Integrated change control
C. Scope change control
D. Effective project management
Answer: B
Hint: It all works together.
Study Guide Objective: Develop Change Management Plan
B is correct. This is part of integrated change control.
A is incorrect because configuration management doesn’t fully answer the question.
C is incorrect because scope change control is part of integrated change control.
In this question, you are examining the impact of a change on all knowledge areas.
D is incorrect because while this may qualify as effective project management procedures,
integrated change control more fully answers the question.
Q48: Planning the Project
48. The configuration management system accomplishes all of the following except
for which one?
A. Provides opportunities to validate and improve the project by considering the impact
of each change
B. Provides opportunities for the project management team to communicate all changes
to the stakeholders
C. Provides a method to identify and request changes to established baselines
D. Provides a method for project management processes to be removed or added to the
project
Answer: D
Hint: All of these already exist.
Study Guide Objective: Develop Change Management Plan
D is correct because the configuration management system does not provide a method
for project management processes to be removed or added to the project.
A, B, and C are incorrect because all of these statements are true.
Q49: Planning the Project
49. You are the project manager of a new home construction project. You are inspecting
the home as part of quality control. You’ve noticed faulty work during one of your
quality control inspections. What is needed?
A. Project scope change control for the new work
B. Recommended defect repair for the incorrect work
C. Change request for the additional work
D. Recommended corrective actions
Answer: B
Hint: Fix it.
Study Guide Objective: Develop Change Management Plan
B is correct. You typically find faulty work during quality control inspections and
then you make recommendations to fix the problems.
A is incorrect because you are not changing the project scope. C is incorrect because
you are not requesting for the project scope to change with additional work. D is
incorrect because you are not making actions to bring future results back into alignment
with the project plan. You are fixing errors—thus, this is defect repair.
Q50: Planning the Project
50. A project manager is completing a project to build a new condo. He needs to
confirm that any field drawings by the architect match the office drawings that will
go into the project archives. Which project management system ensures that changes
to the project scope and the product scope are thoroughly considered and documented?
A. The change control system
B. The integrated change control process
C. The configuration management system
D. The communication management system
Answer: C
Hint: Go configure.
Study Guide Objective: Develop Change Management Plan
C is correct. The configuration management system ensures that requested changes to
the project scope and the product scope are thoroughly considered and documented.
A is incorrect because it does not fully answer the question. B is incorrect because
the configuration management system processes happen before integrated change control.
D is incorrect because this term is not applicable to this scenario.
Q51: Planning the Project
51. Not all risks are negative, and some negative risks are worth accepting into
the project based on the impact, the possible outcomes, and the perceived benefits
that the risk may bring. What terms describes a person’s or organization’s willingness
to accept risk?
A. Utility function
B. Risk exposure
C. Mitigation
D. Risk probability
Answer: A
Hint: It’s based on Bernoulli’s curves.
Study Guide Objective: Identify Risks and Define Risk Strategies
A is correct. Utility function is a term used to describe a person’s or organization’s
willingness to accept risk. The lower the utility function, the more risk response
planning is needed.
B is incorrect because risk exposure is based on each project. C is incorrect because
mitigation is one response to a risk event. D is incorrect because risk probability
describes the likelihood of a risk event actually happening.
Q52: Planning the Project
52. Risk analysis is an iterative process within any project. It sometimes helps
to classify and break down the risk events to provide a deeper understanding of them.
Which structure lists the categories and subcategories for risks within a project?
A. The work breakdown structure
B. The organizational breakdown structure
C. The risk breakdown structure
D. The bill of materials structure
Answer: C
Hint: It’s about risk.
Study Guide Objective: Identify Risks and Define Risk Strategies
C is correct. A risk breakdown structure illustrates the risk categories within a
project.
A is incorrect because the WBS shows the decomposition of the project scope. B is
incorrect because the OBS shows the structure of an organization, not the risks within
the organization. D is also incorrect because the BOM describes the materials needed
in order to build the project scope.
Q53: Planning the Project
53. One of the most important processes of risk management is risk identification.
When does the risk identification conclude?
A. With the planning process group
B. With the execution process group
C. With the closing process group
D. When the project customer deems all the risks have been identified.
Answer: C
Hint: It ain’t over until it’s over.
Study Guide Objective: Identify Risks and Define Risk Strategies
C is correct because risk identification happens throughout the project life cycle.
A is incorrect because risk identification happens throughout the project. B is incorrect
because risk identification is iterative and happens throughout the project. D is
also incorrect. The project customer may not know enough about the project’s discipline
to understand when all of the risks have been identified. Risk identification is iterative
and happens throughout the project.
Q54: Planning the Project
54. You are the project manager of the Highway Automation Project and are facilitating
the risk identification process with your project team and other key stakeholders.
You have encouraged the participants to identify as many project risks as possible.
All of the following are acceptable risk identification techniques except which one?
A. The Delphi Technique
B. SWOT analysis
C. Qualitative analysis
D. Root cause analysis
Answer: C
Hint: This happens later.
Study Guide Objective: Identify Risks and Define Risk Strategies
C is correct. Qualitative analysis happens after risk identification.
A, B, and D are incorrect because all of these are risk identification methods.
Q55: Planning the Project
55. Risk identification and analysis includes careful consideration of project requirements,
scope objectives, the nature of the project work, and the project documentation. Based
on this information, which one of the following statements must be examined for risk?
A. The product requires a foil stamp of .32 millimeters.
B. The product requires oak beams.
C. The product must be constructed during the summer months due to the expected good
weather.
D. The product must be approved by a building inspector before August
1.
Answer: C
Hint: Assumptions.
Study Guide Objective: Identify Risks and Define Risk Strategies
C is correct because all assumptions must be tested.
A is incorrect because this is not an assumption, but a requirement. Both B and D
are incorrect because these are project requirements.
Q56: Planning the Project
56. It’s difficult to capture and analyze all risks that may affect the project
objectives. One approach is using the risk register. What exactly is the risk register?
A. It’s a central database for all risks within an organization.
B. It’s a listing of all risks that have been identified within a project.
C. It’s a listing of all risks that have been identified and responded to within an
organization.
D. It’s a listing of all risks that must be mitigated within a project.
Answer: B
Hint: Keep it simple.
Study Guide Objective: Identify Risks and Define Risk Strategies
B is correct because the risk register is simply a list of identified risks within
a project.
A, C, and D are incorrect because these statements are not true.
Q57: Planning the Project
57. You have identified a risk within your project dealing with the installation
of the electrical system in a building expansion. You have hired a licensed electrician
to complete this portion of the project. This is what type of risk response?
A. Transference
B. Mitigation
C. Procurement
D. Avoidance
Answer: A
Hint: Choose the best answer, or get someone else to do it.
Study Guide Objective: Identify Risks and Define Risk Strategies
A is correct because whenever you hire someone else to own a risk, you are participating
in risk transference.
B is incorrect. Mitigation is an effort to reduce the probability or impact of a risk
event. C is incorrect because this term is not valid for this scenario. D is incorrect
because you are not avoiding the risk, you’re transferring it.
Q58: Planning the Project
58. There’s a risk that a new law will cause your project to fail. What risk response
can you use for this possible law?
A. Mitigation
B. Transference
C. Exploit
D. Acceptance
Answer: D
Hint: There’s nothing you can do about it.
Study Guide Objective: Identify Risks and Define Risk Strategies
D is correct because the only response you can do is to accept the risk.
A is incorrect because you cannot mitigate the risk. B is incorrect because you cannot
transfer the risk. C is incorrect because you cannot accept the risk.
Q59: Planning the Project
59. You are working with management on the project planning processes. They want
to know why you’re spending time on risk management planning so early in the project
planning. Which one of the following is the best response to management’s concern?
A. All projects have risks.
B. Risk management planning increases the probability of success for the other risk
management processes.
C. Risk management planning must happen before any other planning activities.
D. You feel, as the project manager, that the project has too many risks to be successful.
Answer: B
Hint: Planning is iterative.
Study Guide Objective: Obtain Plan Approval
B is correct because risk management planning does increase the possibility of success
for the risk management processes.
A is incorrect because risk management planning is not about risk identification,
but rather how to approach and conduct risk management activities. C is incorrect
because this statement is not true. D is incorrect because this concern centers on
risk identification and response, not the approach to risk management.
Q60: Planning the Project
60. Management has asked you, the project manager of the KJU Project, to provide
an estimate of the project costs. Their decision to move forward with the project
will be based on your initial estimate. You have just started the project so what
estimate type will you likely provide?
A. Rough order of magnitude
B. Definitive
C. Budget
D. Bottom-up
Answer: A
Hint: It’s rough.
Study Guide Objective: Obtain Plan Approval
A is correct because this early estimate is the rough order of magnitude estimate.
B is incorrect because the definitive can be provided once the WBS has been created.
C is incorrect because the budget is provided once the scope statement has been created.
D is incorrect because the bottom-up is created once the WBS has been created.
Q61: Planning the Project
61. You are hiring another organization to complete a project for your organization.
Which document would include information about performance reporting requirements,
operation transfer issues, and post-project support of the deliverable?
A. Proposal
B. Request for proposal
C. Bid
D. Statement of Work
Answer: D
Hint: There’s no contract yet
Study Guide Objective: Obtain Plan Approval
D is correct because the SOW provides all these elements.
A is incorrect because the proposal does not provide these elements but focuses on
how the solution can be implemented. B is incorrect because the RFP asks the vendor
to provide a proposal. C is incorrect because this document comes from the vendor
to the buyer and is focused on price only.
Q62: Planning the Project
62. You have created the project schedule and management has asked to review the
schedule. They have concerns that your labor estimates may be too aggressive. If management
recommends resource leveling, what will likely happen to your project schedule?
A. Nothing. Only more labor will be added.
B. Nothing. Only more costs will be added.
C. The schedule will take longer to complete.
D. The project duration will increase.
Answer: D
Hint: Resource leveling flattens the resources. Reference: PMP Study Guide, Chapter 6 Study Guide Objective: Obtain Plan Approval
D is correct because resource leveling will typically require the project duration
to increase.
A is incorrect because there is no evidence that more labor is available, approved,
or allowed. B is incorrect because there’s no evidence that more funds will be needed
to complete the project work. C is incorrect because the creation of the schedule
will not necessarily take longer to create. The completion of the project will likely
take longer, however.
Q63: Planning the Project
63. While it’s not a project initiation activity, most projects can benefit from
a project kickoff meeting. What’s the goal of the project kickoff meeting?
A. It introduces the project goal.
B. It allows the project manager, the project team, and the key stakeholders to meet
one another.
C. It allows the project manager to gain commitment from the project team and key
stakeholders for the project.
D. It allows the project manager to facilitate their expert power.
Answer: C
Hint: You want this first.
Study Guide Objective: Conduct Kick-Off Meeting
C is correct because the goal of the kick-off meeting is to gain everyone’s commitment
to the project.
A is incorrect because the project goal is established before the kick-off meeting.
B is incorrect because the project manager has likely already met the project team.
