|
D
Practice Exam II
|
Q1: Initiating the Project
1. You are a project manager for your company and are helping management choose
a project. You’ve been presented with the following information: Project 1 has a net
present value of $25,000 and will take five years to complete. Project 2 has a net
present value of $45,000 and will take two years to complete. Project 3 has a net
present value of $33,500 and will take six years to complete. Which project should
your company choose to complete?
A. Project 1
B. Project 2
C. Project 3
D. All projects have equal value, so any project is applicable.
Answer: B
Hint: Find the project with the largest return in the shortest amount of time.
Study Guide Objective: Conduct Project Selection Methods
B is correct. The NPV of $45,000 within two years is the greatest investment of capital.
A is incorrect because Project 1 will take five years to complete and has a moderately
low NPV. C is incorrect because Project 3 has a lower NPV than Project 2 and will
take six years to complete. D is incorrect. The projects listed do not have equal
value.
Q2: Initiating the Project
2. You are the project manager for your organization and you’re working with management
to determine the best project for your company. Beth, a manager, has suggested using
linear programming to help determine the best project. Linear programming is an example
of which project selection method?
A. Benefit/cost ratio
B. Constrained optimization
C. The comparative approach model
D. Prioritization
Answer: B
Hint: This method can be complex.
Study Guide Objective: Conduct Project Selection Methods
B is correct. Constrained optimization methods are complex mathematical formulas and
algorithms that are used to predict the success of projects, the variables within
projects, and tendencies to move forward with selected project investments.
A is incorrect because benefit/cost ratios examine the cost to benefits of multiple
projects. C is incorrect. This approach compares the current project to others to
determine the best choice of action. D is also incorrect. Prioritization is the priority
assigned to multiple existing projects within an organization.
Q3: Initiating the Project
3. You are the project manager for your organization and you’re working with your
project team to help coach them on the processes within project management. During
this coaching you explain the difference between constraints and assumptions and how
this affects project initiation. You also explain how long-term projects and short-term
projects may be measured differently during project ignition. In light of this conversion,
customer demands, changes to the marketplace, and opportunity are all examples of
which one of the following?
A. Project constraints
B. Project assumptions
C. Reasons for project initiation
D. The components of a long-term project
Answer: C
Hint: These are all positive inputs.
Study Guide Objective: Conduct Project Selection Methods
C is correct. Projects can be initiated for varying reasons, though the most common
are customer demands, changes to the marketplace, and opportunity.
A is incorrect. These are not examples of project constraints. B is incorrect because
these are not assumptions. D is also incorrect. These examples are not typical components
within a long-term project. They may influence the project and are thus considerations
for the project.
Q4: Initiating the Project
4. Management must choose a project that will be the most profitable. This approach
to project selection is based on which one of the following?
A. Linear programming
B. Capital management
C. The economic model
D. Multiobjective programming
Answer: C
Hint: It’s for the bottom line.
Study Guide Objective: Conduct Project Selection Methods
C is correct. This is a simple economic model for choosing the most profitable project.
A is incorrect. Linear programming is an example of constrained optimization. B is
incorrect because this term is not valid for this question. D is also incorrect. This
is an example of constrained optimization.
Q5: Initiating the Project
5. You are the project manager of the NHJ Project. This project is to create a
new software package for a client. You’re working with the client, business analysts,
software developers, business developers, and the sales team to create the vision
and requirements of the newly initiated project. Of the following, which one determines
the scope of the project?
A. The project manager
B. The project sponsor
C. The performing organization’s management
D. The customer
Answer: D
Hint: This group or person is the most important stakeholder in a project.
Study Guide Objective: Define scope
D is correct because the customer determines the requirements for the project. After
all, the project is completed for the customer.
A is incorrect because the project manager does not determine the requirements, but
instead manages the methods to achieve them. B is incorrect because the project sponsor
does not set the requirements for the project. C is also incorrect. The performing
organization’s management does not set the requirements for the project. Management
may have input to the process, but ultimately the customer sets the requirements of
the project.
Q6: Initiating the Project
6. June is managing a project which was slated to last one year. The project is
now entering its third year. Of the following, which statement is most applicable
to this situation?
A. The project manager must break the project into subprojects.
B. The project scope has not been properly identified.
C. The project team must prevent any changes from entering the project.
D. The project needs to be stopped.
Answer: B
Hint: There is one answer that can apply to all projects.
Study Guide Objective: Define Scope
B is correct. The project scope has likely not been properly identified, so the project
is taking longer than it should.
A is incorrect. There is no evidence in the information presented that the project
should be broken into subprojects. C is incorrect. The project team may not have the
power to approve or disapprove changes. In addition, the question’s information does
not provide adequate information to determine whether changes are the root of the
problem. D is incorrect. There is not enough information presented to determine that
the project should be stopped.
Q7: Initiating the Project
7. You are an IT project manager for your company and are currently defining the
scope for a new project. The CIO defines project success as “implementation of standard
technical components.” The project sponsor, on the other hand, defines project success
as “achieving excellence in technology,” while the project customer defines project
success as “the presence of sales-promoting features.” What should you do as the project
manager?
A. Follow the customer’s opinion. It is their project.
B. Follow the CIO’s opinion. He is in charge.
C. Follow the sponsor’s opinion. He is in charge.
D. Talk with the stakeholders to define the project objectives in measurable metrics.
Answer: D
Hint: Find the opinion that can be measured.
Study Guide Objective: Define Scope
D is correct. Measurable metrics cannot be applied to each of the stakeholders’ comments,
and in order for the project to succeed, measurable metrics are needed.
A is incorrect. The customer did not provide any metrics for the project’s success.
B is incorrect. The CIO did not provide any metrics for the project’s success. C is
also incorrect. The project sponsor did not provide any metrics for the project’s
success.
Q8: Initiating the Project
8. Yolanda is the project manager of the newly initiated PD Project for her company.
She’s working with the project team and the key stakeholders to review the project
requirements and prep for the project scope creation. All of the following documents
are needed to define the project scope except for which one?
A. The project charter
B. The scope management plan
C. The quality management plan
D. Requirements documentation
Answer: C
Hint: Find the plan that doesn’t exist yet. Reference: PMP Study Guide, Chapter 5 Study Guide Objective: Define Scope
C is correct. The quality management plan isn’t needed during scope definition. The
define scope process has four inputs: the scope management plan, project charter,
requirements documentation, and the organizational process assets.
A is incorrect. The project charter is an input to scope definition. B is incorrect.
The project scope management plan is an input to scope definition. D is incorrect.
Requirements documentation is an input to the define scope process.
Q9: Initiating the Project
9. You are the project manager of the PHG project. You and your project team need
to verify a project assumption. Which one of the following can most help with this
process?
A. Constraints
B. Historical information
C. Organizational policies
D. Project team members’ recollections
Answer: B
Hint: Don’t rely on recollections.
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
B is correct. Historical information can most help with project assumptions.
A is incorrect. Constraints will not help the project team verify an assumption. C
is incorrect. Organizational policies will set the confines of the project, but they
will not help the team verify an assumption. D is incorrect. Team member recollections
are not as reliable as historical information since this is an input that is documented.
Q10: Initiating the Project
10. You are the project manager for your organization. You have just been assigned
a new project with a predetermined budget of $250,000. This is an example of which
one of the following?
A. Constraint
B. Assumption
C. Expert judgment
D. Functional structure
Answer: A
Hint: You’re stuck with this amount.
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
A is correct. A predetermined budget is a project constraint.
B is incorrect because this is not an example of an assumption. C is incorrect because
this is not an expert judgment. D is also incorrect because this is not an example
of a functional structure.
Q11: Initiating the Project
11. You have just taken over a failing project. In your initial review of the project
schedule, you realize the previous project manager has made no exceptions for travel
delays. This is an example of which one of the following?
A. Constraint
B. Assumption
C. Schedule variances
D. Critical path activity
Answer: B
Hint: It is not critical.
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
B is correct. The previous project manager has made an assumption that there will
be no delays when project team members travel.
A is incorrect because this is not a constraint. C is incorrect because this is not
a schedule variance, or if it is, there isn’t enough information provided to make
this decision. D is also incorrect because there isn’t enough information provided
to determine that this is a critical path activity.
Q12: Initiating the Project
12. Assumption identification and documentation should happen as early as possible
in the project. This helps the team plan more effectively. All of the following are
assumptions except for which one?
A. Planning on agreeable weather for a construction project
B. Allowing 10 percent of the time for travel delays
C. Planning on completing the project work during daylight hours only
D. A predetermined budget of $125,000
Answer: D
Hint: It is not flexible.
Study Guide Objective: Document Project Risks, Assumptions, and Constraints
D is correct. A predetermined project budget is a cost constraint.
A, B, and C are incorrect because each is an assumption.
Q13: Initiating the Project
13. Stakeholder identification is a process that should start as early as possible
in the project and continue through the project closure. This activity ensures that
stakeholders are engaged and managed throughout the entire project life cycle. When
does a stakeholder exert the most influence over a project?
A. At the project’s start
B. During the project’s execution
C. During the project’s planning phase
D. During the project’s closing phase
Answer: A
Hint: Their influence will diminish as the project moves towards closure.
Study Guide Objective: Identify and Perform Stakeholder Analysis
A is correct. Stakeholders have the most influence on a project’s success at the start
of the project.
B, C, and D are incorrect because all are false statements.
Q14: Initiating the Project
14. You are the project manager of an industrial expansion in your city. Which one
of the following groups could be viewed as a negative stakeholder?
A. The finance department that will pay for the expansion
B. An environmental group that is opposed to expansion
C. The city council that believes the expansion may bring more jobs to the community
D. The change control board for your project because they do not want changes to the
project scope
Answer: B
Hint: They have a negative outlook on your project.
Study Guide Objective: Identify and Perform Stakeholder Analysis
B is correct. Because the environmental group is opposed to your project, they are
viewed as a negative stakeholder.
A is incorrect. The finance department is a stakeholder, but they are likely positive
since they are part of your organization. C is incorrect. The city council is a positive
stakeholder because they are in favor of your project. D is also incorrect. The change
control board is also a stakeholder, but they will likely be positive given they’re
part of your organization.
Q15: Initiating the Project
15. Stakeholder identification is essential to effective project managers. All of
the following are key stakeholders on every project except for which one?
A. The project manager
B. The project management team
C. Influencers
D. Government agencies
Answer: D
Hint: Ask if they are on every project.
Reference: PMP Study Guide, 13
Study Guide Objective: Identify and Perform Stakeholder Analysis
D is correct because government agencies are not key stakeholders on every project.
A is incorrect because the project manager is a key stakeholder on every project.
B is incorrect because the project management team is a key stakeholder on every project.
C is also incorrect because influencers are key stakeholders on every project.
Q16: Initiating the Project
16. You are a project management consultant to the DWD Project. The team on the
project is concerned about stakeholder identification and stakeholder management.
They want to define the roles and responsibilities for stakeholder management. Who
identifies project stakeholders and determines their requirements for the project?
A. The project champion
B. The project team
C. Influencers
D. The project sponsor
Answer: B
Hint: Go for the obvious answer.
Study Guide Objective: Identify and Perform Stakeholder Analysis
B is correct. The project team is responsible for identifying stakeholders and determining
the requirements for the project.
A, C, and D are incorrect because these are all false statements.
Q17: Initiating the Project
17. A project has been initiated to implement quality improvement throughout your
organization. You have been assigned the role of project manager. Which one of the
following is needed first for this quality improvement project?
A. A quality management plan
B. Quality control mechanisms
C. A project charter
D. A communications management plan
Answer: C
Hint: This is always needed.
Study Guide Objective: Develop Project Charter
C is correct because all projects, regardless of their intent, first need a project
charter.
A is incorrect. While a quality management plan will likely be needed, a project charter
comes first. B is incorrect because a project charter is needed before quality controls.
D is also incorrect because a communications management plan will likely be needed,
but only after the project charter has been issued.
Q18: Initiating the Project
18. You are the project manager for your organization and you’re working with management
to ensure that every project in the organization has a standard project charter. What
is the primary concern of a project charter?
A. To authorize the project
B. To identify the project manager
C. To determine the project budget and schedule
D. To launch the project
Answer: A
Hint: You have no power without a charter.
Study Guide Objective: Develop Project Charter
A is correct because all projects, regardless of their intent, first need a project
charter. The charter authorizes the project.
B is incorrect because the primary concern of the charter is not to identify the project
manager. C is incorrect because the project charter does not determine the project
schedule and budget. D is also incorrect. While one could argue that a charter launches
the project, they’d be wrong. The question asks for the primary concern of the charter,
which is to authorize the project.
Q19: Initiating the Project
19. A project charter has been written for your project which spans multiple departments
within your matrix-structured organization. Who should actually charter this project?
A. You, the project manager
B. The functional managers of each affected department
C. An entity outside of the project but within the organization
D. The project management team
Answer: C
Hint: Avoid power struggles.
Study Guide Objective: Develop Project Charter
C is correct because all projects should be chartered and authorized external to the
project and with the power to execute decisions for resources and time.
A is incorrect. The project manager needs authority from a higher entity within the
organization. B is incorrect. There should be one entity that charters the project.
This scenario will likely cause power struggles for the project resources and deliverables.
D is also incorrect because the project management team does not authorize the project.
Q20: Initiating the Project
20. You are a project manager for your organization. One of the managers is refusing
to allow her employees to spend time on your project. Which one of the following is
likely to be missing from your project in this instance?
A. A project manager
B. A risk management plan
C. Project scope
D. A project charter
Answer: D
Hint: You have no authority.
Study Guide Objective: Obtain Project Charter Approval
D is correct. The functional manager is likely not allowing her employees to work
on the project because there is no charter requiring the manager to do so.
A is incorrect because you are the project manager. B is incorrect because the risk
management plan is not applicable to this scenario. C is also incorrect. The project
scope may be missing, but it is not as important as the project charter, which authorizes
the project.
Q21: Initiating the Project
21. As project manager, you will be managing a politically charged and expensive
project. However, you anticipate that managers from around the company will try to
use the project team for their own aims rather than focus on the goal of the project.
Given this, who should charter the project?