In addition, this is not the goal of the meeting. D is incorrect because this statement
is not valid.
Q64: Planning the Project
64. All of the following are desired outcomes of the project kick-off meeting except
for which one?
A. Provide clarifications on the project goals and objectives.
B. Allow the team and stakeholders to know the points of contact within the project
team.
C. Learn how the current project may interact with other projects.
D. Allow the project team to voice concerns and objections about the project scope.
Answer: D
Hint: No nagging.
Study Guide Objective: Conduct Kick-Off Meeting
D is correct because the kick-off meeting is not the place for this discussion.
A, B, and C are incorrect because all of these are desired outcomes of the project
kick-off meeting.
Q65: Planning the Project
65. All of the following statements are false about the project kick-off meeting
except for which one?
A. The project kick-off meeting is a team-building exercise.
B. Only the project team members should attend the project kick-off meeting.
C. The project kick-off meeting is led by the project sponsor.
D. The project kick-off meeting is held during scope verification.
Answer: A
Hint: The team is there.
Study Guide Objective: Conduct Kick-Off Meeting
A is correct because this is a true statement about the project kick-off meeting.
B, C, and D are incorrect because all of these are false statements about the project
kick-off meeting.
Q66: Planning the Project
66. Management has asked you to create a project kick-off meeting for the GHB Project.
When should the project kick-off meeting happen?
A. When the project manager has the project team assembled for the first time.
B. When the project manager has approved the project plan.
C. When management has approved the initial project plan.
D. At the start of scope verification.
Answer: C
Hint: The plan is needed.
Study Guide Objective: Conduct Kick-Off Meeting
C is correct. The project kick-off meeting happens after the initial project plan
has been approved.
A is incorrect because this does not answer the question as well as C. B is incorrect
because the project manager does not necessarily approve the project plan—management
does. D is incorrect because this is not a valid statement.
Q67: Planning the Project
67. Your organization is partnering with a competing firm in order to complete a
large construction project. You will serve as the project manager in this partnership.
What is this relationship called?
A. Dual-entity project management
B. Dual functional structure
C. Teaming agreement
D. Functional team agreement
Answer: C
Hint: You’re on a temporary, contractual team.
Study Guide Objective: Conduct Kick-Off Meeting
C is correct. When two competing entities partner together to complete a project through
a contractual relationship, it is called a team agreement.
A, B, and D are incorrect because none of these are valid project management terms.
Q68: Planning the Project
68. All of the following are accomplished during the project kick-off meeting except
for which one?
A. The project organization is explained.
B. The project goals are defined.
C. The project objectives are identified.
D. The project risks are examined.
Answer: D
Hint: Not yet.
Study Guide Objective: Conduct Kick-Off Meeting
D is correct because risk does not happen until later in the project planning process.
A, B, and C are incorrect because all of these are true statements about the project
kick-off meeting.
Q69: Executing the Project
69. You are the project manager of the HHA Project for your company. Management
has asked you to present your approach to project execution. Which of the following
defines how the project is executed?
A. The project management plan
B. The work authorization system
C. The project execution process group
D. The project manager
Answer: A
Hint: Not a person.
Study Guide Objective: Execute Tasks Defined in Project Plan
A is correct because the project management plan defines how the project is executed,
monitored and controlled, and closed.
B is incorrect because the work authorization system tracks completed work and allows
scheduled work to begin. C is incorrect because this statement is not valid for this
question. D is incorrect because the project manager doesn’t solely define how the
project is executed, the project team and expert judgment may also contribute.
Q70. Executing the Project
70. While project management planning is essential, planning cannot continue indefinitely.
At some point, the project management team must move into project execution. All of
the following actions are required to execute the project management plan except for
which one?
A. Perform activities to accomplish project objectives.
B. Staff, train, and manage the project team.
C. Manage risks and implement risk response activities.
D. Interact with other project managers.
Answer: D
Hint: This doesn’t have to happen.
Study Guide Objective: Execute Tasks Defined in Project Plan
D is correct because you, the project manager, do not always have to interact with
other project managers to complete the project work. You do always have to complete
choices A, B, and C.
A, B, and C are incorrect because all of these are valid statements.
Q71. Executing the Project
71. You are the project manager of the NGBB Project. Your project team has failed
to complete the work as the project management plan demanded. What action will the
project team now have to perform with your guidance?
A. Quality control
B. Defect repair
C. Peer review
D. Exit interview
Answer: B
Hint: Fix it.
Study Guide Objective: Execute Tasks Defined in Project Plan
B is correct because the project team will have to fix the defects in their work.
A is incorrect because QC is based on inspection. The errors have already been identified
so the project team must fix the errors. C is incorrect because peer review is an
example of QC. The project team must fix the problems. D is incorrect because this
statement is not applicable to the situation. Sorry, but you don’t get to fire your
project team members.
Q72. Executing the Project
72. Harry is the project manager of the HQQ Project. Management has asked him to
report on the project execution and its outcomes. Which one of the following is an
output of project execution?
A. The project charter
B. The cost baseline
C. Change requests
D. Quality control mechanisms
Answer: C
Hint: Read the question before you change your answer.
Study Guide Objective: Execute Tasks Defined in Project Plan
C is correct because change requests are outputs of project execution.
A is incorrect because the project charter is not an output of project execution.
B is incorrect because the cost baseline has been established based on your cost estimates
and the cost budgeting activities. D is incorrect because this is not a valid answer.
Q73. Executing the Project
73. You are the project manager of a large project to install 10,000 fixtures across
a campus. Your project team has been late on their assigned work and you fear the
project will be late. Which one of the following provides forecasting for the project?
A. The program evaluation and review technique
B. The graphical evaluation and review technique
C. Risk analysis
D. The estimate at completion
Answer: D
Hint: EVM.
Study Guide Objective: Execute Tasks Defined in Project Plan
D is correct because the earned value management formula—estimate at completion (EAC)—provides
forecasting for the project success.
A is incorrect because the program evaluation and review technique (PERT) provides
time estimates, not forecasting. B is incorrect because the graphical evaluation and
review technique (GERT) provides branching and loopbacks in network diagramming, not
forecasting. C is incorrect because risk analysis does not provide forecasting to
the level that EAC does.
Q74: Executing the Project
74. You fear that your project team is bloating their time estimates for their assigned
activities. What law addresses bloated estimates?
A. The law of diminishing returns
B. Parkinson’s Law
C. The Pareto principle
D. The contingency reserve
Answer: B
Hint: Work expands.
Study Guide Objective: Execute Tasks Defined in Project Plan
B is correct because Parkinson’s Law states that work will expand to fill the amount
of time allotted to it.
A is incorrect. The law of diminishing returns states that increased labor doesn’t
always guarantee an increase in the yield, and can even diminish an organization’s
overall profit. (See the PMP Study Guide, Chapter 6 for more details.) C is incorrect because the Pareto principle is the 80/20 rule—for
example, 80 percent of your business comes from 20 percent of your customers. D is
incorrect because the contingency reserve is the time allotted for schedule slippage.
(See the PMP Study Guide, Chapter 6.)
Q75: Executing the Project
75. Examine the exhibit. How long will the project take if Activity C in the exhibit
increases by four days?
A. 22
B. 26
C. 16
D. No change because there is float
Answer: B
Hint: There is a change.
Study Guide Objective: Execute Tasks Defined in Project Plan
B is correct because the path ACFHI is the critical path, and with four additional
days of work the duration of the project will increase to 26 days.
A is incorrect because this is the project duration before the change in duration
for Activity C. C is incorrect because this is not valid. D is incorrect because the
duration of the project has increased regardless of the float.
Q76: Executing the Project
76. You are completing a project to build a park in a community. The community is
hosting a meeting where residents can ask you questions and clarify the park’s goals
and features. You insist that the project team attend this meeting. Why should the
project team attend?
A. The team is needed to show the public the expert that you have employed to build
an excellent park for them.
B. The team may have answers to some of the questions the public may ask.
C. The team needs to understand how the project will affect the people and vice versa.
D. The team is needed to see the impact of the project on the community.
Answer: C
Hint: It’s about people.
Study Guide Objective: Ensure Common Understanding and Set Expectations
C is correct because the project team needs to see the impact of their project on
the community and how the community may affect the project outcome.
A is incorrect because this is not a valid reason for having the team present. B is
incorrect because the project manager will be answering the questions from the community.
While the project team may field some questions, this is not the best reason for their
involvement. D is incorrect because this does not answer the question as completely
as choice C.
Q77: Executing the Project
77. You are the project manager of a large international project. Your project team
will be traveling to four different countries to complete the project work. You have
required the project team to complete training regarding the customs, laws, and languages
for each country they will be traveling to. What theory believes that an understanding
of the culture, local language, and colloquialisms allows people to have a better
understanding of the country they’re working in?
A. The Sapir-Whorf hypothesis
B. Ethnocentrism
C. Culture shock
D. Utility function
Answer: A
Hint: It’s not about risk.
Study Guide Objective: Ensure Common Understanding and Set Expectations
A is correct. The Sapir-Whorf hypothesis states that an understanding of the culture,
local language, and colloquialisms allows people to have a better understanding of
the country they’re working in.
B is incorrect because ethnocentrism is when an individual measures another culture
by their own culture. C is incorrect because culture shock describes the initial disorientation
people feel when they first arrive in a foreign culture. D is incorrect because this
describes a person’s willingness to accept risk.
Q78: Executing the Project
78. The project charter must define which one of the following?
A. The risk exposure from not completing the project
B. The quality assurance program the project manager must operate under
C. The work authorization system the project must use
D. Requirements for customer satisfaction
Answer: D
Hint: Not QA.
Study Guide Objective: Ensure Common Understanding and Set Expectations
D is correct because the charter must define the requirements for customer satisfaction.
A, B, and C are incorrect because these are not valid components of the project charter.
Q79: Executing the Project
79. You are the project manager for your organization and you’re working with management
and several subject matter experts to create the project scope statement. Once the
statement is complete, you mention that the key project stakeholders should receive
a copy of the project scope statement. Why should the key stakeholders receive a copy
of the project scope statement?
A. To ensure that all of the key stakeholders have been identified.
B. To ensure that all of the key stakeholders have a common understanding of the project.
C. To ensure that all of the project team members are accounted for among the functional
managers.
D. To ensure that the project manager is identified.
Answer: B
Hint: Understand.
Study Guide Objective: Ensure Common Understanding and Set Expectations
B is correct because the project scope explains what the project will accomplish.
A is incorrect because this is part of communications management. C is incorrect because
this is part of human resources management. D is incorrect because this is accomplished
in the project charter.
Q80: Executing the Project
80. Projects are completed by people and require ground rules to establish clear
expectations. Why must the project team commit to clear guidelines on their behavior
and project participation early in the project?
A. It decreases misunderstandings and increases productivity.
B. It increases the project’s likelihood of success.
C. It decreases storming among the project team members.
D. It increases the project’s risk minimization.
Answer: A
Hint: Two things.
Study Guide Objective: Ensure Common Understanding and Set Expectations
A is correct because early commitment to clear guidelines decreases misunderstandings
and increases productivity for the project team.
B is incorrect. While this may be true, it is not as accurate as A. Risks, lack of
quality, and other influencers could still cause the project to fail. C is incorrect
because storming happens as part of team development. D is incorrect because this
is not a valid statement.
Q81: Executing the Project
81. During the initial project team meeting, the project manager and the project
team established ground rules for how project team meetings would operate. Tina, a
project team member, is not obeying the project rules. Who has the responsibility
to enforce the rules?
A. The project manager
B. The project sponsor
C. The project team
D. The human resources department
Answer: C
Hint: Everyone plays.
Study Guide Objective: Ensure Common Understanding and Set Expectations
C is correct because all project team members share the responsibility to enforce
the rules.
A is incorrect because this does not answer the question fully. The project manager
may lead the enforcement, but the question asks who has the responsibility—and it’s
the entire project team. B is incorrect because the project team has the responsibility.
D is incorrect because the project team has the responsibility. It may, in some instances,
be up to the project manager to escalate the issue through the project sponsor to
human resources.
Q82: Executing the Project
82. Your organization is operating in a functional structure and you’re the project
manager of a newly initiated project. Who has the power on a project team in a functional
organization?
A. The project manager
B. The project sponsor
C. The project team
D. The functional manager
Answer: D
Hint: It’s not fun for the project manager.
Study Guide Objective: Ensure Common Understanding and Set Expectations
D is correct. The functional managers have the power in a functional organization.
A is incorrect because the project manager has little or no authority in a functional
organization. B is incorrect because it’s the functional manager with the power, not
the project sponsor. C is incorrect because the project team does not have the power
in a functional structure.
Q83: Executing the Project
83. Betsy is the project manager of the JGB Project for her organization. She would
like to solicit seven vendors for a price to supply 1000 fixtures for her project.
What type of a document would Betsy issue to the vendors in this scenario?
A. A request for proposal
B. A request for quote
C. A request for information
D. An invitation for a bidders’ conference
Answer: B
Hint: How much?
Study Guide Objective: Implement the Procurement of Project Resources
B is correct because a request for quote only wants a fee for the procured goods or
services.
A is incorrect because a request for proposal wants ideas and suggestions on how to
complete the work. C is incorrect because a request for information is asking the
vendor to provide information on their goods or services. D is incorrect because a
bidder’s conference allows the bidders to meet to ask for clarifications on the provided
statement of work. The question is focused on the price for the fixtures, so a quote
is what’s needed from the vendors.
Q84: Executing the Project
84. Your organization needs to procure training classes. There are many training
companies that you can hire, but you prefer to work with one particular vendor. This
is an example of which market condition?
A. Oligopoly
B. Sole source
C. Single source
D. Qualified seller list
Answer: C
Hint: It’s not the tricky one.
Study Guide Objective: Implement the Procurement of Project Resources
C is correct because a single-source market means they prefer to work with one particular
vendor.
A is incorrect because an oligopoly describes a market condition where the actions
of one vendor affects all of the others (for example, oil, airfare, and software).
B is incorrect because a sole source means there is only one vendor available. D is
incorrect because this is simply a list of vendors that your organization allows you
to do business with.
Q85: Executing the Project
85. Your organization has tasked you with business development. Specifically, they’d
like to bid on government-based contracts. Where will you likely find information
on government contracts that your organization could bid on?
A. Newspapers
B. Historical information
C. Sales channels
D. City hall
Answer: A
Hint: Every Sunday.
Study Guide Objective: Implement the Procurement of Project Resources
A is correct because you’ll often find advertisements in the newspaper of pending
government contracts.
B is incorrect because historical information is activity that has already been completed.
C is incorrect because this is too vague of an answer. D is incorrect because not
all government contracts are available through city hall; consider federal contracts,
military, and other agencies.
Q86: Executing the Project
86. You are trying to determine if you should make or buy a piece of software. If
you create the software, it’ll cost your organization $45,000 to create it and $3,400
each month to support it. A vendor, however, can create the software for $12,000 and
will charge you $0.17 per transaction, per month. According to your calculations,
you’ll have 31,400 transactions each month. What should you do?
A. Hire the vendor if the software will be kept longer than 17 months.
B. Hire the vendor if the software will be replaced within 17 months.
C. Hire the vendor if the transactions will be less than 30,000 per month.
D. Make the software and reduce your monthly expenses by paying the vendor for the
transactions.
Answer: B
Hint: (Build-buy)/(Monthly fee difference)
Study Guide Objective: Implement the Procurement of Project Resources
B is correct because the software will “pay for itself” if it is used 17 months or
longer. This can be calculated by finding the difference of the build and buy, which
is $33,000. Then, you find the difference of the monthly fees, which is $1,938. Divide
the $33,000 by $1,938 and this tells you how long the vendor’s solution will be valid.
If the software is to be kept longer than 17 months, it would be more cost effective
to build the software than to buy it.
A is incorrect because after 17 months the build solution is a better choice. C is
incorrect because the question already explains that the permonth transaction will
be more than 30,000. D is incorrect because this is not a valid choice (especially
for the vendor).
Q87: Executing the Project
87. You are the project manager of a construction project for a new client. The
client has asked that you include an outdoor deck as part of the project—something
your company doesn’t normally do, but you agree to take on this project component
using a contractor to build the seating deck. For this portion of the project, you
would like to use a time and materials contract. What must this contract type have?
A. The signature of the purchasing agent
B. An end date for the procured work
C. A not-to-exceed clause
D. Addendums for each change in the project work
Answer: C
Hint: Not the signature, necessarily.
Study Guide Objective: Implement the Procurement of Project Resources
C is correct because a T&M contract must have a not-to-exceed (NTE) clause, otherwise
the cost can spin out of control.
A is incorrect because while a signature is needed on most contracts, a T&M demands
an NTE clause... or else. B is incorrect because not all T&M contracts require an
end date. D is incorrect because changes can spur new contracts, be covered by the
existing T&M contract, or have addendums.
Q88: Executing the Project
88. You are the project manager of the Home Automation Project. You are uncertain
what the fee will be for wiring the home with bundled cable so you hire a vendor to
examine the home and create an estimate for the SOW you’ve prepared. You’ll use this
estimate from the vendor to measure all other estimates from vendors that want to
bid on the installation of the bundled cable. What is this estimate called?
A. Budget estimate
B. Definitive estimate
C. Good faith estimate
D. Should-cost estimate
Answer: D
Hint: Woulda-coulda.
Study Guide Objective: Implement the Procurement of Project Resources
D is correct because a should-cost estimate, also known as an independent estimate,
is prepared in-house or by a third party. This estimate then measures all other estimates
against it.
A is incorrect because this defines the mid-stage estimate for the entire project.
B is incorrect because this is the most-detailed estimate based on the WBS for the
entire project. C is incorrect because this is not a valid term.
Q89: Executing the Project
89. You have invited seven vendors to create proposals for a portion of your project
work. As part of the invitation, however, the vendor must have a mechanical engineer
on their project team or they cannot offer a proposal. The mechanical engineer requirement
is an example of which one of the following?
A. Resource constraint
B. Resource requirement
C. Screening system
D. Project requirement
Answer: C
Hint: Not a constraint.
Study Guide Objective: Implement the Procurement of Project Resources
C is correct because the requirement to have the mechanical engineer “screens out”
the vendors that do not qualify.
A, B, and D are all incorrect because in this instance the mechanical engineer is
needed to offer a proposal. The question does not say the project requires the mechanical
engineer at all—only to submit a proposal.
Q90: Executing the Project
90. Management would like you, the project manager, to create a chart showing when
resources will be utilized on your project. What chart is management asking you to
create?
A. A Gantt chart
B. A resource histogram
C. A network diagram
D. A Pareto chart
Answer: B
Hint: Not Henry.
Study Guide Objective: Manage Resource Allocation
B is correct because a resource histogram is a bar chart that shows utilization of
resources across time.
A is incorrect because a Gantt chart, from Henry Gantt, is a scheduling tool that
shows project activities across a timeline or calendar. C is incorrect because a network
diagram shows the flow of activities. D is incorrect because a Pareto chart is typically
used in quality control activities and shows categories of failure within a project.
Q91: Executing the Project
91. You are the project manager in a projectized organization. You believe in the
Expectancy Theory. Which one of the following mechanisms will promote and reinforce
desired behavior from your project team?
A. Expert judgment
B. Lectures and motivational speeches
C. Rewards
D. Punishments for poor project performance
Answer: C
Hint: Oh goody!
Study Guide Objective: Manage Resource Allocation
C is correct because rewards and recognition are ideal methods for promoting desired
behavior.
A is incorrect because expert judgment won’t reinforce desired behavior from the project
team. B is incorrect because lectures and motivational speeches are not as effective
as rewards and recognition systems. D is incorrect because there’s no incentive to
do well, only an incentive to not do poorly.
Q92: Executing the Project
92. A project team comprised of people that spend little or no time meeting face
to face is known as what?
A. A dysfunctional project team
B. A non-collocated project team
C. A virtual project team
D. An E-team
Answer: C
Hint: Virtually possible.
Study Guide Objective: Manage Resource Allocation
C is correct because virtual teams are comprised of people that don’t spend much time
working face to face with other project team members.
A and D are incorrect because these terms are not valid. B is incorrect because this
describes a project team that is not all located in one locale.
Q93: Executing the Project
93. You are a project manager consultant for a new project that will utilize a virtual
team. Virtual teams make all of the following possible except for which one?
A. Including people with mobility handicaps
B. Including people that work from home offices
C. Allowing projects to progress that otherwise would have been cut due to travel
expenses
D. Reducing the amount of time dedicated to meetings and communications
Answer: D
Hint: You still have this.
Study Guide Objective: Manage Resource Allocation
D is correct because this is a false statement about virtual teams.
A, B, and C are incorrect because each is a true statement about virtual teams.
Q94: Executing the Project
94. You are the project manager of the KHY Project. This project involves 45 project
team members from across your matrix-structured organization and will last for 18
months. You have requested a central meeting room for communications, project information,
testing equipment, and other project-related activities. This room is called what?
A. A resource request
B. A facility resource request
C. A war room
D. The project headquarters
Answer: C
Hint: You don’t declare it.
Study Guide Objective: Manage Resource Allocation
C is correct because a war room is a meeting room for project support.
A, B, and D are incorrect because these terms are not valid.
Q95: Executing the Project
95. Your project is slipping and you would like to add more labor to complete effort-driven
activities sooner. What is this called?
A. Cost increase
B. Crashing
C. Risk increase
D. Fast tracking
Answer: B
Hint: Kaboom!
Study Guide Objective: Manage Resource Allocation
B is correct because crashing means that the project manager adds resources in efforts
to complete activities faster.
A is incorrect because this is a typical effect of crashing. C is incorrect because
this is a typical effect of fast tracking. D is incorrect because fast tracking allows
phases to overlap.