A. The project manager
B. The functional manager that is perceived to have the most power
C. An entity that is at an organization level and that is appropriate for authorizing
the project’s funding
D. The primary customer affected by the project’s outcome
Answer: C
Hint: It’s an expensive project.
Study Guide Objective: Obtain Project Charter Approval
C is correct. The project should be charted by an entity outside of the project organization
that can authorize the project funding.
A is incorrect because you are already the project manager. B is incorrect because
the functional manager may not have the authority to authorize resources and funds
for the project. D is also incorrect. The primary customer isn’t always the project
sponsor. In addition, the question does not allude to which customer is affected by
the project the most, so one must consider that the customer could be outside of the
organization altogether.
Q22: Initiating the Project
22. Beth is the project manager of the NQL Project for her company and she’s working
with the project management team to draft the project charter. In Beth’s charter,
she should define all except one of the following in order for the project charter
to be approved. Which one does not need to be defined?
A. The project manager and the authority level
B. Anticipated quality standards
C. Summary milestones
D. A summary budget
Answer: B
Hint: Don’t get too far ahead.
Study Guide Objective: Obtain Project Charter Approval
B is correct. Anticipated quality standards are not part of the project charter requirements.
The project charter should define the project purpose, project objectives, high-level
requirements, assumptions and constraints for the project, risks, project boundaries,
milestones, budget, stakeholder list, approval requirements, project manager, and
the project sponsor.
A is incorrect. The project manager and level of authority is one of the project charter
requirements. C is incorrect because summary milestones is one of the project charter
requirements. D is also incorrect because a summary budget is one of the project charter
requirements.
Q23: Planning the Project
23. You are the project manager for your organization. The ART project, which you
have been working on for the last two months, has a very strict cost constraint, high
requirements for quality, and must be completed within the next eight months. If the
project exceeds its budget by more than 1 percent, management will deem the project
a failure. Changes to your project have caused the project costs to increase slightly,
thereby expanding the project schedule by two weeks. Of the following, which control
mechanism is the most important in this project?
A. Time control
B. Cost control
C. Quality control
D. Scope control
Answer: B
Hint: Determine the project constraint.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
B is correct. The predominant constraint on this project is cost, so cost control
is the best answer.
A is incorrect. While time is important, cost is the defined constraint. C is incorrect.
Quality is always important, but quality is affected by the project’s cost constraint.
D is also incorrect. Scope control is important to a project, but cost control is
of higher importance based on the information that the question provides. While changes
to the scope can affect cost, unacceptable work within the scope can also affect cost.
Q24: Planning the Project
24. A new project is forming to create a new warehouse. The warehouse plans call
for completion within one year if the expected resources are available. Management
requires the in-house development team on this project. The project manager and the
project sponsor, however, feel the available resources are committed to too many other
projects and won’t have adequate availability to the new project. Because of all this,
additional time will be needed in developing which one of the following?
A. A team development plan
B. A resource-limited schedule
C. A procurement management plan
D. A responsibility assignment matrix
Answer: B
Hint: Find what the project needs.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
B is correct. Because the project team is assigned to many different projects and
is not readily available for the project work, the project manager should develop
a resource-limited schedule.
A is incorrect. A team development plan is a subsidiary plan to train the project
team on new or missing skills. C is incorrect because procurement is not an option
in this instance. D is also incorrect because the responsibility assignment matrix
is not needed at this time in the project.
Q25: Planning the Project
25. You are the project manager of the NHQA Project for your company and you’re
working with the functional managers to define all of the needed resources on your
construction project. All of the following are resources except for which one?
A. People
B. Equipment
C. Materials
D. Time
Answer: D
Hint: This element is a constraint.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
D is correct. Time is not a resource since it is necessary to complete the project
work.
A is incorrect because people are resources. B is incorrect because equipment is an
example of a resource. C is also incorrect because materials are resources.
Q26: Planning the Project
26. Henry is the project manager of the GHY Project for his company. He’s working
with the project team to develop a robust project plan for the project. Bethanne,
one of the project team members, doesn’t understand why so much time is needed for
the project plan and wants to get to work on the project more quickly. Harold should
explain that the project plan is used for all except one of the following. Which one
isn’t it used for?
A. Guiding the project’s execution
B. Documenting project planning assumptions
C. Creating methods to assign project resources to stakeholders
D. Facilitating communication among stakeholders
Answer: C
Hint: All projects have assumptions.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
C is correct. The project plan does not provide methods to assign the project resources
to stakeholders.
A is incorrect because the project plan does guide project execution. B is incorrect
because the project plan does guide project planning assumptions D is also incorrect
because the project plan does facilitate communication among stakeholders.
Q27: Planning the Project
27. There are many things you’ll need to plan for in project management, but you’ll
always need to address the Triple Constraints of Project Management. What are the
Triple Constraints of Project Management?
A. Time, cost, and scope
B. Time, schedule, and cost
C. Time, resources, scope
D. Schedule, quality, budget
Answer: A
Hint: This is also known as the Iron Triangle.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
A is correct. The Triple Constraints are time, cost, and scope.
B, C, and D are all incorrect because each is a false statement.
Q28: Planning the Project
28. You must have an engineer on your project for the entire second phase. If you
do not have an engineer available, the project will fail. The demand for the engineer
can best be described as what?
A. An assumption
B. A constraint
C. A risk
D. A staffing issue
Answer: B
Hint: You must have the engineer.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
B is correct because the demand for an engineer is a resource constraint.
A is incorrect because this is not an assumption. C is incorrect. This is not a risk
because the question does not define whether or not the resource is available. Not
enough information is provided in the question to know if there are many engineers
available or none at all. In addition, risk does not answer the question as well as
B does. D is incorrect because this statement is false.
Q29: Planning the Project
29. You and your project team are executing a plan to install a new piece of software
for every computer within your organization. Your project team has discovered that
not all of the computers within the organization can run the new software the way
they had hoped. This is an example of which one of the following?
A. Assumption
B. Constraint
C. Risk
D. Planning
Answer: A
Hint: The team believed it was true even though it wasn’t. Reference: PMP Study Guide,
Chapter 2
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
A is correct. The project team is operating under an assumption that all of the computers
can run the new software.
B is incorrect because this is not a constraint, but an assumption. C is also incorrect.
Though there may be a risk present that the computers may not be able to load and
run the application, initially the project team was operating under an assumption.
D is incorrect as well. This statement is too general and does not answer the question
as well as A does.
Q30: Planning the Project
30. Your project is to build a bridge in your city. The project must be completed
by December 1 or your company will have to pay $10,000 a day in fines. This is an
example of which one of the following?
A. Assumption
B. Critical chain method planning
C. A cost constraint
D. A schedule constraint
Answer: D
Hint: The project must end by December 1.
Study Guide Objective: Define and Record Requirements, Constraints, and Assumptions
D is correct. The project must be completed by December 1, so this is an example of
schedule constraint.
A is incorrect because this is not an assumption. B is incorrect because this answer
is not valid for this question. C is also incorrect because this is not a cost constraint.
The $10,000 penalty is only assessed if the project does not complete on time. In
addition, in some instances it is more cost effective to be late with the project
deliverable, accept the penalty, and deliver a higher-quality project.
Q31: Planning the Project
31. You are the project manager of the AAA project, which requires different skills
by different team members at various times throughout the project. Which of the following
should detail how team members are brought onto, and released from, the project?
A. The procurement management plan
B. The staffing management plan
C. Organizational planning
D. The cost management plan
Answer: B
Hint: As the project manager, you’re not directly interested in financials in this
scenario.
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
B is correct. The staffing management plan details how project team members will be
brought onto the project and excused from it.
A is incorrect. The procurement management plan is not applicable to this question.
C is incorrect. Organizational planning is the process of mapping the project’s roles,
responsibilities, and reporting relationships to the appropriate people or groups
of people. D is incorrect. The cost management plan dictates how cost variances will
be managed.
Q32: Planning the Project
32. Resource planning is an important component of every project. You’ll need to
know when resources are needed, when they’ll be released from the project, and what
the schedule of each resource is. One tool, a resource histogram, can help with project
planning. What is the purpose of a resource histogram?
A. It allows the project manager to identify when workers will be working on particular
project activities.
B. It allows the project manager to determine how many resources are used in a given
month on the project.
C. It allows the project manager to determine the cost of the resources.
D. It allows the project manager to identify slipping resources.
Answer: B
Hint: A histogram shows resource demands.
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
B is correct. Resource histograms are charts that illustrate when workers are used
in a project.
A is incorrect. Resource histograms show collective time, not the time mapped to individual
project activities. C is incorrect. Resource histograms do not map costs to project
activities. D is incorrect. Resource histograms do not identify resources that may
be slipping on activities.
Q33: Planning the Project
33. You are the project manager of the BNH project. You have the following project
team members: Thomas, who’s very excited about the project work and will work overtime
if needed; Emily, who always works overtime; Henry, who’s well liked by the customer
and can work overtime if needed; and Samantha, who always completes the project requirements.
Who is the best project team member for this project?
A. Thomas
B. Emily
C. Henry
D. Samantha
Answer: D
Hint: Get the work done.
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
D is correct. Samantha always completes the project requirements, so she is the best
resource for the project.
A is incorrect. Thomas may be excited and willing, but the question does not indicate
whether he can complete the project requirements. B is incorrect. Emily may work overtime,
but the question does not indicate whether she can complete the project requirements.
In addition, a worker who always works overtime can increase project costs. C is also
incorrect. Henry is well liked by the customer and can work overtime if needed, but
the question does not indicate whether he can complete the project requirements. Unless
the customer asks specifically for Henry—and Henry can complete the project requirements—he
is not needed on the project.
Q34: Planning the Project
34. Projects rely on the project manager to lead and direct the project work and
the project team to execute the project work. Which one of the following will help
a project manager determine which project team members complete activities in a project?
A. Functional managers
B. The responsibility assignment matrix
C. A network diagram
D. The work breakdown structure
Answer: B
Hint: Who does what?
Study Guide Objective: Identify Project Team and Define Roles and Responsibilities
B is correct because the responsibility matrix reveals who does what in a project.
A is incorrect. Functional managers will know what their employees’ roles are in a
project, but it’s likely they won’t be a good resource to find out detailed information.
C is incorrect because network diagrams illustrate the sequence of project activities.
D is also incorrect because the WBS does not map team members to the project components.
Q35: Planning the Project
35. Your organization is launching a new project that is similar to an older project.
Which one of the following can streamline the project planning process?
A. Relying on the project deliverables of the previous project
B. Using the previous project’s risk matrix chart to guide the current project’s risk
management planning session
C. Using the WBS of the previous project as a template for this project’s WBS
D. Reviewing the project’s financial control systems
Answer: C
Hint: Don’t reinvent the wheel.
Study Guide Objective: Create the WBS
C is correct because the WBS of the previous project that’s similar to the current
project is the best choice.
A is incorrect because the deliverable of the previous project won’t help with the
planning of the current project as much as the prior project’s WBS will. B is incorrect.
The previous project’s risk matrix chart may help guide the risk assessment, identification,
and risk response process, but it won’t help the risk management planning session.
Plus, the WBS for the current project is needed as well to complete this process,
so that makes C the better choice. D is incorrect. The financial controls are most
likely universal to all projects within an organization; they don’t simply operate
on a per-project basis. Furthermore, if the projects did have independent financial
controls, the WBS would still be needed to complete cost estimating and budgeting.
Q36: Planning the Project
36. What is the process of subdividing project deliverables into smaller, more manageable
components called? (Choose the best answer.)
A. Decomposition
B. WBS composition
C. Progressive elaboration
D. Work packages
Answer: A
Hint: Mozart used to compose but now he’s participating in this.
Study Guide Objective: Create the WBS
A is correct. The subdivision of project deliverables into smaller, more manageable
components is called decomposition.
B is incorrect because this term is not valid for this question. C is incorrect because
progressive elaboration describes any process that progressively elaborates on its
theme. For example, the concept of building a house may be developed into a sketch,
which is then developed into blueprints, and so on. D is incorrect because work packages
are the smallest item in the WBS.
Q37: Planning the Project
37. You and the project team have just created a WBS for your project. Each item
within the work package is recognized by a unique identifier. Your boss wants to know
where the numbering scheme came from. Which of the following would be the best explanation
to give him?
A. A charter of accounts
B. A code of projects
C. A chart of accounts
D. A code of accounts
Answer: D
Hint: It’s not a charter.
Study Guide Objective: Create the WBS
D is correct because the code of accounts is the unique numbering system for each
element in the WBS.
A is incorrect because this term isn’t valid. B is incorrect because the code of project
is not a valid term. C is also incorrect because the chart of accounts is a numbering
system to track costs by category within the project.
Q38: Planning the Project
38. You are the project manager of the NHQ Project for your company. This project
is to create a new condo building in your city and is scheduled to last for just ten
months.
Your project team has just decomposed all of the project deliverables for their construction
project. What is the document that the decomposition creates?
A. An organizational breakdown structure
B. A work breakdown structure
C. A bill of materials
D. A resource breakdown structure
Answer: B
Hint: This is not a trick question.
Study Guide Objective: Create the WBS
B is correct because the project team has created the work breakdown structure.
A is incorrect. The organizational breakdown structure defines the hierarchy of the
project organization. C is incorrect as well because the bill of materials is a definition
of all the materials required to complete the project work. D is also incorrect because
the resource breakdown structure illustrates the resources used within the project.
Q39: Planning the Project
39. You and your project team are working on the creation of the project’s WBS.
Some of the elements cannot be decomposed until late in the project. What approach
can the project team take in this scenario?
A. Decompose the packages as far as they can based on the current information.
B. Decompose the packages as far as they can based on past projects’ performances.
C. Utilize rolling wave planning.
D. The project work must be fully decomposed in order for the project’s work authorization
system to be active.
Answer: C
Hint: Surf’s up!
Study Guide Objective: Create the WBS
C is correct. The project team should utilize rolling wave planning, which would allow
the project team to revisit the deliverables that need to be decomposed as more information
becomes available.
A is incorrect because this answer does not fully satisfy the question. B is incorrect.