Q96: Executing the Project
96. You are the project manager for your organization and you’ve told management
that you’ll be using the critical chain method for this project. Management is unaware
of this approach and they want to know more about it. What is the critical chain method?
A. It utilizes just-in-time ordering.
B. It finds the longest path to project completion and allows float on the other activities
in the project.
C. It is a schedule network analysis that accounts for limited resources.
D. It is a project network diagram with the project float exposed.
Answer: C
Hint: Not CPM.
Study Guide Objective: Manage Resource Allocation
C is correct because the critical chain method accounts for limited resources. For
example, a structural engineer may be needed on two concurrent activities, but she
can only work on one activity at a time.
A is incorrect because this scheduling method is not applicable to this scenario.
B is incorrect because this describes the critical path method. D is incorrect because
this is the critical path method.
Q97: Executing the Project
97. Several project team members want to schedule vacation days in July, but you
need to confirm if Jane, a network engineer, has already scheduled her vacation. Which
calendar will tell you, the project manager, if Jane is available on July 17?
A. The resource calendar
B. The project calendar
C. The project schedule
D. The HR calendar
Answer: A
Hint: Jane’s a resource.
Study Guide Objective: Manage Resource Allocation
A is correct because Jane is a resource and resource calendars are specific to each
resource on the project.
B is incorrect because the project calendar determines when project work is allowed.
C is incorrect because the project schedule shows the mapping of the project work.
D is incorrect because this term is not valid.
Q98: Executing the Project
98. You are the project manager of the KJP Project. You, the project team, and the
project sponsor are working together to complete quality management planning. The
stakeholder has compared your current project scope to a recently completed project
that utilized Six Sigma techniques in their project. This is called what?
A. Quality assurance
B. Quality control
C. Statistical analysis
D. Benchmarking
Answer: D
Hint: Comparisons.
Study Guide Objective: Implement Quality Management Plan
D is correct because benchmarking is when one project is compared to another.
A is incorrect because QA is the organization-wide program for quality. B is incorrect
because QC is an inspection to determine the existence of quality. C is incorrect
because statistical analysis is the examination of statistics and production.
Q99: Executing the Project
99. Your project team does not know how to install the new materials you’ll be using
in your project. You hire a trainer to teach the team how to install the project.
The costs of the trainer are described as what?
A. The cost of conformance to quality
B. Sunk costs
C. Team development
D. The cost of doing business
Answer: A
Hint: Got to do it, or else.
Study Guide Objective: Implement Quality Management Plan
A is correct because training is an example of the cost of conformance to quality.
If you don’t train the project team, then quality will suffer.
B is incorrect because sunk costs describes monies spent on project work that has
failed and that cannot typically be recovered. C is incorrect because team development
involves activities to facilitate team cohesion. The costs, in this question, are
not attributed to team development. D is incorrect because this is not an example
of the costs of doing business. These costs are unique to this project.
Q100: Executing the Project
100. You are the project manager of a project that must operate by your organization’s
quality policy. Management has decided to examine your project’s processes to determine
if you are following the quality policy. This review process is known as what?
A. Quality control
B. Quality assurance
C. Quality audit
D. Quality planning
Answer: C
Hint: Looking for proof of compliance.
Study Guide Objective: Implement Quality Management Plan
C is correct because a quality audit examines a project to determine if the project
is complying with an organization’s quality policies.
A is incorrect because QC examines the project work to determine the quality of the
project deliverables. B is incorrect because QA is the company quality policy. D is
incorrect because quality planning constitutes those activities that determine how
the project will adhere to the quality demands of the organization.
Q101: Executing the Project
101. Quality control and quality assurance are needed in every project. Which one
of the following is an example of quality assurance?
A. A Pareto chart
B. A control chart
C. Inspection
D. A Six Sigma program
Answer: D
Hint: Started at Motorola.
Study Guide Objective: Implement Quality Management Plan
D is correct because Six Sigma is a quality assurance program.
A, B, and C are incorrect because each is a quality control tool.
Q102: Executing the Project
102. You are the project manager of the NJQ Project and you have created a chart as
in the exhibit. What is the area highlighted in the chart called?
A. Out of control
B. Within control
C. Rule of Seven
D. Improvement of quality
Answer: C
Hint: It’s not out.
Study Guide Objective: Implement Quality Management Plan
C is correct because the result of seven measurements in a row on one side of the
mean in a control chart is called the “Rule of Seven.” This is an assignable cause.
A is incorrect because out of control means one measurement exceeds the control limits.
B is incorrect because in control means that the result of one measurement stayed
within the control limits. D is incorrect because the Rule of Seven doesn’t always
signal quality improvement. It could, in some instances, signal that the mean is set
too low for the project.
Q103: Executing the Project
103. You are a project manager and you want to perform some analysis of defects and
problems that have been discovered in the project. Which chart can reveal factors
that might be linked to potential problems within your project?
A. An Ishikawa diagram
B. A control chart
C. A Pareto chart
D. A flowchart
Answer: A
Hint: Fishy.
Study Guide Objective: Implement Quality Management Plan
A is correct because an Ishikawa diagram, also called a cause-and-effect diagram,
reveals potential problems that contribute to effects.
B is incorrect because control charts show if a project is stable and predictable.
C is incorrect because Pareto charts show categories of failure. D is incorrect because
flowcharts help analyze how problems occur.
Q104: Executing the Project
104. You are the project manager of a large project that spans the United States.
Your project team is non-collocated so your communication and travel demands are high.
You’ve made it known that no changes can enter the project unless the stakeholder
wanting the change completes a change request through your web-based change request
form. It has come to your attention that Scotty, a developer in Phoenix, has been
allowing stakeholders to request changes to his work. What must you do in this scenario?
A. Implement corrective action so Scotty won’t allow any more changes to the project
work without using the change control system.
B. Inspect the changes that have entered the project and then have
Scotty reverse any changes you do not approve of.
C. Meet with Scotty and his supervisor to discuss what discipline is most appropriate.
D. Meet with your project team members and key stakeholders in
Phoenix and discuss in detail the change management processes you’ve established.
Answer: A
Hint: Poor Scotty.
Study Guide Objective: Implement Approved Changes
A is correct because you want to implement corrective actions to prevent the problem
from happening again.
B is incorrect because you are not following the change control system or preventing
the problem from happening again. C is incorrect because you are Scotty’s supervisor
when it comes to project discipline. D is incorrect. While this choice seems appropriate,
not all of the project team members or the stakeholders are circumventing the change
control system—just Scotty in this instance. As the project manager, you need to address
the problem directly. In addition, the question states that all of the project team
members and stakeholders are located throughout the United States, not just in Phoenix.
Q105: Executing the Project
105. Congratulations! You’ve finished the project work and are performing quality
control. You are about to enter scope verification and management would first like
to examine all of the changes that have been requested and their status. Management
wants to see which changes have been approved and declined. Where can you find all
of this information?
A. You will only have records of the change requests that have been approved as declined
change requests are discarded.
B. You will only have records of the change requests that have been declined because
all approved changes are incorporated into the project scope and the time and cost
baselines are updated.
C. The Configuration Management System
D. The Risk Register
Answer: C
Hint: You better have both.
Study Guide Objective: Implement Approved Changes
C is correct because the Configuration Management System included the process for
submitting, tracking, reviewing, and approving proposed changes.
A and B are incorrect because you will keep declined and approved change requests.
D is incorrect because this is not relevant with change request tracking.
Q106: Executing the Project
106. Where will a project manager find information on how the project’s product characteristics
can be changed?
A. The project charter
B. The Configuration Management System
C. The project scope
D. The change control board
Answer: B
Hint: Don’t be bored.
Study Guide Objective: Implement Approved Changes
B is correct because that’s what the Configuration Management System does.
A is incorrect because the project charter authorizes the project work. C is incorrect
because the project scope defines the project work. D is incorrect because the CCB
may approve or decline changes based on the change control system the project is using.
Q107: Executing the Project
107. You have a project that must be finished by July 30 or your organization will
have to pay fines and penalties. Management is adamant that you do not exceed more
than $125,000 for the project budget. The project is nearing completion but you will
likely miss the target end date. What can you do to meet the project end date without
spending more dollars on the project?
A. Nothing. You will have to spend more money to complete on time because you will
need to buy more labor.
B. Crash the project.
C. Add lag to the project.
D. Trim the project scope of everything that is not affected by the fines and penalties.
Answer: D
Hint: Lose the fat.
Study Guide Objective: Implement Approved Changes
D is correct because while it does assume there are things to trim in the project
scope, it is the only option that won’t increase costs and complete the project by
the scheduled end date.
A is incorrect because this statement is not true. B is incorrect because crashing
the project means you’ll be adding labor, which will drive costs. C is incorrect because
lag is positive time (or waiting time), so this will actually cause the project to
be late.
Q108: Executing the Project
108. Your project continues to stall because of additional changes to the project
scope. You’ve asked that all changes to the project scope stop unless the changes
are truly needed for the success of the project scope as it was approved. Management,
however, has demanded a change to the project. What must be examined?
A. The change request and its impact on the entire project
B. The change request and the cost to implement the change
C. The change request and the time to implement the change
D. The change request and the purpose for the change
Answer: A
Hint: Integrated Change Control.
Study Guide Objective: Implement Approved Changes
A is correct because the change may affect all or some of the knowledge areas: time,
cost, quality, communications, risk, human resources, procurement.
B is incorrect because it only addresses cost. C is incorrect because it only addresses
time. D is incorrect because it only addresses the change request.
Q109: Executing the Project
109. Your project team has incorporated some minor changes into their project work
as directed by the customer. You agree that these changes are needed. What is this
an example of?
A. Fluid change control
B. Integrated change control
C. Expert judgment
D. Scope creep
Answer: D
Hint: It’s not good.
Study Guide Objective: Implement Approved Changes
D is correct because uncontrolled changes are called scope creep.
A is incorrect because this term is not valid. B is incorrect because integrated change
control requires documented changes to follow a set of rules of reviewing and approving
change requests. C is incorrect because expert judgment is when an expert helps you,
the project manager, make the best decision. In this instance, no one helped with
the decision, it was just implemented without any review or consideration.
Q110: Executing the Project
110. Holly is the project manager of the UIM Project for her company. A new change
request has moved through the change control board and it was approved. Now Holly
needs to incorporate the change into the project to reflect the additional scope requirements.
All of the following are results of approved changes except for which one?
A. Project charter updates
B. Project scope updates
C. WBS updates
D. WBS dictionary updates
Answer: A
Hint: Not the big one.
Study Guide Objective: Implement Approved Changes
A is correct because the charter is not updated as a result of an approved change
request.
B is incorrect because the scope may be updated as a result of an approved change
request. C is incorrect because the scope may be updated as a result of an approved
change request. D is incorrect because the scope may be updated as a result of an
approved change request.
Q111: Executing the Project
111. Project management requires cost control, which can mean tradeoffs and additional
funds for changes. Currently, your project is running over on costs due to unknown
unknowns. What can you do?
A. Nothing because unknown unknowns are risks.
B. Propose to management to obtain more funds to counteract the unknown unknowns.
C. Propose to management to utilize the management contingency reserve.
D. Prepare an assessment of why the project has failed due to the unknown unknowns.
Answer: C
Hint: Only for emergencies.
Study Guide Objective: Implement Approved Actions and Workarounds
C is correct because the management contingency reserve is an amount of funds set
aside for unplanned events that consume the project budget.
A is incorrect because while unknowns may be risks, this is not the best response.
B is incorrect because it does not answer the question as completely as C. D is incorrect
because the project has not failed at this point.
Q112: Executing the Project
112. Bob is a project manager in a functional organization. He disagrees with the
project sponsor on how some activities of the project should commence. The project
sponsor, however, insists that Bob have the project team begin working on the project.
What should Bob do?
A. Instruct the project team to begin working on the project.
B. Object to the project sponsor’s manager.
C. Document the disagreements in a formal report for lessons learned when the project
fails.
D. Instruct the project team to work only on critical path activities.
Answer: A
Hint: No fun for the project manager.
Study Guide Objective: Implement Approved Actions and Workarounds
A is correct because the project sponsor is in charge in a functional organization.
In addition, it’s permissible to have disagreements regarding the project work as
long as the disagreements don’t hinder the project from moving forward.
B is incorrect because Bob is operating in a functional organization. C is incorrect
because there’s no reason for Bob to document the issues in a formal report. In addition,
this answer implies that the project will fail while the question does not stress
the magnitude of the problem or disagreement. D is incorrect because the project team
should work on the activities as planned, not only the activities on the critical
path.
Q113: Executing the Project
113. You need a vendor to ship a piece of software for your project immediately so
your project team can install the software over the holiday weekend. Because of the
holiday weekend, however, no one will be able to accept the package when the delivery
company attempts to deliver the package. Which one of the following is an example
of an appropriate workaround?
A. Don’t start the project work activities until after the holiday when the mailroom
can accept the package.
B. Fly to the vendor’s location to pick up the package in person.
C. Have the vendor deliver the software to one of the team member’s homes so they
have the software delivered directly to them.
D. Demand a discount from the vendor because of the shipping error.
Answer: C
Hint: There’s no error.
Study Guide Objective: Implement Approved Actions and Workarounds
C is correct because this workaround allows the project team member to receive the
software before the project is scheduled to start.
A is incorrect because this will delay the project. B is incorrect because this workaround
will increase costs and would be a waste of time. D is incorrect because there is
no error with the shipping. A discount would not get the software to the project team
member’s home as needed.
Q114: Executing the Project
114. The project vendor you selected to provide materials for your project cannot
deliver. You need the materials by the end of the week. The change control board agrees
that you should call another vendor that has slightly higher prices but can deliver
as needed. This is an example of which one of the following?
A. A workaround
B. A contingency plan
C. A transference
D. Mitigation
Answer: A
Hint: It’s not planned.
Study Guide Objective: Implement Approved Actions and Workarounds
A is correct because this is an example of a workaround.
B is incorrect because a contingency plan is pre-planned, whereas a workaround is
a response to an immediate risk. C is incorrect because transference transfers the
risks to another party. D is incorrect because mitigation is a planned attempt to
reduce or eliminate the impact of a known risk. In this instance, the risk was not
known.
Q115: Executing the Project
115. The project team has completed some of the project work incorrectly. You’ve instructed
the project team to redo the work. What must happen next?
A. Conduct an analysis of the delay because of the rework.
B. Conduct an analysis of the cost increase because of the rework.
C. Review each project team member’s performance.
D. Review the defect repair.
Answer: D
Hint: Make sure everything is correct.
Study Guide Objective: Implement Approved Actions and Workarounds
D is correct because the repair must be reviewed for accuracy.
A is incorrect because the repair must be correct before the project can move forward.
If the repair is assumed to be correct, then the review of the time delay may be inaccurate
because of future rework, waste, or a series of failures because of the inaccurate
rework. B is incorrect because the repair must be reviewed for accuracy first. C is
incorrect because this is not the most pressing issue at this point in the project.
Q116: Executing the Project
116. Quality control is managed by Terry, a quality engineer on your project. Terry
reports that she’ll need some time and resources to complete quality control on the
project deliverables. Terry also reports the tools she’ll use as part of the quality
control activities. All of the following are quality control tools Terry could use
except for which one?
A. Control charts
B. Baseline updates
C. Flowcharting
D. Inspection
Answer: B
Hint: No changes.
Study Guide Objective: Implement Approved Actions and Workarounds
B is correct because this is not a quality control tool. A baseline update reflects
changes to the project’s scope, cost, or schedule baseline.
A is incorrect because this is a quality control tool. Control charts show fluctuations
from the project’s mean. C is incorrect because this is a quality control tool. Flowcharts
show the flow of work, information, or data through a defined system. D is incorrect
because this is a quality control tool. Inspection is the primary quality control
tool Terry will use.
Q117: Executing the Project
117. As a project manager, you may rely on organizational theories to help you better
manage the project team. Which organizational theory believes that an absence of hygiene
agents will demotivate a project team?
A. Maslow’s Hierarchy of Needs
B. Ouchi’s Theory Z
C. Herzberg’s Theory of Motivation
D. McGregor’s X and Y
Answer: C
Hint: Not an ouchie.
Study Guide Objective: Improve Team Performance
C is correct because Herzberg’s Theory of Motivation states that hygiene agents, such
as a paycheck, won’t motivate people, but their absence will demotivate.
A is incorrect because Maslow’s Hierarchy of Needs identifies the seven needs we all
pursue. B is incorrect because Ouchi’s Theory Z is based on the Japanese management
style. D is incorrect because McGregor’s X and Y is a description of management’s
view of its employees. The X believe that project team members must be micromanaged.
The Y believe that project team members can be self-led.
Q118: Executing the Project
118. Which organization theory believes that project teams can be self-led?
A. Maslow’s Hierarchy of Needs
B. Ouchi’s Theory Z
C. Herzberg’s Theory of Motivation
D. McGregor’s X and Y
Answer: D
Hint: Not an ouchie.
Study Guide Objective: Improve Team Performance
D is correct because McGregor’s X and Y is a description of management’s view of its
employees. The X managers believe that project team members must be micromanaged.
The Y managers believe that project team members can be self-led.
C is incorrect because Herzberg’s Theory of Motivation states that hygiene agents,
such as a paycheck, won’t motivate people, but their absence will demotivate. A is
incorrect because Maslow’s Hierarchy of Needs identifies the seven needs we all pursue.
B is incorrect because Ouchi’s Theory Z is based on the Japanese management style.
Q119: Executing the Project
119. McClelland’s Theory of Needs states that there are three needs that we all have.
The needs are developed over time and through life experiences. What is the name of
the analysis which determines an individual’s driving need?
A. The Myers-Brigg test
B. The Thematic Apperception Test
C. The Big Five Personality Test
D. The Accurate Personality Test
Answer: B
Hint: Tit for TAT.
Study Guide Objective: Improve Team Performance
B is correct. The Thematic Apperception Test (TAT) can determine if power, achievement,
or affiliation drives an individual.
A is incorrect. The Myers-Brigg test is based on the work of Carl Jung, not McClelland.
C is incorrect. The Big Five Personality Test was developed by Paul Costa and Robert
McCrae. D is incorrect because this is not a valid test for determining driving needs.
Q120: Executing the Project
120. June is the project manager of her project and wants to recognize team members
that have contributed to the project work in a significant way each month. June decides
that she’ll award one team member the title of “Team Member of the Month.” This person
will get to park in a reserved parking space and will receive one paid day off from
the project. What is the danger in June’s plan for rewards and recognition?
A. There is no danger. This is an example of a reward and recognition system.
B. Only project team members that have activities during the month can be awarded
the title.
C. Only one team member can be awarded the title per month.
D. The project manager chooses the team member, not the project team.
Answer: C
Hint: It’s not good for everyone.
Study Guide Objective: Improve Team Performance
C is correct because this is an example of a zero sum reward. Only one team member
can be awarded the title.
A is incorrect because this is an example of a zero sum reward. B is incorrect because
it doesn’t fully answer the question. D is incorrect because this is not the issue
of the reward. Regardless of who chooses the reward, only one team member can receive
the award.
Q121: Executing the Project
121. All of the following are true statements about the staffing management plan except
for which one?
A. The staffing management plan provides information about when project team members
may be released from the project team.
B. The staffing management plan provides information about staff acquisition.
C. The staffing management plan provides information about project safety.
D. The staffing management plan provides information about project quality.
Answer: D
Hint: Isn’t there another plan for this one?
Study Guide Objective: Improve Team Performance
D is correct because this is a false statement about the staffing management plan.
The quality management plan defines quality expectations.
A, B, and C are incorrect because each is a true statement about the staffing management
plan.
Q122: Executing the Project
122. You are the project manager for your organization which will utilize contract
labor on your project. The labor will be part of a union workforce. Which plan defines
union contracts?
A. The project plan
B. The procurement management plan
C. The staffing management plan
D. The risk management plan
Answer: C
Hint: 9
Hint: Not risky.
Study Guide Objective: Improve Team Performance
C is correct because the staffing management plan does define compliance issues with
union contracts.
A is incorrect because this is too broad an answer. B is incorrect because this plan
defines the procurement policies of the organization. D is incorrect because this
plan defines risk management for the project.
Q123: Monitoring and Controlling the Project
123. You are a project manager for your organization. Your project has a BAC of $400,000
and is expected to last one year. The project work is scheduled to be completed in
equal amounts each month. Currently, the project is in month three but is only 20
percent complete. You have spent $35,000 to complete the work. What is the earned
value for this project?
A. Negative $20,000
B. $80,000
C. $100,000
D. Not enough information to know
Answer: B
Hint: Find the percent complete.
Study Guide Objective: Measure Project Performance
B is correct. The earned value for this project is 20 percent complete. The formula
is EV= % complete × BAC.
A is incorrect. The EV is not a negative number because it is 20 percent complete.
C is incorrect because $100,000 is the planned value amount. D is incorrect. There
is enough information to calculate the formula.
Q124: Monitoring and Controlling the Project
124. You are a project manager for your organization. Your project has a BAC of $400,000
and is expected to last one year. The project work is scheduled to be completed in
equal amounts each month. Currently the project is in month three but is only 20 percent
complete. You have spent $35,000 to complete the work. What is the planned value for
this project?
A. $20,000
B. $35,000
C. $80,000
D. $100,000
Answer: D
Hint: Find out how much should have been spent. Reference: PMP Study Guide, Chapter 7
Study Guide Objective: Measure Project Performance
D is correct. The planned value is the amount the project should have spent to reach
this point in the schedule. Because the project is schedule to last one year with
the work completed in part each month, month three represents 25 percent of the project,
or $100,000.
A is incorrect because $20,000 is not the planned value. B is incorrect because $35,000
is the actual cost. C is incorrect because $80,000 is the earned value.
Q125: Monitoring and Controlling the Project
125. You are a project manager for your organization. Your project has a BAC of $250,000
and is expected to last ten months. Currently the project is in month six and is 40
percent complete, but the project was expected to be 60 percent complete by this time.