It may be useful to use the WBS of past projects, but this answer assumes that the
past projects are similar. In addition, the question states that some of the deliverables
cannot be decomposed until later in the project duration. D is incorrect because this
is not a true statement.
Q40: Planning the Project
40. You, a project manager, must know all of the components of a project plan and
be able to explain the importance, significance, and depth of each project management
planning component. One document you’ll use often in project planning is the WBS.
What is the smallest item in the WBS called? (Choose the best answer.)
A. A work package
B. A deliverable
C. A project component
D. A leaf object
Answer: A
Hint: You don’t have to wrap this.
Study Guide Objective: Create the WBS
A is correct. The smallest item in the WBS is called the work package.
B is incorrect. This answer may be true, but it is not the best choice for the question.
C is incorrect because this is not the best choice for the question. D is incorrect
because this is not a true statement.
Q41: Planning the Project
41. All except one of the following activities are usually involved in the creation
of the WBS. Which one is the exception?
A. Identifying the deliverables and related work
B. Structuring and organizing the WBS
C. Developing and assigning identification codes to the WBS components
D. Evaluating the project risk components
Answer: D
Hint: This happens later.
Study Guide Objective: Create the WBS
D is correct. Project risk assessment and evaluations come after the WBS has been
created.
A, B, and C are incorrect because each is part of the WBS creation.
Q42: Planning the Project
42. Joan is the project manager of the NQQ Project for her company and she’s working
with the project team to create the work breakdown structure (WBS). What is the purpose
of the WBS? (Choose the best answer.)
A. It identifies the project.
B. It organizes and defines the project scope.
C. It helps the project team visualize the project work.
D. It identifies areas of the project that need more planning.
Answer: B
Hint: It’s the scope.
Study Guide Objective: Create the WBS
B is correct. The WBS organizes and defines the project scope.
A is incorrect because this is not the purpose of the WBS. C is incorrect. Though
the WBS is a visual component, this is not its primary purpose. D is incorrect. This
statement may be true, but this is not the purpose of the WBS.
Q43: Planning the Project
43. You are creating a plan to control how changes to the project scope will be
permitted. Which one of the following would be the name of this plan?
A. The change control system
B. The cost management plan
C. The scope management plan
D. The risk management plan
Answer: C
Hint: Only the required work is needed.
Study Guide Objective: Develop Change Management Plan
C is correct. The scope management plan explains how the project scope will be managed
and how scope changes will be factored into the project plan.
A is incorrect because the change control system (CCS) is the process of how changes
are presented, processed, documented, and managed. B is incorrect because the cost
management plan dictates how cost variances will be managed. D is incorrect because
the risk management plan details how risks are planned for and responded to.
Q44: Planning the Project
44. Your project is not costing as much as you predicted. If you do not use your
entire budget allotment for the first phase of the project, you will receive a budget
reduction for the second phase of your project. You elect to order slightly better
materials that will provide a higher product for the customer, but that will also
allow you to meet the predicted budget for this phase of the project. This condition
is best described as which one of the following?
A. Effective cost management
B. Integrated change control
C. Gold plating
D. Parkinson’s Law
Answer: C
Hint: Don’t deliver more than what is needed.
Study Guide Objective: Develop Change Management Plan
C is correct. When a project manager delivers higher-grade materials than what is
needed to drive up the price of the project, this is known as gold plating. It is
not an effective project management method.
A is incorrect because this is not effective cost management. B is incorrect. Integrated
change control is the process of integrating changes across the entire project. D
is also incorrect because this is not Parkinson’s Law. Parkinson’s Law states that
work will expand to fulfill the time allotted to it.
Q45: Planning the Project
45. The project manager reports that the project is progressing according to scope.
Management asks to change a few requirements with the scope. Which plan details how
requirements will be analyzed, documented, and managed in the project?
A. The scope management plan
B. The change control system
C. The communications management plan
D. The requirements management plan
Answer: D
Hint: Manage the requirements.
Study Guide Objective: Develop Change Management Plan
D is correct. The requirements management plan defines everything when it comes to
identifying, documenting, and controlling project requirements.
A is incorrect because the scope management plan defines just the details of the project
scope and how it is defined and controlled. B is incorrect because the change control
system is the process for all of change management. C is also incorrect because the
communications management plan does not detail how changes to the scope will be documented.
Q46: Planning the Project
46. You are the project manager of a large construction project you are completing
for another organization. You and the project team have finished the requirements
gathering process and are creating the work breakdown structure for the project. The
customer informs you, however, that they need to increase the size of the building
by 10,000 square feet. They are willing to accept the fee and time schedule change.
What must happen next?
A. The project scope must be revised.
B. The project must be started over.
C. Nothing. The project manager can add the 10,000 square feet to the WBS.
D. The change must be managed through the cost control system.
Answer: A
Hint: The project is still early on in the planning process group.
Study Guide Objective: Develop Change Management Plan
A is correct. Revisions are a special type of project schedule change, and cause the
project start date and, more likely, the project end date to be changed. Revisions
typically stem from project scope changes.
B is incorrect. The project has really just started because the WBS hasn’t even been
created yet. Thus, it isn’t necessary to scrap the project and start over at this
point. C is incorrect. The project manager cannot simply add the additional requests
into the WBS. They must be added to the project scope, documented, planned for, and
then migrated into the WBS. D is also incorrect. A cost control system may not be
created at this point. In addition, the project is being completed for another entity
and they demand the change.
Q47: Planning the Project
47. You are the project manager of a large construction project. You and your project
team are planning a method to control changes during the construction project, and
both of you realize that changes often happen in the field—changes that may be different
than what the blueprints in the office reflect. The goal of your planning activity
is a way to track actual changes in the field and reflect those changes in the blueprints
in the office. You want consistency between what’s actually being constructed and
what the blueprints in the office reflect. What is this process called? (Choose the
best answer.)
A. Project management planning
B. Change assessment
C. Scope validation
D. Configuration management
Answer: D
Hint: You want consistency.
Study Guide Objective: Develop Change Management Plan
D is correct. This is an example of configuration management, which seeks consistency
in tracking and monitoring approved changes in a project.
A is incorrect. Though this is part of project planning, it does not fully answer
the question. B is incorrect. This is not a valid choice for this question because
no changes have been proposed yet; the project team is simply planning on how configuration
management should work within their project. C is incorrect. Scope validation happens
with the customer and seeks acceptance of the project work.
Q48: Planning the Project
48. In most projects, change is inevitable. Changes must be considered for their
impact on the project as a whole, documented, and tracked throughout the entire project.
Which system would track how project deliverables are controlled, changed, and approved?
A. The change control system
B. The project management information system
C. The change management system
D. The scope management system
Answer: A
Hint: Protect the scope.
Study Guide Objective: Develop Change Management Plan
A is correct. The change control system seeks to control how deliverables are controlled,
changed, and approved.
B is incorrect because this is not a valid answer for this question. C is incorrect
because this, too, is not a valid answer for this question. D is also incorrect because
this is not a valid answer for this question as well.
Q49: Planning the Project
49. Kevin is the project manager of the BQA Project for his organization and he’s
working with management and the project team to define the change control system.
All of the following activities should be planned as part of the change control system
except for which one?
A. Methods to identify that a change has occurred (or must occur)
B. The process for reviewing and approving requested changes
C. A method for documenting the impact of requested changes
D. A methodology to track team personnel changes
Answer: D
Hint: Focus on the project scope.
Study Guide Objective: Develop Change Management Plan
D is correct. Changes to the team personnel are not part of the change control system.
A, B, and C are incorrect. Neither of them is a valid answer for the question because
each is part of the change control system.
Q50: Planning the Project
50. You and the project team are creating the change control system for your project.
Marcy, a project team member, wants to know why there is so much emphasis on creating
and documenting the change control system. Which one of the following is the best
answer to Marcy’s query?
A. A documented change control system is required by management.
B. A documented change control system is required by the project customer.
C. A documented change control system allows the project to improve because the impact
of each change must be considered before it is approved.
D. A documented change control system allows the project’s profitability to improve
because each change may affect the profit and loss of the project.
Answer: C
Hint: Improvement
Study Guide Objective: Develop Change Management Plan
C is correct. A change control system requires that each change request be evaluated
and its impact on the project considered before approving the change request.
A is incorrect. While this is likely true in many organizations, it is not the best
answer for this question. B is also incorrect. The project customer may not know or
realize that a change control system exists. In addition, this is not the best answer
for Marcy’s question. D is incorrect as well. This is not a valid answer for this
question because not every project has a profit and loss statement (consider micro
projects and not-for-profit endeavors).
Q51: Planning the Project
51. You are the project manager of the Absolute Quality Company. You are working
with your project team to determine the best approach for identifying and analyzing
project risks. Which of the following is not a risk diagramming technique?
A. Influence diagrams
B. A network diagram
C. A process flowchart
D. Cause-and-effect diagrams
Answer: B
Hint: Think activity on the node. Reference: PMP Study Guide, Chapter 11
Study Guide Objective: Identify Risks and Define Risk Strategies
B is correct because a network diagram does not help identify risks but is instead
a tool used in activity sequencing to identify precedents and dependencies.
A is incorrect because influence diagrams are graphical representations showing causal
influences and can help identify risks. C is incorrect because process flowcharts
show how elements of a system interrelate and can help identify risks. D is incorrect
as well. Cause-and-effect diagrams are also known as Ishikawa or fishbone diagrams
and can help identify risks.
Q52: Planning the Project
52. Risks should be identified as early as possible in the project and then analyzed
and tracked for their outcomes and in-depth planning. The risk register contains all
but one of the following. Which doesn’t it include?
A. Qualitative risk analysis
B. Root causes of risks
C. Updated risk categories
D. A list of potential responses
Answer: A
Hint: Not the preliminaries.
Study Guide Objective: Identify Risks and Define Risk Strategies
A is correct because qualitative risk analysis is not contained in the risk register.
B is incorrect because root causes of risks describe the fundamental conditions or
events that give rise to the risk, and are included in the risk register. C is incorrect
because the process of identifying risk can lead to new categories of risk and these
are included in the risk register. D is also incorrect. Potential responses may be
identified during the risk identification process and are included in the risk register.
Q53: Planning the Project
53. You are the project manager of the GGJ Project and you’re working with your
project team to create the project’s risk management plan. Which one of the following
items is NOT part of the risk management plan?
A. Budgeting
B. Risk categories
C. The risk register
D. Methodology
Answer: C
Hint: This should register with you.
Study Guide Objective: Identify Risks and Define Risk Strategies
C is correct. The risk register is not part of the risk management plan but rather
the output of the risk identification process.
A is incorrect because it assigns resources and cost estimates for risk management
activities and is therefore part of the risk management plan. B is incorrect because
risk categories provide a structure that ensures a comprehensive process to identify
risks to a consistent level of detail and is, therefore, part of the risk management
plan. D is incorrect because a methodology defines the approach, tools, and data sources
that will be used to perform risk management and is thus part of the risk management
plan.
Q54: Planning the Project
54. As the project manager of a new project, the sponsor thinks that there may be
unidentified risks in the project. Which of the following items is not an input to
the risk identification process?
A. Organizational process assets
B. Pareto charts
C. The project scope statement
D. The risk management plan
Answer: B
Hint: 80/20.
Study Guide Objective: Identify Risks and Define Risk Strategies
B is correct. While Pareto charts are useful for quality control, they are not specific
inputs to the risk identification process.
A is incorrect. Organizational process assets are an input to risk identification
because information on prior projects may be available, including actual data and
lessons learned. C is incorrect. The project scope statement is an input to risk identification
because any uncertainty in project assumptions should be evaluated as a potential
cause of risk. D is incorrect. The risk management plan is a key input to risk identification,
including roles and responsibilities, provisions for risk management activities in
the budget and schedule, and categories of risk.
Q55: Planning the Project
55. Barry is working with his project team and key stakeholders to identify project
risks. Which of the following items is a tool or technique for risk identification?
A. Control charts
B. Defect repair review
C. A strength, weakness, opportunities, and threats (SWOT) analysis
D. A product analysis
Answer: C
Hint: Not a police force.
Study Guide Objective: Identify Risks and Define Risk Strategies
C is correct. This technique ensures examination of the project from each of the SWOT
perspectives to increase the breadth of considered risks. It is therefore an effective
risk identification technique.
A is incorrect. The purpose of control charts is to determine whether or not a process
is stable, or has predictable performance. Thus, it is not a risk identification technique.
B is incorrect. Defect repair review is an action taken by the quality control department
to ensure defects are repaired. It is therefore not a risk identification technique.
D is also incorrect. Product analysis uses techniques like product breakdown to help
define the scope of a project rather than identify risks.
Q56: Planning the Project
56. You are the project manager of the new server project for your company. This
project will replace 128 network servers on your company’s network. Your project sponsor
has requested that you keep her informed of the outcomes of the quantitative risk
analysis process. Which of the following is a common quantitative risk analysis technique?
A. Risk categorization
B. Expected monetary value analysis
C. A probability-impact matrix
D. A risk register
Answer: B
Hint: EMV.
Study Guide Objective: Identify Risks and Define Risk Strategies
B is correct. Expected monetary value analysis is a statistical concept that calculates
the average outcome when the future includes scenarios that may or may not happen.
Therefore, it is a quantitative analysis technique.
A is incorrect. Risk categorization determines areas of the project most exposed to
the effects of uncertainty, but it is not a quantitative analysis technique. C is
incorrect because this matrix prioritizes risks for further quantitative analysis.
D is incorrect because the risk register is an output of the risk identification process
and is not a quantitative analysis technique.
Q57: Planning the Project
57. Which quantitative analysis diagramming technique can help the project manager
make the best decision by evaluating a situation and the implication of each variable?
A. Alternatives identification
B. The precedence diagramming method
C. The arrow diagramming method
D. A decision tree
Answer: D
Hint: The root of the matter.
Study Guide Objective: Identify Risks and Define Risk Strategies
D is correct. This is a decision tree diagram that describes a situation and the implications
of each of the available choices with the costs and rewards of each choice.