You have spent $125,000 to complete the work. What is the cost performance index of
the project?
A. 80
B. 1.25
C. $125,000
D. .80
Answer: D
Hint: Double-check your work.
Study Guide Objective: Measure Project Performance
D is correct. The cost performance index is calculated by dividing the earned value
by the actual costs. In this instance, the formula is CPI = 100,000/125,000. This
results in .80.
A is incorrect. The CPI is .80, not 80. B is incorrect because this is not the right
value. C is incorrect. The CPI is not a dollar amount, so this value is incorrect.
Q126: Monitoring and Controlling the Project
126. You are a project manager for your organization. Your project has a BAC of $250,000
and is expected to last ten months. Currently the project is in month six and is 40
percent complete, but the project was expected to be 60 percent complete by this time.
You have spent $125,000 to complete the work. What is the schedule performance index
of the project?
A. .80
B. .67
C. $67,000
D. $80,000
Answer: B
Hint: Not a dollar amount.
Study Guide Objective: Measure Project Performance
B is correct. The schedule performance index (SPI) is calculated by dividing the earned
value by the planned value. In this instance, the formula is $100,000/150,000 = .67.
A is incorrect. This is the value of the cost performance index. C and D are incorrect
because the SPI is not a dollar amount.
Q127: Monitoring and Controlling the Project
127. You are the project manager for your organization and you’re examining several
projects you’re managing for your company. In your analysis, you’ve noticed that one
of your projects has an SPI of .80. A project with an SPI of .80 means what?
A. The project is behind schedule.
B. The project is ahead of schedule.
C. The project is losing money.
D. The project is 80 percent complete.
Answer: A
Hint: SPI is the schedule performance index.
Study Guide Objective: Measure Project Performance
A is correct. A schedule performance index of .80 means the project is behind schedule.
The closer to “1” the SPI is, the better the project.
B is incorrect. An SPI of .80 means the project is behind schedule, not ahead. C is
incorrect. While the project likely will result in being over budget due to the labor
demands to complete the project, the SPI deals with the project schedule. D is incorrect.
An SPI does not reflect the percent complete of the project.
Q128: Monitoring and Controlling the Project
128. You are the project manager for your organization and you’re examining several
projects you’re managing for your company. In your analysis, you’ve noticed that one
of your projects has a CPI of .98. A project that has a CPI of .98 means what?
A. The project is late.
B. The project is making money.
C. The project has to spend one dollar for every 98 cents worth of work it receives.
D. The project is 98 percent complete.
Answer: C
Hint: CPI is the cost performance index. Reference: PMP Study Guide, Chapter 7 Study Guide Objective: Measure Project Performance
C is correct. A project with a CPI of .98 has to spend one dollar for every 98 cents
worth of work it receives.
A is incorrect. There is no evidence that the project is late. B is incorrect because
the project is actually losing money with this CPI, not making it. D is incorrect
because a CPI of .98 does not mean the project is 98 percent complete.
Q129: Monitoring and Controlling the Project
129. You are the project manager of a project to install new light fixtures throughout
several factories. The project is expected to last one year and has a BAC of $750,000.
The project is now in month four and has a CPI of .89. Which one of the following
statements is true about this project?
A. The project is performing well.
B. The project spends one dollar for 89 cents of work.
C. The project will likely finish under budget.
D. The project will likely finish in alignment with the cost baseline.
Answer: B
Hint: CPI = EV/AC
Study Guide Objective: Measure Project Performance
B is correct. The project with a CPI of .89 is not doing too well. For every dollar
the project spends, it loses 11 cents.
A is incorrect. The project is not performing well. C is incorrect. The project will
likely finish over budget. D is incorrect. The probably won’t be in alignment with
the cost baseline.
Q130: Monitoring and Controlling the Project
130. Examine the exhibit. You are the project manager for your organization. You’re
working with your project team to help them understand the concept of the critical
path in a project. If the exhibit represents your project, what is the critical path?
A. ABEI
B. ABDGI
C. ACFHI
D. IGDBA
Answer: C
Hint: Find the longest path to completion.
Study Guide Objective: Execute Tasks Defined in Project Plan
C is correct. The critical path is the longest path of duration from the project start
to its completion. In this example, the critical path is the sum of duration for tasks
ACFHI at 22 days.
A is incorrect. The path of ABEI is only 13 days. B is incorrect. The path of ABDGI
is 21 days. D is incorrect. To find the critical path, add up the duration of the
path moving forward, not backward.
Q131: Executing the Project
131. You are the project manager of the NHQ Project for your company. You are working
with your project team and the project sponsor to create a stakeholder management
strategy. You want to determine the needed level of interaction among the project
stakeholder. What document will best help you complete this task?
A. The project charter
B. The stakeholder registry
C. The stakeholder management plan
D. The project management plan
Answer: C
Hint: You’re executing a plan.
Study Guide Objective: Manage Stakeholder Engagement
C is correct. The stakeholder management plan is an input to management stakeholder
engagements. This plan defines the needed levels of interactions of the project stakeholders.
A is incorrect. The project charter authorizes the project and the project manager,
but it doesn’t define the interactions among the project stakeholders. B is incorrect.
The stakeholder registry defines the project stakeholders, their communication preferences,
and project concerns. D is incorrect. The stakeholder management plan is part of the
project’s management plan, but this isn’t the best answer for the question because
the stakeholder management plan is most specific.
Q132: Monitoring and Controlling the Project
132. Harry is the manager of a software development project for his company. In this
project, Harry is utilizing an issue log. What should Harry do with the issue log
when issues have been resolved?
A. Delete the issue log.
B. Delete the resolved issues from the log.
C. Update the project risk register because the issue is no longer relevant to the
project success.
D. Update the issue log.
Answer: D
Hint: Don’t delete anything.
Study Guide Objective: Manage Stakeholder Engagement
D is correct. When an issue has been resolved, Harry should update the issue log to
reflect the status of the issue as resolved.
A is incorrect. The issue log should not be deleted because it will become part of
the organizational process assets. B is incorrect because the issue should be marked
as resolved, not deleted. C is incorrect because the issue log is separate from the
risk register.
Q133: Monitoring and Controlling the Project
133. You are preparing for stakeholder engagement in your project. All of the following
items will be needed as part of stakeholder engagement except for which one?
A. The project management plan
B. The issue log
C. Work performance data
D. The risk management plan
Answer: D
Hint: Not risky.
Study Guide Objective: Manage Stakeholder Engagement
D is correct because the risk management plan is not an input to the control stakeholder
engagement process. There are four inputs to this process: the project management
plan, issue logs, project documents, and work performance data.
A is incorrect because the project management plan is an input to the control stakeholder
engagement process. B is incorrect because the issue log is an input to the control
stakeholder engagement process. C is incorrect because work performance data is an
input to the control stakeholder engagement process.
Q134: Monitoring and Controlling the Project
134. Management has compared your project to a similar project that’s just been completed
in your organization. This finished project was deemed successful. This is benchmarking.
What is the goal of this comparison?
A. To provide a basis by which management may measure performance of your project.
B. To provide a basis by which management may measure all projects.
C. To provide a basis by which management may measure the completed project.
D. To provide a basis by which management may measure project managers.
Answer: A
Hint: Not the project managers.
Study Guide Objective: Measure Project Performance
A is correct because management wants to determine how your project is fairing in
comparison to a completed project that they’ve already deemed successful.
B is incorrect because benchmarking is most useful for similar projects, though it
is possible to benchmark projects that are not in the same discipline. C is incorrect
because management has already deemed the finished project as successful. D is incorrect
because the goal is to measure your project, not you.
Q135: Monitoring and Controlling the Project
135. In the early stages of a project, this event is easy to accept. Later in the
project it is difficult to accept. What is the event?
A. Change
B. Risk
C. Team development
D. Scope verification
Answer: A
Hint: The further the project is from completing, the higher the risk and uncertainty.
Study Guide Objective: Verify and Manage Changes to the Project
A is correct. Change is easily accepted in the beginning of a project. As the project
moves toward completion, change is harder to incorporate.
B is incorrect. Risk is only accepted based on its impact of the project and the performing
organization’s utility function. Recall that the utility function is an organization’s
willingness to accept risk. C is incorrect. Team development happens throughout the
project. D is incorrect. Scope verification happens throughout the project at phase
completion, at major project deliverables, and at project completion.
Q136: Monitoring and Controlling the Project
136. You are the project manager of the NHB Project. You’ve just learned that the
cost of materials will increase by 10 percent due to a hurricane along the Gulf Coast.
You would like to update the cost baseline to reflect these unanticipated changes.
What system will allow you to make these changes?
A. The change control system
B. The cost change control system
C. The change control board
D. The cost management system
Answer: B
Hint: It’s money.
Study Guide Objective: Verify and Manage Changes to the Project
B is correct because procedures on how to change the cost baseline are documented
in the cost change control system.
A is incorrect because this does not answer the question as completely as B. C is
incorrect because the CCB may be part of the change control system, but B answers
the question completely. D is incorrect because this term is not valid.
Q137: Monitoring and Controlling the Project
137. Charles, the carpenter for the XHG project, has made a change to the wood floor
he’s installing. He decided that the floor should be installed at an angle because
of a doorway in the living room. You inspect the installed wood floor and agree with
his decision. This is an example of which one of the following?
A. Expert judgment
B. Ineffective change control
C. Corrective action
D. Self-led teams
Answer: B
Hint: It’s not good.
Study Guide Objective: Verify and Manage Changes to the Project
B is correct because the change was made by Charles on his own accord. The change
control system was not followed.
A is incorrect because expert judgment is using an expert to help make the best decision.
No consultation was done on the change. C is incorrect because corrective action is
correcting a problem to get the project work back into scope. D is incorrect because
Charles did not consult, document, or involve the project team in his decision.
Q138: Monitoring and Controlling the Project
138. You are the project manager for your organization and you’re working with the
project team to define the change control system. You want to capture the correct
information when changes are presented and analyzed for your project. Which one of
the following must be completed for each change that is proposed for a project?
A. The project charter must be examined.
B. The project life cycle costs must be reviewed.
C. The change must be reviewed for any associated risks.
D. The benefit/cost ratio must be reviewed.
Answer: C
Hint: Review it.
Study Guide Objective: Verify and Manage Changes to the Project
C is correct because integrated change control calls for all of the knowledge areas,
including risks, to be reviewed for the impact of the proposed change.
A is incorrect because the charter does not have to be examined. B is incorrect because
the life cycle costs concern the cost of the project’s deliverable once it’s in production.
In some instances, life-cycle costing may be appropriate, but not in every instance
of a change request. D is incorrect because benefit/cost ratios are a method for selecting
projects, not evaluating change requests.
Q139: Monitoring and Controlling the Project
139. You are the project manager of a software development project. In this project,
you will approve or decline proposed changes before they are incorporated into the
project plan. You have recently approved a change that will increase the project’s
costs. What must you do next?