A is incorrect. Alternatives identification is a technique used to generate different
approaches to perform the work of the project rather than a quantitative risk analysis
technique. B is incorrect. The precedence diagramming method is a way to construct
the project schedule and thus is not a quantitative risk analysis technique. C is
incorrect. The arrow diagramming method is a way to construct the project schedule
network diagram and is therefore not a quantitative risk analysis technique.
Q58: Planning the Project
58. Which risk diagramming technique can help predict project cost based on probability
and cost of risk?
A. Cost simulation
B. The Pareto chart
C. An Ishikawa diagram
D. A decision tree
Answer: A
Hint: Avoid the quality tools.
Study Guide Objective: Identify Risks and Define Risk Strategies
A is correct. Through numerous iterations, this chart describes the cumulative distribution
of results from a cost simulation.
B is incorrect because a Pareto chart is a quality control technique. C is incorrect
because an Ishikawa diagram is used for root cause analysis rather than quantitative
risk analysis. D is also incorrect because a decision tree diagram is a quantitative
risk analysis technique, but this is not what is shown in the diagram.
Q59: Planning the Project
59. You and your project team have just created the proposed project plan, but your
functional manager disagrees with you on many areas of it. Because you are operating
in a functional environment, you’d like some compromise with your functional manager.
Which individual has the power in a functional organization?
A. The project manager
B. The customer
C. The functional manager
D. The program manager
Answer: C
Hint: This organizational structure limits the project manager’s autonomy.
Study Guide Objective: Obtain Plan Approval
C is correct. The functional manager has the power in a functional organization.
A is incorrect. The project manager has limited power in a functional organization
and may even be known as a project coordinator or team leader. B is incorrect. Although
the customer sets the project requirements, they have little project management authority.
D is incorrect because a program manager won’t likely exist in a functional organization.
Q60: Planning the Project
60. Your project plan may not be approved due to the amount of working capital your
project would require to move into execution. Working capital is defined as which
one of the following?
A. Funds that have been invested into a project that is failing to meet performance
objectives
B. Funds available to invest in a new project
C. Funds the project will generate before the project is even completed
D. The amount of funds the monies would have earned if they were invested in a savings
account rather than in a project
Answer: B
Hint: Companies put their money to work.
Study Guide Objective: Determine Resource Requirements
B is correct. Working capital is the money an organization has to run the business
and invest in new opportunities—which includes projects.
A is incorrect. This explanation describes sunk costs. C is incorrect. This explanation
describes the return on investment for the project. D is incorrect. This explanation
describes the time value of money.
Q61: Planning the Project
61. You and your project team have just created the proposed project plan, but a
functional manager disagrees with you on many areas of it. Because you are operating
in a strong matrix environment, you’d like some compromise with your functional manager.
Which individual has more power in a strong matrix organization?
A. The project manager
B. The customer
C. The functional manager
D. The program manager
Answer: A
Hint: Strong is good for the project manager. Reference: PMP Study Guide, Chapter 2
Study Guide Objective: Obtain Plan Approval
A is correct. The project manager has the power in a strong matrix organization.
B is incorrect. Although the customer sets the project requirements, they have little
project management authority. C is incorrect because the functional manager has limited
power in a strong matrix organization. D is incorrect because a program manager may
not even exist in a strong matrix organization.
Q62: Planning the Project
62. Alice is the project manager of the LAB Project for her company. She’s working
with her project team to create the project management plan. Which of the following
statements about the project plan is true?
A. A project plan is not needed for all projects.
B. A project plan cannot be changed during the project implementation.
C. Management must approve the project plan.
D. Customers have the final say regarding the project plan’s approval.
Answer: C
Hint: All projects require this.
Study Guide Objective: Obtain Plan Approval
C is correct. Management must approve all project plans.
A is incorrect. All projects need a project plan. B is incorrect. Project plans can,
and often are, changed during project implementation. D is incorrect. Customers have
input, but not the final say on a project plan’s approval.
Q63: Planning the Project
63. Why should the project manager and the project team invite the stakeholders
to participate in the project planning sessions?
A. Actually, the project stakeholders should not be involved in the project planning
because their presence may stifle creativity among the project team members.
B. The project stakeholders are usually the individuals that are paying for the project
work, so they should be involved in the planning sessions.
C. The project stakeholders must be present to monitor the planning sessions in case
the project team moves away from their requirements. This way they can correct the
discussion and keep the planning on track for their deliverables.
D. The stakeholders have skills and knowledge that can be leveraged in developing
the project plan.
Answer: D
Hint: Use the stakeholders’ knowledge.
Study Guide Objective: Obtain Plan Approval
D is correct. Stakeholders have skills and knowledge that can be leveraged in developing
the project plan.
A is incorrect because this isn’t true. B is incorrect. While this statement may be
true in many instances, it is not the best reason to involve stakeholders in the project
planning sessions. C is also incorrect. This is not true because the goal of involving
stakeholders is to use their knowledge about the deliverable they want, not to direct
the project team in their discussion on how to best create the deliverables.
Q64: Planning the Project
64. Your project is just beginning and you have invited all of the key stakeholders,
the project team, and members of management to participate in an initial meeting.
What is this type of meeting called?
A. A requirements gathering meeting
B. A risk identification meeting
C. A kick-off meeting
D. A team development meeting
Answer: C
Hint: Get going.
Study Guide Objective: Conduct Kick-Off Meeting
C is correct. A project kick-off meeting gets the project moving and identifies the
individuals involved in the project.
A is incorrect. This is not the requirements gathering meeting, though project requirements
may be touched on. B is incorrect because this is not a meeting for risk identification.
D is also incorrect because this is not a team development meeting.
Q65: Planning the Project
65. You are the project manager for your company and you’ve recently been assigned
to a new high-profile project. When should the project kick-off meeting happen?
A. When the project manager has the project team assembled for the first time
B. When the project manager has approved the project plan
C. When management has approved the initial project plan
D. At the start of scope validation
Answer: C
Hint: Get going.
Study Guide Objective: Conduct Kick-Off Meeting
C is correct. The project kick-off meeting happens after the initial project plan
has been approved.
A is incorrect because this does not answer the question as well as C. B is incorrect
because the project manager does not necessarily approve the project plan—management
does. D is incorrect because this is not a valid statement because scope validation
is an inspection-drive process that aims for the project customer to accept the project
work.
Q66: Planning the Project
66. You are the project manager for your company and you’re managing a new project.
You want to schedule a kick-off meeting but your project sponsor doesn’t want to do
this. Why should you host a kick-off meeting?
A. It allows all the stakeholders to meet.
B. It allows the project to begin.
C. It ensures that all of the participants understand the project’s purpose.
D. It builds morale for all of the stakeholders.
Answer: C
Hint: Seek understanding.
Study Guide Objective: Conduct Kick-Off Meeting
C is correct. The project kick-off meeting happens so that the participants can all
understand the project’s purpose.
A is incorrect because while this may be a true statement for many projects, it is
not the primary purpose of the project’s kick-off meeting. B is incorrect because
the project charter is technically what launches the project, not the kick-off meeting.
D is incorrect because this is not the primary purpose of the project’s kick-off meeting.
Q67: Planning the Project
67. Beth wants to host a project kick-off meeting for her new project. Which of
the following is false about the project kick-off meeting?
A. It allows all the stakeholders to meet one another.
B. Only the project team should attend.
C. It ensures that all of the participants understand the project’s purpose.
D. It builds morale for all of the stakeholders.
Answer: B
Hint: Don’t leave anyone out.
Study Guide Objective: Conduct Kick-Off Meeting
B is correct. All of the key stakeholders should attend the project kick-off meeting,
not just the project team.
A is incorrect because this is true of the project kick-off meeting. C is incorrect
because this is true of the project kick-off meeting. D is incorrect because this
is true of the project kick-off meeting.
Q68: Executing the Project
68. A project manager has added time between two activities. This is an example
of which one of the following?
A. Lag
B. Lead
C. Crashing
D. Fast tracking
Answer: A
Hint: It’s waiting time.
Study Guide Objective: Execute Tasks Defined in the Project Plan
A is correct. Lag time is waiting time. When a project manager adds times between
activities, he is adding lag.
B is incorrect. Lead is subtracting time between activities. C is incorrect because
crashing adds resources to activities so they can finish faster. D is incorrect because
fast tracking changes the relationship between activities so they can finish faster.
Q69: Executing the Project
69. You are working with a vendor that is completing some of the project activities.
Some of the vendor’s activities are on the critical path. Which one of the following
statements about the critical path is true?
A. The critical path is the path with the most activities.
B. The critical path is the path with zero float.
C. The critical path is the path with the least lag.
D. The critical path is the path with critical activities.
Answer: B
Hint: All projects have a critical path.
Study Guide Objective: Execute Tasks Defined in the Project Plan
B is correct. The critical path is the path with zero float.
A is incorrect. A path can have many activities and not be the critical path. C is
also incorrect. While lag can increase a project’s duration, a path with the least
lag does not make it the critical path. D is incorrect because this is not a valid
answer.
Q70: Executing the Project
70. You are a project manager for your organization and are working on assigning
project team members to activities. You must complete an activity by a predetermined
date. Currently, with four project team members assigned to the activity, the work
will take 40 hours. You know that by adding eight project team members to the work,
the task won’t necessarily be reduced to 20 hours. This is because of which one of
the following?
A. Herzberg’s Theory of Motivation
B. The law of diminishing returns
C. Parkinson’s Law
D. Theory Z
Answer: B
Hint: You can only get so much wheat from a wheat field.
Study Guide Objective: Execute Tasks Defined in the Project Plan
B is correct. The law of diminishing returns affects the yield of work in relation
to work duration.
A is incorrect because Herzberg’s Theory of Motivation deals with hygiene agents and
motivating agents. C is incorrect because Parkinson’s Law states that work will expand
to fulfill the time allotted to it. D is also incorrect because Ouchi’s Theory Z believes
in cooperative management.
Q71: Executing the Project
71. You are the project manager of a two-year project for your company. You’re working
with the project team to identify the constraints and assumptions of the project.
Your project sponsor comes to the analysis meeting and wants to know when the largest
percentage of the project budget will be spent. What should you tell the project sponsor?
A. During the initiation processes
B. During the planning processes
C. During the execution processes
D. During the control processes
Answer: C
Hint: Do the project work.
Study Guide Objective: Execute Tasks Defined in the Project Plan
C is correct. The largest percentage of the project budget will be spent during the
project execution processes.
A is incorrect. The initiation processes do not require the bulk of the project budget.
B is incorrect because the planning processes do not require the bulk of the project
budget. D is also incorrect because the control processes do not require the bulk
of the project budget.
Q72: Executing the Project
72. You are the project manager of an interior decorating project. Currently, the
project plan calls for the painter to prime the walls for painting, wait four hours
for the walls to cure, and then begin the painting process. However, due to humidity,
the walls are taking four hours longer to cure than planned. The painting activities
are on the critical path. Which one of the following is an acceptable solution for
this problem that won’t change the project end date?
A. Add lead time to the painting activity.
B. Add lag time to the painting activity.
C. Change the relation of other activities so the primer can cure faster.
D. Examine the network diagram to determine if the relationships between activities
can be changed. If so, move the painting activities to later in the project.
Answer: D
Hint: The critical path has no slack.
Study Guide Objective: Execute Tasks Defined in the Project Plan
D is correct. Because the critical path cannot be expanded, the only logical choice
is to attempt to move the activities to later in the project. The project team should
focus on other activities while the primer cures.
A is incorrect because lead time subtracts time from the scheduled start time of activities.
B is incorrect. Lag time will increase the time of the painting activities. C is also
incorrect because changing the relationship of activities will not help the primer
cure faster.
Q73: Executing the Project
73. You are the project manager of a building restoration project. You have elected
to add more workers to an activity on the critical path so the project can finish
on time. This is an example of which one of the following?
A. Risk management
B. Time management
C. Crashing
D. Fast tracking
Answer: C
Hint: You should hope the workers don’t “bump” into each other.
Study Guide Objective: Execute Tasks Defined in the Project Plan
C is correct. Crashing allows the project manager to add resources to an activity
to complete it faster. This does not always work because some activities have a fixed
duration.
A is incorrect. This is not risk management. Fast tracking, not crashing, introduces
new risk for projects. B is incorrect because this is not an example of time management.
D is also incorrect. Fast tracking allows activities that should start in succession
to overlap so the project may finish sooner. Fast tracking may also use lead time.
Q74: Executing the Project
74. You are the project manager of a project to create a training manual. The project
is running late. You elect to change the relationship of several activities from finish-to-start
to start-to-start so the project may complete on schedule. This is an example of which
one of the following?
A. Crashing
B. Fast tracking
C. Rolling wave planning
D. Expert judgment
Answer: B
Hint: Don’t make waves.
Study Guide Objective: Execute Tasks Defined in the Project Plan
B is correct. Fast tracking changes the relationships of activities so the project
may finish sooner than expected.
A is incorrect. Crashing allows the project manager to add resources to the project
work in order to complete it sooner than expected. C is incorrect. Rolling wave planning
allows planning to be completed based on the conditions within the project in waves
or successions. D is also incorrect because this is not an example of expert judgment.
Q75: Executing the Project
75. Ned is the project manager of the NQA Project and he’s using earned value management
to show project performance. He learns, however, that his project has an SPI of .80.
A project with an SPI of .80 means what?
A. The project is behind schedule.
B. The project is ahead of schedule.
C. The project is losing money.
D. The project is 80 percent complete.
Answer: A
Hint: SPI is the schedule performance index.
Study Guide Objective: Execute Tasks Defined in the Project Plan
A is correct. A schedule performance index of .80 means the project is behind schedule.
The closer to “1” the SPI is, the better the project.
B is incorrect because an SPI of .80 means the project is behind schedule, not ahead.
C is also incorrect. While the project likely will result in being over budget due
to the labor demands to complete the project, the SPI deals with the project schedule.
D is incorrect as well since an SPI does not reflect the percentage complete of the
project.
Q76: Executing the Project
76. A project is moving toward completion. Janet, an engineer on the project, has
identified a risk that can cause the project to stop if the pressure in a valve goes
below 80 percent. The 80 percent pressure is known as what?
A. Risk
B. The management horizon
C. Risk impact
D. The threshold
Answer: D
Hint: You don’t want to cross this.
Study Guide Objective: Ensure Common Understanding and Set Objectives
D is correct because the 80 percent mark is known as a threshold.
A is incorrect because the 80 percent mark is not the risk. The risk comes after the
threshold is passed. B is incorrect because the management horizon is the point in
time when the project has paid for the investment. C is also incorrect because risk
impact is the affect the risk event has on the project’s success.
Q77: Executing the Project
77. The first phase of a project has been completed. The project manager reports
the results of the project to management and they elect to stop the project. The end
of the first phase of completion is also known as which one of the following?
A. The kill point
B. Progressive elaboration
C. Rolling wave planning
D. Project scheduling
Answer: A
Hint: The project can die here.
Study Guide Objective: Ensure Common Understanding and Set Objectives
A is correct. Based on the end result of a phase, management or the customer may elect
to kill a project.
B is incorrect. Progressive elaboration is the refinement of the project concept as
the project progresses. C is incorrect. Rolling wave planning is the successions of
planning that happen throughout a project based on conditions and results of the project
work. D
is incorrect because this is not an example of project scheduling. Q78: Executing
the Project
78. Which of the following can best be used to determine the true progress of a
project?
A. Variance reports
B. Baselines
C. Change requests approved versus declined
D. Interviews with the project team
Answer: B
Hint: These predict.
Study Guide Objective: Ensure Common Understanding and Set Objectives
B is correct because baselines can be used to compare what is actual against what
was predicted.
A is incorrect because variance reports don’t necessarily reflect project progress.
C is incorrect because change requests do not reflect the progression of a project.
D is also incorrect because interviews with the project team may not reflect the project’s
overall progress.
Q79: Executing the Project
79. A performance report leads to a change request. Which one of the following is
the most likely reason why a performance report can lead to a change request?
A. The project is not performing well, so a change request is made to cancel the project.
B. The project is not performing well, so a change request is submitted to the project
manager.
C. The project is not performing well, so a change request is made to remove the project
manager and replace him with a more experienced project manager.
D. The project is performing well, so additional requirements are added to the project
scope.
Answer: B
Hint: Correct the problem before adding anything new.
Study Guide Objective: Ensure Common Understanding and Set Objectives
B is correct. When a project is going badly, operating beyond its budget, or off schedule,
changes may be made to reduce the project scope or to add quality activities to ensure
the product is correct.
A is incorrect. Projects are not canceled via change requests. C is incorrect. Change
requests are not made for administrative changes. D is also incorrect. A well-performing
project should stay on course with no changes to project scope.
Q80: Executing the Project
80. Management wants to know how long the project work will take. The project manager
uses a similar project to predict the duration of the current project work. The project
manager is using which form of estimating?
A. Parametric
B. Analogous
C. Bottom-up
D. Expert judgment
Answer: B
Hint: You don’t have to be an expert to use this method.
Study Guide Objective: Ensure Common Understanding and Set Objectives
B is correct. Because the project manager is using another similar project to predict
the duration of the current project, he is using the analogous method.
A is incorrect because parametric estimating is based on parameters, such as units,
metric tons, and so on. C is incorrect. Bottom-up estimates start at zero and take
in all costs for each activity. D is also incorrect because this is not the best answer
for the question.
Q81: Executing the Project
81. Quality assurance is needed in every project based on your organizational process
assets and enterprise environmental factors. Which of the following statements best
defines quality assurance?
A. Work results are monitored to see if they meet relevant quality standards. If the
results do not meet the quality standards, the project manager applies root cause
analysis to determine the cause of the poor performance and then eliminates the cause.
B. The overall performance is evaluated to ensure the project meets the relevant quality
standards.
C. The project performance is measured and evaluated, and corrective actions are applied
to improve the product and the project.
D. It is an international standard that helps organizations follow their own quality
procedures.
Answer: B
Hint: Organizational standards apply for all projects.
Study Guide Objective: Ensure Common Understanding and Set Objectives
B is correct. Quality assurance maps to an organization’s quality policy and is typically
a managerial process.
A is incorrect because this statement defines quality control. C is incorrect because
this statement defines quality improvement. D is also incorrect because this statement
defines ISO 9000.
Q82: Executing the Project
82. You are preparing for quality assurance with your quality department and the
project team. Which of the following tools cannot be used with quality assurance?
A. Herzberg’s Theory of Motivation
B. Benefit cost analysis
C. Flowcharting
D. Design of experiments
Answer: A
Hint: Agents aren’t helpful here.
Study Guide Objective: Ensure Common Understanding and Set Objectives
A is correct. Herzberg’s Theory of Motivation is based on motivating agents and hygiene
agents and is not applied to quality assurance.
B is incorrect because benefit cost analysis can be applied to quality assurance.
C is incorrect because flowcharting can be applied to quality assurance. D is also
incorrect. Design of experiments is a tool that can be applied to quality assurance.
Q83: Executing the Project
83. Your project is running late and you need to make a decision about whether you
should purchase a piece of software or have your project team build the software.
Thus, you need to complete a make-or-buy analysis for a procurement decision. In which
process is the make-or-buy analysis used?
A. Contract closeout
B. Source selection
C. Purchase planning
D. Initiating
Answer: C
Hint: You’ve made no decisions yet.
Study Guide Objective: Implement the Procurement of Project Resources
C is correct. You are creating a make-or-buy analysis to determine the need to complete
the work in-house or send the work to a vendor. At this point in the project, you
are completing procurement planning.
A is incorrect. This is not done in contract closeout. B is incorrect because source
selection will happen if the decision is made to buy the product or service. D is
incorrect because solicitation will happen if the result of the analysis is to buy
the project or service from a vendor.
Q84: Executing the Project
84. Management has demanded a change to your project scope but this change has a
risk that management is not willing to accept. They recommend you buy errors and omissions
insurance. This is an example of which one of the following?
A. Mitigation
B. Transference
C. Avoidance
D. Countermeasure
Answer: B
Hint: Someone else owns the risk responsibility.
Study Guide Objective: Implement the Procurement of Project Resources
B is correct because purchasing insurance as a response to a risk is transference.
A is incorrect because mitigations are actions taken to reduce the impact or probability
of a risk event. C is incorrect because avoidance avoids the project risk. D is also
incorrect because countermeasures are actions taken to neutralize the risk impact.
Q85: Executing the Project
85. You are a project manager for your organization. You have procured four staff
members from a vendor to help with the project work. Two of these staff members are
no longer needed on the project. Which document will determine how the procured project
team members may be excused from the project?
A. The contract between your organization and the vendor
B. The staffing management plan
C. The scope management plan
D. The schedule management plan
Answer: A
Hint: There is a buyer and a seller.
Reference: PMP Study Guide, Chapter 12 introduction
Study Guide Objective: Implement the Procurement of Project Resources
A is correct. The contract will determine how long the project team members will be
allowed to, or are required to, stay on the project.
B is incorrect. The staffing management plan will concur with the contract details
to determine how procured resources are released from the project. C is incorrect
because the scope management plan determines how the project scope may be changed.
D is incorrect because the schedule management plan determines how changes to the
schedule will be managed.
Q86: Executing the Project
86. You are hosting a bidder’s conference. Which one of the following is the best
approach in managing the session?
A. Require all vendors to present their pricing information during the session.
B. Allow vendors time to ask questions to clarify the project requirements.
C. Allow vendors time to negotiate the pricing.
D. Allow the contract manager to negotiate with the bidders.
Answer: B
Hint: Be fair.
Study Guide Objective: Implement the Procurement of Project Resources
B is correct. Vendors should have ample time to ask questions to clarify the project
requirements.
A is incorrect. Vendors likely will not have pricing information during the bidder’s
conference. C is incorrect because vendors will not negotiate pricing in the conference.
D is also incorrect because the contract manager may handle negotiations with bidders,
but the negotiation process does not happen at the bidder’s conference
Q87: Executing the Project
87. You are the project manager of a construction project. You have procured an
electrician to complete the wiring for the project. The electrician reports that he
is finished with the services you have hired him to complete. Which one of the following
must you do next in regard to the electrician?
A. Complete the invoice
B. Pay the invoice
C. Inspect the work results
D. Sign off on the work
Answer: C
Hint: Only sign off on approved work.
Study Guide Objective: Implement the Procurement of Project Resources
C is correct. Once the vendor reports that the work is complete, the project manager
should inspect the work. This inspection can be done firsthand, if the project manager
is qualified, or by another qualified person or group. A is incorrect because the
vendor completes the invoice for the buyer. B is incorrect. The project manager will
pay the invoice according to the project contract—and after the work is verified as
complete. D is also incorrect. The project manager will sign off on the work once
it has been inspected and deemed acceptable.
Q88: Executing the Project
88. The project has been completed and management wants to know exactly how much
money has been spent with each vendor on the project. Which of the following is most
likely to happen in this situation?
A. An audit of the project plan
B. An audit of the quality of the project
C. An audit of the procurement documents
D. An audit of the project team members’ work
Answer: C
Hint: Vendors have been paid.
Study Guide Objective: Implement the Procurement of Project Resources
C is correct. Management will likely want to complete an audit of the procurement
records.
A is incorrect because a project plan audit is not needed. B is incorrect. While the
quality of the project work is needed, it will not help management ascertain where
the monies have been spent in the project. D is also incorrect. The project team members’
work may be audited for quality and completeness, but it will not answer management’s
question about the finances.
Q89: Executing the Project
89. You are the project manager for your organization and you’re starting the project
process of conducting project procurements. Which of the following is an example of
a screening system?
A. An organization breakdown structure
B. An independent estimate
C. A requirement for the seller to have a PMP on staff
D. A weighted model
Answer: C
Hint: You will qualify soon.
Study Guide Objective: Implement the Procurement of Project Resources
C is correct. The requirement for the vendor to have a PMP on staff can be used as
a screening system to filter out vendors that do not have the proper qualifications.
A is incorrect because an organization breakdown structure shows how the organization
is decomposed into departments, groups, managers, and other functional-based components.
B is incorrect because an independent estimate is used to compare vendors’ bids on
the project work. D is also incorrect because a weighted model scores vendors in different
categories of qualification.
Q90: Executing the Project
90. You are a project manager for your organization, but one of the managers is
refusing to allow her employees to spend time on your project. Which one of the following
is likely to be missing from your project in this instance?
A. The project manager
B. The risk management plan
C. The project scope
D. The project charter
Answer: D
Hint: You have no authority.
Study Guide Objective: Manage Resource Allocation
D is correct. The functional manager likely isn’t allowing her employees to work on
the project because there is no charter requiring the manager to do so.
A is incorrect because you are the project manager. B is incorrect because the risk
management plan is not applicable to this scenario. C is also incorrect. The project
scope may be missing, but it is not as important as the project charter, which authorizes
the project.
Q91: Executing the Project
91. You are a project manager in a weak matrix. You have recently completed the
project schedule. You must now get the project schedule approved so that the resources
can be officially assigned to their project work. Which one of the following stakeholders
will need to approve the project schedule?
A. Functional managers
B. The project champion
C. Project team members
D. No one. The project manager has autonomy on the project in this structure.
Answer: A
Hint: Power is limited.
Study Guide Objective: Manage Resource Allocation
A is correct. The functional managers in a weak matrix will have to approve the project
schedule.
B is incorrect because the project champion does not approve the project schedule.
C is incorrect. The project team does not approve the project schedule; they may provide
input, but not approval. D is also incorrect because the project manager has limited
authority in a weak matrix structure.
Q92: Executing the Project
92. Management says that your project is taking too long to complete. Which one
of the following is the best solution to this problem?
A. Add lead time
B. Add lag time
C. Add qualified resources to the critical path
D. Fast track the project
Answer: C
Hint: Use your project team.
Study Guide Objective: Manage Resource Allocation
C is correct. When there are unused resources that can help, the project manager should
add these resources to the critical path to reduce the duration of the activities.
A is incorrect because lead time is not the best solution. B is incorrect because
lag time will cause the project to last longer. D is also incorrect. Fast tracking
the project will shorten the project duration, but it also increases risk. Plus, adding
unused resources is the best solution to attempt first.
Q93: Executing the Project
93. You are a project manager for your organization. You are currently determining
the physical resources, the amount of resources needed, and when the resources will
be needed in the project schedule. This is called which one of the following?
A. Resource selecting
B. Source selection
C. Resource planning
D. Resource process selection
Answer: C
Hint: Always do this before committing.
Study Guide Objective: Manage Resource Allocation
C is correct. Resource planning considers the resource pool, resource availability,
resource costs, and resource calendars against the project calendar, scheduled activities,
and overall need for particular resources to determine what is the best resource for
a given activity.
A is incorrect. Resource selecting is simply choosing which resource is appropriate
for the project team or the project work. B is incorrect. Source selection is a procurement
process to determine which vendor is the best choice for the project work. D is incorrect
because this answer is an invalid choice and is not appropriate.
Q94: Executing the Project
94. You are the project manager for your organization and are currently determining
which resource is the best fit for each of the project activities. Thus, you are completing
which one of the following?
A. Project human resource management
B. Project role assignment
C. The development of the project team
D. The fulfillment of staff acquisitions
Answer: A
Hint: This is a formal process.
Study Guide Objective: Manage Resource Allocation
A is correct. Project human resource management is the process of successfully applying
the right resource to the project work in the most effective way in order to accomplish
the project goals while maintaining cost and schedule.
B is incorrect because role assignment is not a viable choice for this question. C
is incorrect. Developing the project team involves updating skill set and team relationships,
so it is not a viable choice. D is also incorrect because the question does not indicate
that project team members need to be acquired for the project.
Q95: Executing the Project
95. John is the project sponsor for your project and you’ve been working with him
regarding some quality and risk issues. Which of the following statements is true
about the project sponsor’s activities?
A. The project sponsor manages the project with the project manager.
B. The project sponsor assigns the project team members to specific project activities.
C. The project sponsor allows the project manager to make all decisions in a functional
environment.
D. The project sponsor ensures the project manager has the necessary resources to
complete the project.
Answer: D
Hint: Look toward the project completion.
Study Guide Objective: Manage Resource Allocation
D is correct. The project sponsor does ensure that the project manager has the necessary
resources to complete the project.