A. Prepare a cost variance report.
B. Examine the overall impact of the change request on the project.
C. Examine the direct costs of the change.
D. Change the project’s cost baseline to reflect the added change.
Answer: D
Hint: It’s about change.
Study Guide Objective: Verify and Manage Changes to the Project
D is correct because the project’s baselines must be changed to reflect the added
change.
A is incorrect because there’s no reasons to create a variance report; it’s a change
not a cost overrun. B is incorrect because this is part of the process to approve
the change request. The change request has already been approved in this instance.
C is incorrect because this is part of the process to approve the change request.
The change request has already been approved in this instance.
Q140: Monitoring and Controlling the Project
140. A vendor has proposed a change to the work you’ve contracted them to do for your
project. The vendor says it is because of the hardware installed on your company’s
server. Your hardware technician says this is not true, that the hardware installation
is accurate and there is no need for the change. What should you do with the proposed
change?
A. Discard the change request and ask the vendor to continue as planned.
B. Accept the vendor’s proposed change because it’s their contract to complete the
work.
C. Enter the change request into the SOW update for consideration.
D. Add the change request to the project’s change control system for consideration.
Answer: D
Hint: Add it.
Study Guide Objective: Verify and Manage Changes to the Project
D is correct because this is a proposed change. It should be documented and reviewed
for consideration. Just because the change is considered doesn’t mean that it will
necessarily be implemented.
A is incorrect because discarding the change offers no documentation in case the change
is actually needed. B is incorrect because the change should be added to the change
control system for review, not just assigned to the vendor to complete. C is incorrect
because changes don’t go into the SOW at this point.
Q141: Monitoring and Controlling the Project
141. You are the project manager for an organization completing a project for your
customer. Your boss approaches you and asks that you add a few features to the deliverable
your project team is creating as part of the project. What should you do next?
A. Instruct the team to add the features.
B. Consult with the customer about the features your project team is adding to the
project scope.
C. Ask the customer if they would like the features as part of the deliverable.
D. Add the features but document them in an approved change request.
Answer: C
Hint: It’s not your deliverable.
Study Guide Objective: Verify and Manage Changes to the Project
C is correct because the customer must approve any changes to the project deliverable.
A is incorrect because the customer must first approve proposed changes. B is incorrect
because the project manager must gain approval from the customer in order to make
the changes. D is incorrect because it circumvents the change management process.
Q142: Monitoring and Controlling the Project
142. Your functional manager asks you to add features to the project scope to consume
the remaining dollars in the project budget. This is an example of which one of the
following?
A. Gold plating
B. Change control
C. Functional management
D. Cost of quality
Answer: A
Hint: Sounds nice, but it’s not.
Study Guide Objective: Verify and Manage Changes to the Project
A is correct because adding features to the project scope just to consume the project
budget is called gold plating.
B is incorrect because this does not answer the question as completely as A. C is
incorrect because the organizational structure does not change that this is gold plating.
D is incorrect because this answer is not relevant to this question.
Q143: Monitoring and Controlling the Project
143. You are the project manager of a project that has a preset budget and must be
completed within six months. You’ve completed the first phase of your project. The
stakeholder, however, wants to know why one of the changes you and he discussed was
not implemented into the deliverable. During the original conversation about the change,
the stakeholder wanted to perform a cost-benefits analysis, which he reported the
results of to you. What’s your response?
A. The change was not needed.
B. The change would have cost too much.
C. The change would have taken too long to deliver.
D. The change request was never documented for the change control system.
Answer: D
Hint: Do it right.
Study Guide Objective: Verify and Manage Changes to the Project
D is correct because in the change control system all changes should be formally documented.
Undocumented change requests should not be processed or implemented.
A is incorrect because the change may have been needed but the failure to follow the
change control system prevents the change from entering the project scope. B is incorrect
because there’s no mention of how much the change would cost the project. C is incorrect
because there’s no mention of how much additional time the change would require.
Q144: Monitoring and Controlling the Project
144. Which one of the following statements about changes to the project scope is correct?
A. All changes should be formally documented.
B. All changes require additional project time.
C. All changes require additional project funding.
D. All changes follow the rules of the change control system.
Answer: A
Hint: Ask yourself, “Do all changes require this?”
Study Guide Objective: Verify and Manage Changes to the Project
A is correct because all changes, approved or otherwise, should be formally documented.
B is incorrect because not all changes require additional time. C is incorrect because
not all changes require additional funding. D is incorrect because not all changes,
unfortunately, follow the change control system. Some changes are unauthorized, but
they occur anyway.
Q145: Monitoring and Controlling the Project
145. John is the project manager of the BHQ Project. This project is to create new
software for a client. John insists on a documented approach to quality control for
the software deliverable. Quality control focuses on what activity?
A. Quality assurance
B. Quality management
C. Inspection
D. Acceptance
Answer: C
Hint: It’s work.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
C is correct because quality control focuses on prevention and inspection.
A is incorrect because quality assurance is a management process to ensure that the
project employs all processes to meet requirements. B is incorrect because this term
is not valid. D is incorrect because this term applies to scope verification.
Q146: Monitoring and Controlling the Project
146. You are the project manager for your organization and you’ve identified several
mistakes in the project deliverables. You’d like to investigate the issue more closely
and your project sponsor recommends you create an Ishikawa diagram. What is an Ishikawa
diagram?
A. A control chart
B. A fishbone diagram
C. A scatter diagram
D. A Pareto chart
Answer: B
Hint: Hooked you.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
B is correct because an Ishikawa diagram is also called a fishbone diagram. It’s also
known as a cause-and-effect diagram.
A is incorrect because a control chart is used to predict performance. C is incorrect
because a scatter diagram shows the pattern of relationship between two variables.
D is incorrect because a Pareto chart shows categories of failure.
Q147: Monitoring and Controlling the Project
147. Examine the exhibit. What is the highlighted area in the following chart called?
A. The mean
B. The Rule of Seven
C. The control limit
D. Six Sigma
Answer: B
Hint: Not Sigma.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
B is correct because whenever there are seven measurements in a row all on one side
of the mean, this is called the Rule of Seven. It is an assignable cause.
A is incorrect because the mean is represented by the solid bar in the middle of the
control chart. C is incorrect because the control limits are the top and bottom lines
in the control chart. D is incorrect because Six Sigma is a quality assurance program
invented by Motorola.
Q148: Monitoring and Controlling the Project
148. Management wants a histogram that demonstrates the number of defects that were
caused by equipment failure, software errors, human errors, and drive conflicts. What
type of histogram is management asking for?
A. A cause-and-effect diagram
B. A control chart
C. A Pareto chart
D. A flowchart
Answer: C
Hint: 80/20.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
C is correct because a Pareto chart is a histogram that shows categories of failure.
A is incorrect because a cause and effect diagram seeks to identify why the failures
happened, while a Pareto chart only wants to identify the categories of failure. B
is incorrect because a control chart tracks success and failures as a whole—not by
individual errors. D is incorrect because a flowchart shows the flow of work or processes
within a system.
Q149: Monitoring and Controlling the Project
149. Jim is the project manager of the BHQ Project for his company. This project is
a manufacturing project for a new client. Beth, the project sponsor, has asked Jim
to create a chart that will help the stakeholders see the history of the project work
and any variations to the project mean. This chart, however, must be measured against
a timeline. Which type of quality control chart shows the history and pattern of variation?
A. A run chart
B. A flowchart
C. A Pareto chart
D. A network diagram chart
Answer: A
Hint: On your mark...
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
A is correct. Run charts show the history and pattern of variation.
B is incorrect because a flowchart shows the flow of work or processes within a system.
C is incorrect because a Pareto chart is a histogram that shows categories of failure.
D is incorrect because a network diagram chart demonstrates the flow of activities
within a project.
Q150: Monitoring and Controlling the Project
150. Pi is the project manager for her organization. Management has asked her to identify
the quality control tools she’ll use in the project. All of the following are examples
of quality control tools except for which one?
A. Inspection
B. Defect repair review
C. Statistical sampling
D. Quality audits
Answer: D
Hint: Organization-wide.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct because quality audits are a tool used for quality assurance.
A is incorrect because inspection is a QC tool. B is incorrect because defect repair
review is a QC tool. C is incorrect because statistical sampling is a QC tool.
Q151: Monitoring and Controlling the Project
151. You are the project manager of the BHQ Manufacturing Project. In this project,
you have utilized a control chart to measure project performance of repeatable activities.
You are examining a control chart. When should processes be adjusted?
A. When the control chart’s mean is too low.
B. When the control chart’s mean is too high.
C. When the process is within acceptable limits.
D. When the process is outside of acceptable limits.
Answer: D
Hint: Fix the problem.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct because processes outside of acceptable limits should be adjusted to
bring the process into acceptable limits.
A is incorrect because the mean represents the average or predicted average for the
results. B is incorrect because the mean represents the average or predicted average
for the results. C is incorrect because processes within acceptable limits should
not be adjusted.
Q152: Monitoring and Controlling the Project
152. As part of your construction project, there are several standards and regulations
that you must accommodate in the project work. What is the difference between a standard
and a regulation?
A. Standards and regulations are essentially the same.
B. Standards are determined by the Organization for International
Standards, while regulations are specific to each industry.
C. Standards are optional, while regulations vary by industry.
D. Standards are optional, while regulations are not.
Answer: D
Hint: Don’t go to jail.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct because standards are guidelines, which are optional, while regulations
are never optional.
A, B, and C are incorrect because each is a false statement about regulations and
standards.
Q153: Monitoring and Controlling the Project
153. You are the project manager of the HNN Project. Your team needs safety training
in order to install several of the components in your project. The cost of this training
is known as which one of the following?
A. Team development
B. Cost of quality
C. Cost of nonconformance
D. Variable costs
Answer: B
Hint: The training is needed in order to complete the project.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
B is correct because the cost of training is considered a cost of quality.
A is incorrect because training is one method of team development, but the cost of
training is not. C is incorrect because the cost of nonconformance to quality is the
costs that will occur if quality is not obtained. D is incorrect because variable
costs describes costs that fluctuate within a project.
Q154: Monitoring and Controlling the Project
154. All project managers should set expectations for the quality of the project.
These expectations should be clearly defined as part of the quality management plan.
All of the following are quality planning tools except for which one?
A. Force field analysis
B. Flowcharts
C. Brainstorming
D. Inspection
Answer: D
Hint: Not Spock!
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct because inspection is a quality control tool, not a quality planning
tool. You’ll inspect the results of the project work well after the quality planning
occurs.
A is incorrect because this is an example of a quality planning tool. B is incorrect
because this is an example of a quality planning tool. C is incorrect because this
is an example of a quality planning tool.
Q155: Monitoring and Controlling the Project
155. An organization’s willingness to accept risk is known as what?
A. The entrepreneurial spirit
B. An autocratic belief
C. The utility function
D. Risk threshold
Answer: C
Hint: It’s not a threshold.
Study Guide Objective: Monitor All Risks
C is correct because the utility function is the term used to describe an organization’s
willingness to accept risk.