A is incorrect because the project sponsor does not manage with the project manager.
B is incorrect because the project sponsor does not assign project team members to
activities, the project manager does. C is also incorrect because a project manager
has little to no authority in a functional environment.
Q96: Executing the Project
96. You and another project manager are in competition for Juan. Both of you need
him for activities on your projects full-time, but your projects overlap in schedule.
This is an example of which one of the following?
A. Resource pool availability
B. Conflict management
C. Ivory tower
D. Resource constraint
Answer: D
Hint: Forget the castles.
Study Guide Objective: Manage Resource Allocation
D is correct because if certain activities require a worker with a highly specialized
skill, these activities are resource-dependent.
A is incorrect because while the availability of the resources must be examined, this
is an example of resource-dependent activities. B is incorrect because the question
does not provide enough information to determine if conflict management was involved
or successful. C is also incorrect. Ivory tower is slang for resources that involve
the only worker with a highly specialized skill set. Usually the individual is in
demand and may develop a cocky attitude about their abilities within the organization.
Q97: Planning the Project
97. Management has asked you to create an Ishikawa diagram for your new project.
An Ishikawa diagram aims to do which one of the following?
A. Facilitate design of experiments
B. Complete the statistical analysis of defects
C. Offer insight into problems that are causing failure
D. Offer a complete cause-and-effect analysis
Answer: D
Hint: Ishikawa diagrams are also called fishbone diagrams. Reference: PMP Study Guide,
Chapter 8
Study Guide Objective: Implement Quality Management Plan
D is correct. An Ishikawa diagram facilitates cause-and-effect analysis.
A is incorrect because Ishikawa diagrams do not facilitate design of experiments.
B is incorrect because control charts and Pareto charts complete the statistical analysis
of defects. C is also incorrect because a Pareto chart offers insights into problems
that are causing failure.
Q98: Executing the Project
98. A project manager has a project team member whose work is consistently not in
alignment with the quality metrics as required by the customer. This discrepancy results
in rework and wasted time. What should the project manager do?
A. Adjust the quality baseline.
B. Implement corrective actions.
C. Discipline the project team member.
D. Update the quality management plan.
Answer: B
Hint: Fix the problem.
Study Guide Objective: Implement Quality Management Plan
B is correct because corrective actions are actions taken to bring future performance
into alignment with the project plan.
A is incorrect because adjusting the quality baseline will not change what is expected
from the customer. C is incorrect. Corrective actions may include disciplining the
project team member and other mechanisms to prevent the problem from recurring. D
is also incorrect because updating any plans will not solve the actual problem of
unacceptable work.
Q99: Executing the Project
99. Complete this statement: Low _______________ may not be a problem; low _______________
always is.
A. Quality, grade
B. Quality, craft
C. Grade, quality
D. Targets, quality
Answer: C
Hint: Stay away from targets.
Study Guide Objective: Implement Quality Management Plan
C is correct. Low grade may not be a problem if that is what the customer has asked
for. Low quality, however, is always a problem.
A, B, and D are incorrect because these are not viable choices for this question.
Q100: Executing the Project
100. You are the project manager of a project to solve customer service problems in
your company’s call center. You would like to create a chart showing the frequency
of problems your project team has identified. What is the name of the chart you would
like to create?
A. A Pareto chart
B. A control chart
C. A flowchart
D. A Gantt chart
Answer: A
Hint: Remember the 80/20 rule.
Study Guide Objective: Implement Quality Management Plan
A is correct because a Pareto chart lists the problems and shows their frequency of
events.
B is incorrect because control charts are a graphic display of the end results of
a process sampling over time. C is incorrect because flowcharts show the relationship
between components in a system. D is incorrect because a Gantt chart shows activity
time mapped to a calendar.
Q101: Executing the Project
101. You are the project manager of a project to manufacture a new product. The project
is almost complete. The initial product is being tested and the quality engineers
discover a part is seven millimeters off target. Because of the errors, the product
is rejected. What is the likely outcome of this scenario?
A. A change request must be immediately created to change the product’s design.
B. The project team must rework the part to correct the problem.
C. The project is deemed a failure and is canceled.
D. The prototype is discarded and the design document is re-created.
Answer: B
Hint: The project is not over yet.
Study Guide Objective: Implement Quality Management Plan
B is correct. The project is not over. Rework must be done to bring the project back
into alignment with the product requirements.
A is incorrect. A change request is not the best answer for this question. Rework
is required instead to correct the problem. A change request signifies an addition
or subtraction from the project scope. C is incorrect because this is not a viable
option. D is incorrect because the design document is not re-created. Rework is completed
to meet the project objectives.
Q102: Executing the Project
102. You are the project manager for your organization and you’re currently mentoring
Marcy in the principles of project management. She does not understand the difference
between quality and grade. Which of the following statements would best explain to
Marcy what grade is?
A. Grade is the degree of perfection a component has.
B. Grade is the category or rank given to a component with the same functionality
but different technical characteristics.
C. Grade is the category or rank given to a component with the same functionalities.
D. Grade is the category or rank given to project work as deemed by the customer.
Answer: B
Hint: Think of paint, metal, or travel.
Study Guide Objective: Implement Quality Management Plan
B is correct. Grade, according to the PMP Study Guide, “is a category or rank given
to entities having the same functional use but different technical characteristics.”
A is incorrect. Grade and perfection may seem related, but a high grade of a component
may still have multiple imperfections. C is incorrect because the products being measured
for grade have the same functionality, but different characteristics. Consider travel,
where travelers have coach, business class, and first class. D is incorrect. The customer
has input to the quality and desire for a particular grade of the component, but does
not determine what the grade may be.
Q103: Executing the Project
103. You are a project manager responsible for the implementation of a software program.
Your project team will travel to several hundred remote locations to install the software
onsite. Project team members are reporting that the stakeholders in the locations
are asking them to do extra configuration work as part of the install. If the changes
are routed through the change control system, it may be several days before the changes
can happen, and the project team members are only onsite for two days at each location.
What should you do?
A. Refuse the changes because they are outside of the original project scope.
B. Evaluate the changes that have been requested so far in the project and determine
if the changes are valid. If so, blanket-approve the changes if other sites request
them.
C. Evaluate the changes that have been requested so far in the project and determine
if the changes are valid. If so, approve the changes as part of the installation process
for all sites.
D. Require all changes to flow through the change control system. If changes are approved,
they’ll be added at a later date and time if the project team agrees to complete the
work.
Answer: C
Hint: Aim for consistency.
Study Guide Objective: Implement Approved Changes
C is correct. If the changes the stakeholders are requesting at each of the sites
are valid requests that should be approved, the project manager should integrate these
changes across all installations, not just for the customers who request the changes.
A is incorrect because if the changes are valid, they should be approved. B is incorrect
because changes should be uniform across the project, not piecemeal. D is also incorrect.
Adding the changes later rather than anticipating the change requests is not cost-effective.
The project manager should evaluate the changes and implement them as part of the
project plan.
Q104: Executing the Project
104. In the early stages of a project, this event is easy to accept. Later in the
project, it is difficult to accept. What is the event?
A. Change
B. Risk
C. Team development
D. Scope validation
Answer: A
Hint: The further the project is from completing, the higher the risk and uncertainty.
Study Guide Objective: Implement Approved Changes
A is correct. Change is easily accepted in the beginning of a project. As the project
moves toward completion, change is harder to incorporate.
B is incorrect. Risk is only accepted based on its impact on the project and the performing
organization’s utility function. Recall that the utility function is an organization’s
willingness to accept risk. C is incorrect because team development happens throughout
the project. D is incorrect because scope validation happens throughout the project
at phase completion, at major project deliverables, and at project completion.
Q105: Executing the Project
105. A stakeholder has proposed some changes that will enhance the deliverable of
the project. Where is the scope change control system documented?
A. The change control plan
B. The project scope management plan
C. The cost management plan
D. The quality management plan
Answer: B
Hint: Protect the scope.
Study Guide Objective: Implement Approved Changes
B is correct. The change control system is documented in the project scope management
plan.
A is incorrect because this is not a valid project management plan. C is incorrect
because this plan does not define change control. D is also incorrect for the same
reason.
Q106: Executing the Project
106. A change has been approved for your project. This change will cause the project
to increase in costs by $25,000. What needs to be updated as a result of this change?
(Choose the best answer.)
A. The change control plan
B. Project cost estimates
C. The project schedule
D. The cost baseline
Answer: D
Hint: More money doesn’t mean more time. Reference: PMP Study Guide, Chapter 7
Study Guide Objective: Implement Approved Changes
D is correct. The cost baseline must be updated to reflect this change to the project
scope.
A is incorrect because this is not a valid plan. B is incorrect because the cost estimates
come before the project work has begun. This change has been approved. C is also incorrect.
Just because additional expenses have been introduced to the project does not mean
that the schedule will need to be updated as well. Consider the costs associated with
changing materials.
Q107: Executing the Project
107. A change has been demanded by the customer for your project scope. Which one
of the following does not need to be examined because of the change?
A. The project charter
B. Risk
C. The schedule
D. Project costs
Answer: A
Hint: This document authorizes the project.
Study Guide Objective: Implement Approved Changes
A is correct. The project charter has already been created because it authorizes the
project.
B is incorrect. Risk does not need to be examined again because the change may introduce
risk concerns into the project. C is incorrect. The schedule will need to be examined
because the changes may cause the current schedule to change. D is also incorrect.
The changes may bring additional costs with them so the project costs will need to
be examined.
Q108: Executing the Project
108. You are the project manager of the HGF Project. The project scope has been approved
by all stakeholders and management. The project is now moving forward. A week later,
however, two of the key stakeholders, John and Tina, come to you demanding to change
some aspects of the scope statement. What should the project manager do?
A. Refuse to make any changes because the scope has already been approved.
B. Refuse to make any changes because the scope cannot be changed once it has been
approved.
C. Refuse to make any changes, but have the stakeholders complete a change request
form.
D. Refuse to make any changes, but refer the stakeholders to your project sponsor.
Answer: C
Hint: Stakeholders must follow the rules.
Study Guide Objective: Implement Approved Changes
C is correct. A change request form will allow the change request to be documented,
considered, and approved or declined.
A is incorrect because this is not a correct statement about the circumstance described.
B is incorrect because scope statements can be changed if the need is appropriate.
D is also incorrect. The project sponsor is not the party to talk to about changes
at this point. A change request is the best form of action.
Q109: Executing the Project
109. Julianne is the project manager of the JGB Project. A change request has been
approved that will add a considerable amount of time and cost to the project. What
must be updated to reflect these changes?
A. The scope baseline
B. The project charter
C. The communications matrix
D. Contractual agreements
Answer: A
Hint: Document the deliverables.
Study Guide Objective: Implement Approved Changes
A is correct. A change that adds to the project scope will likely cause the WBS and
the WBS dictionary to be updated. The scope baseline is the combination of the project
scope statement, the WBS, and the WBS dictionary so all three are updated and linked
together.
B is incorrect. The project charter does not need to change. C is incorrect. In some
instances, the communications matrix will need to be updated—but not in all instances.
That’s why A is a better answer to this question. D is incorrect. In some instances,
the contractual agreements will need to be updated—but not in all instances. Again,
that’s why A is a better answer to this question. For instance, not every project
will have a contract.
Q110: Planning the Project
110. You are the project manager for your organization. Your latest project is to
create a web interface that allows customers to purchase items from an online catalog.
If you create the product in-house, it will cost $150,000 to create and nearly $4,500
each month in administration and fees. A vendor has supplied a quote to create the
software for $160,000 and to handle the administration for five cents per transaction.
There are expected to be 65,000 transactions each month. Which one of the following
will help you determine which decision has the best value?
A. A control chart
B. Trend analysis
C. A decision tree
D. A Pareto chart
Answer: C
Hint: Nothing has been created yet.
Study Guide Objective: Implement Approved Actions and Workarounds
C is correct. A decision tree will help you determine which one is the best decision
for the project.
A is incorrect because control charts illustrate patterns and the results of sampling.
B is incorrect because trend analysis can use historical information to predict future
trends. D is also incorrect because a Pareto chart illustrates the causes of defects
and their frequency.
Q111: Executing the Project
111. A project manager wants to assign resources to activities that must happen during
off-hours. The labor union, however, wants to discuss this issue with the project
manager before approving the schedule. The relationship between the labor union and
management is represented by which one of the following?
A. The contract
B. A collective bargaining agreement
C. Time and materials
D. A project constraint
Answer: B
Hint: T–M doesn’t apply.
Study Guide Objective: Implement Approved Actions and Workarounds
B is correct. The agreement between management and the labor union is known as a collective
bargaining agreement.
A is incorrect. Although the agreement between management and the labor union is a
contract, this answer is not as good as answer B. C is incorrect because this is not
applicable to the agreement. D is also incorrect. The union’s rules and policies may
be a project constraint, but this does not describe the relationship between management
and the union.
Q112: Executing the Project
112. You are the project manager for your organization and you’re working with management
and the project team to create the project management plan. Which plan controls how
team members are brought onto and released from the project?
A. The staffing management plan
B. The cost management plan
C. The communications management plan
D. The scope management plan
Answer: A
Hint: This answer doesn’t affect the scope.
Study Guide Objective: Implement Approved Actions and Workarounds
A is correct. The staffing management plan details how workers are brought onto and
released from the project. Note that the staffing management plan is a component within
the project’s human resource management plan.
B is incorrect because the cost management plan details how variances to cost will
be managed. C is incorrect because the communications management plan details who
needs what information and when. D is incorrect because the scope management plan
details how changes to the scope will be prevented or allowed.
Q113: Executing the Project
113. Fred is the project manager of the HUT Project and he’s in a conflict with Sarah
about requiring the project team to work overtime. Fred insists that overworking the
project team may result in all but one of the following. Which one won’t result?
A. Unacceptable work
B. A decline in team morale
C. An increase in quality inspections
D. A decrease in the project team’s willingness to work
Answer: C
Hint: This comes from an outside influence.
Study Guide Objective: Implement Approved Actions and Workarounds
C is correct. An increase in quality inspections may be needed, but there is no guarantee
these will come as a result of an overworked team.
A is incorrect because an overworked team may create unacceptable work. B is incorrect
because a decline in team morale is likely with an overworked project team. D is also
incorrect. A willingness to work will likely decrease because the project team is
exhausted and frustrated with both the project manager and the project work.
Q114: Executing the Project
114. A project manager is completing a project for another organization and is currently
completing risk planning in order to determine which risks demand actions in the project.
Which one of the following must be considered when planning to take actions regarding
the project risks?
A. Herzberg’s Theory of Motivation
B. The Utility method
C. The negative risk event value
D. The organizational structure
Answer: B
Hint: A willingness to accept risks determines the actions required.
Study Guide Objective: Implement Approved Actions and Workarounds
B is correct. The Utility method describes an organization’s willingness to accept
risk, and the willingness to accept risk will determine the level of response required
for the identified risks.
A is incorrect because Herzberg’s Theory of Motivation is not relevant to this question.
C is incorrect. The risk event value may be considered, but only after the Utility
method is considered. D is also incorrect because the organizational structure has
little input to the risk response in most projects.
Q115: Controlling the Project
115. Sarah is the project manager of a project to create an online help manual for
customers of a product her company sells. Samuel, a writer for the project, is taking
considerably longer than what was planned to create the documentation. While Samuel’s
work is excellent, if he continues to be late with the needed documentation, the project
will be late. Which of the following is NOT an appropriate corrective action for this
problem?
A. Remove Samuel from the project team.
B. Assign other writers to some of Samuel’s project work.
C. Determine why Samuel’s work is late.
D. Assign Samuel to noncritical activities.
Answer: A
Hint: Samuel is a good writer.
Study Guide Objective: Implement Approved Actions and Workarounds
A is correct. Because Samuel is a good writer, it would be detrimental to the project
to remove him entirely. The project manager should determine why the problem exists
and then respond to the problem with corrective actions.
B is incorrect. It may be beneficial to offload some of Samuel’s assigned work to
other writers. C is incorrect. The project manager should determine why Samuel’s work
is late. D is incorrect because it may be appropriate to assign Samuel to noncritical
path activities.
Q116: Executing the Project
116. You are the project manager of the generator upgrade and replacement project,
which is expected to last 36 months. The project work is extremely dangerous so the
project team will undergo intense safety training to ensure the safety of the workers
and to make certain the project is not delayed due to faulty work. The cost of the
safety training is known as which one of the following?
A. The cost of conformance to quality
B. The cost of nonconformance to quality
C. The cost of doing business
D. The cost of regulations
Answer: A
Hint: This ensures quality is met.
Study Guide Objective: Improve Team Performance
A is correct. This is an example of the cost of conformance to quality.
B is incorrect. The cost of nonconformance is the cost of having to redo the project
work, loss of sales, downtime, and other expenses caused by not doing the training.
C is incorrect. The cost of doing business is usually assigned to regular expenses
such as salaries, rent for office space, lights, and so on. Training, especially this
type of training, is above and beyond the cost of doing business. D is incorrect because
the question does not suggest that regulations require this training.
Q117: Controlling the Project
117. The communications management plan will detail the schedule for expected communications
among other activities. One of the regularly scheduled meetings is used to record
the status of project work. Which one of the following is used to record the status
of project work?
A. A quality review meeting
B. A change control meeting
C. A status meeting
D. A team development meeting
Answer: C
Hint: Find out how the project is doing.
Study Guide Objective: Improve Team Performance
C is correct. Status review meetings are regularly scheduled meetings to record the
status of the project work.
A is incorrect. Quality review meetings review the overall quality of the project
and how it may be improved if the quality is off target. B is incorrect because change
control meetings are called for to review change requests. D is incorrect as well
because team development meetings are used to foster project team relations.
Q118: Executing the Project
118. Team development is an important part of project management. Team development
fosters relationships and good communication among the project team members. Which
one of the following can improve project teamwork?
A. Hallway meetings
B. Informal e-mails
C. Videoconferences
D. Offsite activities
Answer: D
Hint: Go bowling.
Study Guide Objective: Improve Team Performance
D is correct. Offsite activities can give the project team an opportunity to get to
know each other without the stress and interference of the workplace.
A is incorrect because hallway meetings are part of communications. B is incorrect
because informal e-mails are part of communications as well. C is incorrect because
videoconferences do not develop the project team.
Q119: Executing the Project
119. John is the project manager for his company. John believes that the project team
should just know and do their assignments. Team development, John believes, is wasted
time away from doing the project work. Why should the project manager work to develop
the project team?
A. The project manager should not work for team development. It is a natural process
that will occur on its own accord.
B. To improve the skills of team members in order to increase their ability to complete
project activities
C. To increase the likelihood of the project being profitable
D. To increase communications
Answer: B
Hint: Focus on the project.
Study Guide Objective: Improve Team Performance
B is correct. Part of team development is to increase each team member’s ability to
complete the project work.
A is incorrect. Team development may happen, to some extent, on its own, but it should
be facilitated by the project manager. C is incorrect because not all projects have
a focus on profits. D is incorrect as well. An increase in communications is not always
a good thing; consider effective communications versus rampant communications.
Q120: Executing the Project
120. You are the project manager of the JKG Project. You have determined that the
project team needs additional training to complete the project work. The additional
training is which type of cost?
A. Direct costs
B. Indirect costs
C. Variable costs
D. Fixed costs
Answer: A
Hint: The project team needs training for this project’s work.
Study Guide Objective: Improve Team Performance
A is correct. This is an example of direct costs because the training is needed to
complete the current project’s work.
B is incorrect since indirect costs are shared across multiple projects. C is incorrect.
This is not an example of a variable cost. Variable costs fluctuate depending on the
conditions within a project. D is incorrect because fixed costs are persistent throughout
the project—such as leasing a piece of equipment.
Q121: Executing the Project
121. You are the project manager of a large network upgrade project. The project scope
has been approved and now you’re ready to create the WBS. Who actually creates the
WBS?
A. Stakeholders
B. The project sponsor
C. The project manager
D. The project team
Answer: D
Hint: The WBS creation is not a solo activity.
Study Guide Objective: Create the WBS
D is correct. The project team creates the WBS.
A is incorrect. Stakeholders do not create the WBS. Consider a project that may have
thousands of stakeholders—it would be impractical to have them contribute to the creation
of the WBS. In addition, they likely would not have the required skills to contribute
to the WBS. B is incorrect because the project sponsor does not create the WBS. C
is incorrect as well. The project manager does not create the WBS. He may contribute,
guide, and facilitate the process, but it is not a solo activity. Q122: Executing
the Project
122. Which human resource theory believes that the project team can be self-led and
productive if challenged?
A. Ouchi’s Theory Z
B. Deming
C. Herzberg’s Theory of Motivation
D. Pareto’s Law
Answer: A
Hint: This doesn’t hurt.
Study Guide Objective: Develop the Project Team
A is correct. Ouchi’s Theory Z, also known as the Japanese Management Style, believes
that the project team can be self-led and productive if challenged.
B is incorrect. Deming offered philosophies on quality, not necessarily human resources.
C is incorrect because Herzberg’s Theory of Motivation defines hygiene agents and
motivating agents that cause an individual to excel. D is also incorrect. Pareto’s
Law is commonly known as the 80/20 rule. For example, 80 percent of your business
comes from 20 percent of your customers.
Q123: Monitoring and Controlling the Project
123. Which one of the following is the best tool for tracking project scope?
A. The work breakdown structure
B. The network diagram
C. Quality control
D. Risk event triggers
Answer: A
Hint: This serves as an input to other planning processes.
Study Guide Objective: Measure Project Performance
A is correct. The WBS is the best tool for tracking project scope.
B is incorrect because a network diagram illustrates the sequence of project activities.
C is incorrect because QC involves methods to ensure the work meets the expected quality
designed for the project. D is also incorrect. Risk event triggers are conditions
that signal a risk event has occurred or is about to occur.
Q124: Monitoring and Controlling the Project
124. You need to know when project team members are available to work on the project.
Which calendar will take into account project team members’ vacations?
A. The project calendar
B. The resource calendar
C. The project team calendar
D. The human resource management calendar
Answer: B
Hint: The answer is not HR-related.
Study Guide Objective: Measure Project Performance
B is correct. The resource calendar controls when resources, such as project team
members, consultants, and SMEs are available to work on the project. It takes into
account vacations, other commitments within the organization, restrictions on contracted
work, overtime issues, and so on.
A is incorrect because the project calendar details when work is allowed on the project.
C and D are incorrect because neither is a valid answer.
Q125: Monitoring and Controlling the Project
125. You are a project manager for your organization. Your project has a BAC of $400,000
and is expected to last one year. The project work is scheduled to be completed in
equal amounts each month. Currently, the project is in month three but is only 20
percent complete. You have spent $35,000 to complete the work. What is the earned
value for this project?
A. Negative $20,000
B. $80,000
C. $100,000
D. Not enough information has been supplied to determine this
Answer: B
Hint: Find the percent complete. Reference: PMP Study Guide, Chapter 7
Study Guide Objective: Measure Project Performance
B is correct. The earned value for this project is 20 percent complete. The formula
is EV = % complete × BAC.
A is incorrect. The EV is not a negative number since it is 20 percent complete. C
is incorrect because $100,000 is the planned value amount. D is also incorrect because
there is enough information to calculate the formula.
Q126: Monitoring and Controlling the Project
126. You are a project manager for your organization. Your project has a BAC of $400,000
and is expected to last one year. The project work is scheduled to be completed in
equal amounts each month. Currently, the project is in month three, but is only 20
percent complete. You have spent $35,000 to complete the work. Given this, what is
the planned value for this project?
A. $20,000
B. $35,000
C. $80,000
D. $100,000
Answer: D
Hint: Find out how much should have been spent.
Study Guide Objective: Measure Project Performance
D is correct. The planned value is the amount the project should have spent to reach
this point in the schedule. Because the project is scheduled to last one year with
the work completed in separate parts each month, month three represents 25 percent
of the project, or $100,000.
A is incorrect because $20,000 is not the planned value. B is incorrect because $35,000
is the actual cost. C is also incorrect because $80,000 is the earned value
Q127: Monitoring and Controlling the Project
127. You are a project manager for your organization. Your project has a BAC of $250,000
and is expected to last ten months. Currently, the project is in month six and is
40 percent complete, but the project was expected to be 60 percent complete by this
time. You have spent $125,000 to complete the work. What is the cost performance index
of the project?
A. 80
B. 15
C. $125,000
D. .80
Answer: D
Hint: Double-check your work.
Study Guide Objective: Measure Project Performance
D is correct. The cost performance index is calculated by dividing the earned value
by the actual costs. In this instance, the formula is CPI = 100,000 / 125,000. This
results in .80.
A is incorrect. The CPI is .80, not 80. B is incorrect because this is an incorrect
value.
C is incorrect as well. The CPI is not a dollar amount, so this value is incorrect.
Q128: Monitoring and Controlling the Project
128. You are a project manager for your organization. Your project has a BAC of $250,000
and is expected to last ten months. Currently, the project is in month six and is
40 percent complete, but the project was expected to be 60 percent complete by this
time. You have spent $125,000 to complete the work. What is the schedule performance
index of the project?
A. .80
B. .67
C. $67,000
D. $80,000
Answer: B
Hint: The answer doesn’t need a dollar amount.
Study Guide Objective: Measure Project Performance
B is correct. The schedule performance index (SPI) is calculated by dividing the earned
value by the planned value. In this instance, the formula is $100,000 / 150,000 =
.67.
A is incorrect because this is the value of the cost performance index. C and D are
incorrect because the SPI is not a dollar amount.
Q129: Monitoring and Controlling the Project
129: Lenny is the project manager of the GHA Project for his company. A recent earned
value management calculation shows that Lenny has a CPI of .98 on this project. A
project that has a CPI of .98 means what?
A. The project is late.
B. The project is making money.
C. The project has to spend one dollar for every 98 cents of work it receives.
D. The project is 98 percent complete.
Answer: C
Hint: CPI is the cost performance index.
Study Guide Objective: Measure Project Performance
C is correct. A project with a CPI of .98 has to spend one dollar for every 98 cents
of work it receives.
A is incorrect because there’s no evidence that the project is late. B is incorrect
because the project is actually losing money with this CPI, not making it. D is also
incorrect since a CPI of .98 does not mean the project is 98 percent complete.
Q130: Monitoring and Controlling the Project
130. Management in your company is tracking the status of all projects using earned
value management. Which of the following values can alert management to a problem
on the project?
A. A CPI of 1
B. A CPI of .90
C. An SPI of .99
D. A BAC of $125,000
Answer: B
Hint: The project is losing money.
Study Guide Objective: Measure Project Performance
B is correct. A CPI of .90 means the project has to pay one dollar of every 90 cents
of work.
A is incorrect because a CPI of 1 is perfect. C is incorrect because an SPI of .99
is close to perfect, while a CPI of .90 is far from perfect. D is also incorrect.
A BAC of $125,000 is fine—this is the budget at completion and is set by the demands
of the project.
Q131: Monitoring and Controlling the Project
131. You are the project manager for your organization. Your latest project has a
BAC of $250,000. You have calculated your CPI to be .91 and your AC to $175,000. What
is your project’s EAC?
A. $25,000
B. $15,750
C. $265,000
D. $275,000
Answer: D
Hint: Remember the formula EAC = BAC / CPI.
Study Guide Objective: Measure Project Performance
D is correct. The formula EAC = BAC / CPI is written, in this instance, as EAC = 250,000
/ .91. This equates to $274,725, which is rounded up to $275,000.
A, B, and C are all incorrect because these are erroneous calculations.
Q132: Monitoring and Controlling the Project
132. You have just taken over a project that is several months late and is in very
bad shape. The previous project manager had not kept accurate records on the project
work, project expenses, or the overall performance of the project. The customer is
still very interested in having the project completed and is not holding you responsible
for the project work up to this point. Of the following, which one is the best solution
to move forward and to create accurate records of your progress?
A. Scrap the project and start over.
B. Create a work authorization system.
C. Create a new project plan.
D. Rebaseline the project.
Answer: D
Hint: The customer wants the project to move forward with your guidance.