A is incorrect because this term is not valid. B is incorrect because this describes
project management leadership, not risk. D is incorrect because the term describes
a condition that a risk event is pending or has come to fruition.
Q156: Monitoring and Controlling the Project
156. You are the project manager for a new software development project for a client.
You are explaining to the client the approach you’ll use to identify, plan, and manage
the risks within the project. Which best describes when risk identification occurs?
A. Early in the project
B. During project initiation
C. Iteratively
D. As scheduled by the risk management plan
Answer: C
Hint: Over and over.
Study Guide Objective: Monitor All Risks
C is correct because risk identification is an iterative process. The project team
must proactively look for risks.
A is incorrect because risk doesn’t happen only early in the project, but throughout
the project. B is incorrect because risk identification doesn’t happen in initiation,
but iteratively throughout the project. D is incorrect because risk identification
happens sans schedule, as needed.
Q157: Monitoring and Controlling the Project
157. Your project sponsor has asked you to review some of the risks of the project
with him. In particular, the project sponsor wants to define some of the root causes
of risks. Which component will help you, the project manager, identify the root causes
of risk?
A. The project team
B. Expert judgment
C. Project scope
D. Risk register
Answer: D
Hint: Not a person.
Study Guide Objective: Monitor All Risks
D is correct because the risk register includes the root causes of risk.
A is incorrect because the project team may contribute to the root cause analysis,
but the risk register is the component that stores the root cause of identified risk.
B is incorrect because experts may contribute to the root cause analysis, but the
risk register is the component that stores the root cause of identified risk. C is
incorrect because the project scope does not contribute to or supply the root cause
of risks.
Q158: Monitoring and Controlling the Project
158. Based on the following table, what is the needed contingency reserve?
A. -11,600
B. 11,600
C. 4000
D. 120 percent of the project budget
Answer: B
Hint: You don’t get it all.
Study Guide Objective: Monitor All Risks
B is correct because the contingency reserve is found by multiplying the probability
times the impact. The sum of the expected monetary value equates, in positive numbers,
to the amount of the contingency reserve.
A is incorrect because this is a negative number. The contingency reserve is a positive
number. C is incorrect because this is an incorrect calculation for the contingency
reserve. D is incorrect because this statement is false.
Q159: Monitoring and Controlling the Project
159. Management wants you, the project manager, to create a matrix to quickly show
the probability of each risk in your project. What is management asking for?
A. A probability-impact matrix
B. A risk rating matrix
C. An RAG rating matrix
D. A risk owner’s matrix
Answer: A
Hint: You can create these for qualitative and quantitative risk analysis.
Study Guide Objective: Monitor All Risks
A is correct because this matrix identifies the probability, impact, and overall risk
score for the project.
B and D are incorrect because neither term is valid. C is incorrect because an RAG
rating is represented by a red-amber-green rating for risk identification or risk
activity.
Q160: Monitoring and Controlling the Project
160. You would like to use a simulation to predict a project’s success based on the
number of identified risks and their overall impact. What method could you use?
A. PERT
B. GERT
C. A Monte Carlo Simulation
D. A risk simulation
Answer: C
Hint: It’s not a gamble.
Study Guide Objective: Monitor All Risks
C is correct because a Monte Carlo Simulation can be used to determine the likelihood
of a project’s success.
A is incorrect because PERT is a time-estimating formula. B is incorrect because GERT
is a network diagramming technique. D is incorrect because this answer is not valid
for this question.
Q161: Monitoring and Controlling the Project
161. You have identified a risk that may cause safety concerns for the workers completing
the task. You’ve decided to hire a third party to complete this work because the risk
is too great to accept internally. Which risk response is this?
A. Mitigation
B. Acceptance
C. Avoidance
D. Transference
Answer: D
Hint: Someone is doing the risky work. Reference: PMP Study Guide, Chapter 11 Study Guide Objective: Monitor All Risks
D is correct because transference is when someone else owns the risk—usually for a
fee. The risk doesn’t go away.
A is incorrect because mitigation is any effort to reduce or eliminate the risk. B
is incorrect because acceptance means just that—the risk has been accepted. C is incorrect
because avoidance is changing the project management plan to avoid the risk altogether.
Q162: Monitoring and Controlling the Project
162. You’ve identified a risk with your project team that may cause major delays in
your project. There’s nothing you can do about the risk, however, because of the nature
of the project work. Which risk response will you likely choose?
A. Acceptance
B. Avoidance
C. Exploit
D. Mitigate
Answer: A
Hint: Not much you can do.
Study Guide Objective: Monitor All Risks
A is correct because you are forced to accept the risk.
B is incorrect because avoidance implies that the risk can be taken out of the project,
but in this instance it cannot because the risk is inherent to the project work. C
is incorrect because exploit is a risk response when the risk is identified as a positive
risk or opportunity. D is incorrect because mitigate is a response to lower or eliminate
the risk impact. In this instance, there’s nothing that can be done about the risk.
Q163: Monitoring and Controlling the Project
163. You are the project manager of a large project for your organization. Management
has just called to let you know that they will be participating in a new risk audit
that will begin next week. What is a risk audit?
A. It is a process to see what risks are within a project.
B. It is a process to determine the risk exposure for a project.
C. It is a process to determine the effectiveness of the risk responses.
D. It is a process to determine the costs of risks.
Answer: C
Hint: Not money.
Study Guide Objective: Monitor All Risks
C is correct because a risk audit determines the effectiveness of risk responses.
A is incorrect because this answer describes the risk identification process. B is
incorrect because this answer describes the risk analysis process. D is incorrect
because this answer describes the expected monetary value performed in quantitative
risk analysis.
Q164: Monitoring and Controlling the Project
164. The largest risk in your project has just occurred. This risk event has depleted
nearly all of your risk contingency reserve. What must happen next?
A. The project must be scrapped.
B. The project must be reviewed for additional risks.
C. The project manager and the project team must complete reserve analysis.
D. The project manager must ask for additional funds.
Answer: C
Hint: Find the problem first.
Study Guide Objective: Monitor All Risks
C is correct because when a risk depletes the contingency reserve, it calls for reserve
analysis in relation to the amount of remaining risks within the project.
A is incorrect because the project likely won’t need to canceled because of the risk
event. B is incorrect because this event is iterative. D is incorrect because there’s
no evidence yet if additional funds are needed.
Q165: Closing the Project
165. Your project just got canceled. You were nearly 60 percent done. What should
happen next?
A. Bill for 60 percent of the contracted fee.
B. Determine why the project has failed.
C. Complete scope verification.
D. Offer your resignation.
Answer: C
Hint: Don’t quit.
Study Guide Objective: Obtain Final Acceptance for the Project
C is correct because even though the project’s been canceled, you need to complete
scope verification.
A is incorrect because the contract for the project will determine what will happen
in this scenario. In addition, internal projects may have no contract. B is incorrect
because there’s no evidence that the project has failed. There could be other reasons
why the project has been canceled, such as advancements in technology or a shift in
the market. D is incorrect because this isn’t valid. It may feel valid, but it’s not
the best choice.
Q166: Closing the Project
166. Marci wants to know the difference between scope verification and quality control.
What’s the difference?
A. QC is concerned with inspection, while scope verification is concerned with the
quality.
B. QC is concerned with the correctness of the deliverables, while scope verification
is concerned with the acceptance of the project scope.
C. QC and scope verification are the same.
D. QC is concerned with the correctness of the deliverables, while scope verification
is concerned with the acceptance of the project deliverables.
Answer: D
Hint: Read carefully.
Study Guide Objective: Obtain Final Acceptance for the Project
D is correct because scope verification is concerned with the acceptance of the project
deliverables.
A is incorrect because this is not a true statement about scope verification. B is
incorrect because this is not a true statement about scope verification. C is incorrect
because while QC and scope verification both rely on inspection, they are not the
same thing. QC happens without the project customers, while scope verification happens
with them.
Q167: Closing the Project
167. You are the project manager of the NHG Project. Your project is to create 8453
custom doorknobs for a hotel. Your project team has completed the work, the customer
has agreed to the project deliverables, and has signed off on the project work. The
customer, however, asks you to drop off the doorknobs to the next project team that
will install the work. You agree to do this. When you deliver the doorknobs to the
next project team, their project manager asks when your team will arrive to help install
the doorknobs. What should you do?
A. Nothing. Your project is done.
B. Nothing. Your project team has moved onto other projects.
C. Complete a change request for the installation of the doorknobs.
D. Consult with the customer to see if they’d like you to help install the doorknobs—for
a fee.
Answer: A
Hint: Done is done.
Study Guide Objective: Obtain Final Acceptance for the Project
A is correct because the project is done.
B is incorrect because, regardless of the team’s status, the project has been completed.
C is incorrect because there’s no need to do a change request—the project is completed.
D is incorrect because your project is done. It’s up to the project manager of the
installation project to request for additional labor if he feels it’s needed.
Q168: Closing the Project
168. You have hired a vendor to complete a project for your organization. The vendor
presents the project as complete but you disagree with the completeness of the project.
What should you do?
A. Create a change request for the vendor.
B. Consult the project sponsor for advice.
C. Reference the details of the contract for the acceptance of the project deliverables.
D. Reference the details of the local law for processes of arbitration.
Answer: C
Hint: A deal’s a deal.
Study Guide Objective: Obtain Financial, Legal, and Administrative Closure
C is correct because the contract stipulates the terms for project acceptance.
A is incorrect because a change request isn’t needed unless you are adding deliverables
to the project scope. B is incorrect because the project sponsor may need to be included
in the discussion, but the best choice is to consult the contract first. D is incorrect
because the contract should be consulted before any options of arbitration.
Q169: Closing the Project
169. A project team has just completed the final work packages for a project. The
project manager needs to find the final CPI for the project. The BAC was $250,000,
but the actual costs came in at $286,000. What’s the final CPI?
A. .87
B. $286,000
C. -$36,000
D. The earned value information is needed to answer this question.
Answer: A
Hint: The project work is 100 percent complete.
Study Guide Objective: Obtain Financial, Legal, and Administrative Closure
A is correct because the CPI is found through the formula EV/AC. In this instance,
the EV is $250,000, which is 100 percent of the BAC because the project is complete.
B is incorrect because this is the final AC for the project. C is incorrect because
this is the cost variance for the project. D is incorrect because the EV information
is supplied in the question.
Q170: Closing the Project
170. A project has just finished the final work packages. Management has deemed that
this project is a failure because the project came in late and over budget. Management
wants to know why the project has failed. Which closing process can answer management’s
question?
A. Scope verification
B. Administrative closure
C. Lessons Learned
D. Contract closeout
Answer: B
Hint: Not a lesson.
Study Guide Objective: Obtain Financial, Legal, and Administrative Closure
B is correct because administrative closure does include analyzing project success
and failure.
A is incorrect because scope verification verifies the project deliverables. C is
incorrect because lessons learned is part of administrative closure, which answers
this question more completely. D is incorrect because there’s no evidence that a contract
was even used in this project. In addition, A answers the question.