Study Guide Objective: Measure Project Performance
D is correct. Rebaselining the project is probably the best solution in this instance
because the project is in such disarray. This also allows the project manager to record
and compare work actions from this point forward.
A is incorrect because the customer does not want to cancel the project. B is incorrect.
A work authorization system is needed, but it is not a solution to this problem. C
is also incorrect because the question does not detail whether the project plan is
bad or whether it’s just not being implemented properly.
Q133: Monitoring and Controlling the Project
133. A project has a budget of $7,500,000 and is expected to last five years. The
project is now in year three and is 40 percent complete. What is the earned value
of this project if the project manager has spent $4,225,000 of the project budget
so far?
A. $3,000,000
B. .66
C. $4,225,000
D. $4,500,000
Answer: A
Hint: The project is 40 percent complete.
Study Guide Objective: Measure Project Performance
A is correct. The EV is calculated by multiplying the percent complete times the budget
at completion.
B is incorrect. This is the cost performance index for the project. C is incorrect
because this is not a valid calculation for the question. D is incorrect for the same
reason.
Q134: Monitoring and Controlling the Project
134. The project manager of a large software implementation project just finished
a project status meeting. In the meeting, he learned that a crucial piece of the software
his team was creating is faulty. The news will cause the project to be late by at
least one month and will likely cost additional fees for the developers’ time. What
is the next step the project manager should take?
A. Fire the project team member responsible for the mistake.
B. Create a change request for the immediate correction to the software.
C. Complete a root-cause analysis to determine why the problem occurred.
D. Present the news to management and the customer with a solution to resolve the
problem.
Answer: D
Hint: Find a solution.
Study Guide Objective: Verify and Manage Changes to the Project
D is correct. The project manager needs to share the news with management and the
customers with a solution to fix the problem. The project manager should never go
to management with a problem without a solution.
A is incorrect. An immediate reaction to fire the project team member may not be appropriate.
In addition, the project manager may not have the authority to release the project
team member. B is incorrect. Change requests are needed for additions to (or subtractions
from) the project scope, not to complete rework. In addition, this answer calls for
immediate correction to the software. C is also incorrect. Root-cause analysis can
be helpful, but it should be completed after informing both management and the customer.
Q135: Monitoring and Controlling the Project
135. Virginia is a project manager overseeing the construction of a new retail shopping
center. The project is scheduled to last one year and is currently in month five.
She is working with several subcontractors on the project to complete the paving,
road connections, and parking lot lighting. It has come to her attention from the
paving contractor that the city has raised the fees to connect the parking lot to
the city drive. Which of the following communications is most appropriate for this
change?
A. A formal presentation
B. A memo to management regarding the fees
C. A cost variance report
D. A memo from the paving contractor to management
Answer: C
Hint: Document the variance.
Study Guide Objective: Verify and Manage Changes to the Project
C is correct. The change in the cost of the connection should be documented in a cost
variance report.
A is incorrect. A formal presentation may or may not be necessary for the cost increase,
but a cost variance report is needed. B is incorrect because a memo is not the appropriate
report needed. D is incorrect because a memo from the contractor to management is
also inappropriate.
Q136: Monitoring and Controlling the Project
136. Protecting the project scope is paramount in all projects, but sometimes changes
will happen. In which of the following is the project scope change control system
documented?
A. The project scope management plan
B. The quality management plan
C. The change control board documentation
D. The project charter
Answer: A
Hint: Protect the scope.
Study Guide Objective: Verify and Manage Changes to the Project
A is correct. The project scope change control system is documented in the project
scope management plan.
B is incorrect. The quality management plan addresses the quality of the project,
not the process for controlling changes. C is incorrect because this is not a valid
answer for this question. D is incorrect because the project charter authorizes the
project and does not address the process for managing changes.
Q137: Monitoring and Controlling the Project
137. You are the project manager for the BNH Project. A stakeholder is demanding that
your project team make some immediate changes to the product your project is creating.
You inform the customer that the changes cannot happen immediately because of the
project processes that are established by your organization. In which of the following
are these processes documented?
A. The change control board
B. The organizational assets
C. The scope change control system
D. The project charter
Answer: C
Hint: Protect the scope.
Study Guide Objective: Verify and Manage Changes to the Project
C is correct. The scope change control system documents how changes are authorized
for a project.
A is incorrect. Not every project will have a change control board. In addition, the
processes for change are documented in the scope change control system. B is incorrect.
This is not a valid answer for this question. D is incorrect. The charter authorizes
the project; it does not document the change control process.
Q138: Monitoring and Controlling the Project
138. A value-added change has been approved for your project. The change will require
the project to take two months longer and will cost $25,000. What must the project
manager do once these changes have been approved?
A. Reflect the changes in change control documentation.
B. Complete a risk assessment of the change.
C. Update the change control system to reflect the new changes to the project scope.
D. Update the time, cost, and scope baselines to reflect the new changes.
Answer: D
Hint: Reflect the change.
Study Guide Objective: Verify and Manage Changes to the Project
D is correct. Once the changes have been approved, the project manager should reflect
the additional time, cost, and scope changes accordingly in each baseline.
A is incorrect. The changes are not reflected in the change control documentation
because this documentation explains the process for how changes may enter the project
scope. B is incorrect. A risk assessment of each change is completed as part of the
change control process—not after the change has been approved. C is also incorrect.
The change control system is not updated because of the change.
Q139: Monitoring and Controlling the Project
139. You are a project manager for your organization. Your project utilizes a vendor
to complete all of the electrical work within your project. Your stakeholder has requested
a change in the scope of the project which will cause additional work for the vendor.
Which of the following documents will dictate how the change will proceed in regard
to the vendor?
A. The change control documentation
B. The scope document
C. The procurement management plan
D. The contract
Answer: D
Hint: This document overrides everything else.
Study Guide Objective: Verify and Manage Changes to the Project
D is correct. The contractual agreement between the vendor and the customer override
all other documents.
A is incorrect. The change control system should comply with the contractual agreement
between the vendor and the customer. B is incorrect because the scope details the
project work, not the contractual obligations between the vendor and the customer.
C is also incorrect because the procurement management plan is not as specific as
the terms defined within the contract.
Q140: Monitoring and Controlling the Project
140. Change control is essential to project success. Part of change control is the
coordination of all changes across the entire project. When does integrated change
control happen?
A. From project inception through completion
B. During project execution
C. During project monitoring and controlling
D. During project planning
Answer: A
Hint: Don’t rule out anything.
Study Guide Objective: Verify and Manage Changes to the Project
A is correct. Integrated change control happens throughout the entire project, not
just during any one process group.
B, C, and D are incorrect because integrated change control happens throughout the
entire project.
Q141: Monitoring and Controlling the Project
141. Mary is the project manager of a software development project. The stakeholders
of the project have requested a major change to the project scope. The change control
board has reviewed and approved the change even though it will require six additional
weeks of the development team’s time. What must Mary do next?
A. Hire additional project team members to complete the project on time.
B. Complete a risk assessment on the proposed change.
C. Work with the project team to update the project scope, WBS, and WBS dictionary.
D. Calculate the project costs with the additional change.
Answer: C
Hint: This change has already been approved.
Study Guide Objective: Verify and Manage Changes to the Project
C is correct. Once the scope has been modified, as in this instance, the project manager
and the project team should reflect the scope addition in the scope statement, the
WBS, and the WBS dictionary.
A is incorrect. While crashing the project may be appropriate in some instances, this
question already acknowledges the additional time for the added work. B is incorrect.
A risk assessment is likely to have already happened because the change requested
passed through the change control board process. D is incorrect because costs and
time are calculated before the change has been accepted.
Q142: Monitoring and Controlling the Project
142. Your organization completes projects for other organizations. You are the project
manager of the BGV Project. It is almost complete but the stakeholders have requested
a change to the project scope. The customer is willing to pay any additional fees
for this change. This additional change will cause the project to run three weeks
longer than was planned. The problem, you realize, is that you have already scheduled
your current project team to start a three-year project for a different customer that
will overlap with the new work the customer has just added to the scope. You need
to complete the current project, keep your current customer happy, and start the next
project on time. What should you do?
A. Hire additional project team members to complete the project on time.
B. Promise the customer that the changes can be added at a later date.
C. Refuse to add the changes to the current project.
D. Promise the customer that you can do the changes as requested but you will need
to stop the current project, move your project team to the other project, and then
return to the project when the team is available.
Answer: A
Hint: Crash the project.
Study Guide Objective: Verify and Manage Changes to the Project
A is correct. The best choice is to hire additional work to ensure that your current
project ends on time.
B is incorrect. This choice, while feasible, likely won’t keep your current customer
happy. C and D are incorrect because they won’t keep your customer happy.
Q143: Monitoring and Controlling the Project
143. David is a project manager for his company and he’s reviewing the defined change
control processes as part of his company’s enterprise environmental factors. In his
review, he sees that changes to the project’s product are controlled by a particular
system. Which of the following systems will control changes to the project’s product?
A. The scope configuration system
B. The change configuration system
C. The product scope
D. The configuration management system
Answer: D
Hint: It’s a subsystem of the project management information system.
Study Guide Objective: Verify and Manage Changes to the Project
D is correct. The configuration management system controls changes to the functional
and physical characteristics of a product or component.
A, B, and C are incorrect because they are not valid choices for this question.
Q144: Monitoring and Controlling the Project
144. You are the project manager for your organization. Marcy, the sponsor of the
project, has asked that you use a different grade of materials for your project. She
believes the current materials used are of lesser quality than the materials she proposes.
The customer demands the highest quality on the project deliverable. This change in
materials will cause the project costs to increase by 20 percent. Which one of the
following best describes the cost of the materials?
A. Gold plating
B. Cost of quality
C. The project management cost
D. Discretionary costs
Answer: B
Hint: Meet the customer’s demands. Reference: PMP Study Guide, Chapter 8
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
B is correct. The cost to quality is the best choice. The expense of the better materials
is attributed to the better product the project will create.
A is incorrect. Gold plating is the act of adding work, additional materials, or more
expensive than needed materials to drive up the project cost for personal gain. C
is incorrect. This is not an example of project management costs. D is incorrect.
These are not discretionary costs but costs attributed to the cost of the quality
as demanded by the customer.
Q145: Monitoring and Controlling the Project
145. You are a project manager for a manufacturing company. There are several OSHA
guidelines that must be met on your project. These OSHA guidelines ensure the safety
of the project team members. Which of the following is the most appropriate reference
to these guidelines?
A. Constraints
B. Assumptions
C. Standards
D. Regulations
Answer: D
Hint: These are requirements.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct. OSHA guidelines are requirements your project must meet.
A is incorrect. While some project managers may view these regulations as constraints,
regulations are a better description for the rules. If the project manager does not
follow these regulations, it may cause fines, penalties, and even injuries or death
to the project team members. B is incorrect because these are not assumptions. C is
incorrect. Standards are optional, while OSHA regulations are not optional.
Q146: Monitoring and Controlling the Project
146. Finish this statement: _______________ is planned into a project, not inspected
in.
A. Quality
B. Safety
C. Control
D. Teamwork
Answer: A
Hint: It is not teamwork.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
A is correct. Quality is planned into a project from the start. Inspections prove
its existence.
B is incorrect. While safety is important, it is not the correct answer. Safety may
be inspected into a project when you consider construction projects, electrical wiring
projects, or similar work. C is incorrect because control is not a viable choice.
D is incorrect. Teamwork is developed, planned, and hoped for, but this is not the
best choice for the question.
Q147: Monitoring and Controlling the Project
147. Dean’s company uses ISO 9000 as part its manufacturing environment. Dean has
been asked to incorporate an ISO 9000 approach to his projects. What is ISO 9000?
A. A quality management system
B. A quality control system
C. A management approach to implement quality on customer projects
D. A method of following procedures created internally to an organization
Answer: D
Hint: You can have bad procedures and still be ISO 9000 certified.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct. ISO 9000 is not a quality system, but a method of following procedures
created internally to an organization.
A is incorrect because ISO 9000 is not a quality management system. B is incorrect
because ISO 9000 is not a quality control system. C is incorrect because ISO 9000
is an organization-wide approach, not just a project-centric one.
Q148: Monitoring and Controlling the Project
148. You are the project manager of the Call Center Improvement Project. The project
calls for training all 320 call center representatives on the new software your project
team will be installing. Part of the project also involves an improvement in the customer
service support of the call center agents. You and the call center manager have set
operational definitions for the call center. Which one of the following is an operational
definition?
A. All customer service reps will complete the required training.
B. All customer service reps will complete the required training within 30 days.
C. A live operator will answer all inbound telephone calls within one minute.
D. All customer service reps will answer the telephone calls with their name and a
standard greeting.
Answer: C
Hint: Look for the metric.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
C is correct. A live operator will answer all inbound telephone calls within one minute
is an example of an operational definition because it has a given metric.
A, B, and D are incorrect because these are examples of project requirements.
Q149: Monitoring and Controlling the Project
149. The project manager and a quality engineer have completed a six-month analysis
of production in a manufacturer’s environment. The quality engineer now wants to plot
out the results to identify trends. Which one of the following is the chart or diagram
that will best satisfy the request?
A. A Pareto chart
B. An Ishikawa diagram
C. A control chart
D. A flowchart
Answer: C
Hint: The quality engineer is looking for assignable cause.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
C is correct. A control chart will allow the quality engineer and the project manager
to plot out the results to find assignable causes for variances.
A is incorrect because a Pareto chart maps out the causes and frequency of quality
problems. B is incorrect because an Ishikawa diagram is a cause-and-effect diagram
to determine root-cause analysis. D is incorrect because a flowchart shows the relation
of components within a system and how a process works through a system.
Q150: Monitoring and Controlling the Project
150. Quality must first be defined before it can be achieved. There is a cost factor
to the achievement of quality and a cost factor for poor quality. Which of the following
is NOT an example of the cost of poor quality?
A. Rework
B. Corrective actions
C. Safety measures
D. A loss of customers
Answer: C
Hint: This ensures quality.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
C is correct. Safety measures are a cost of the conformance to quality. If the measures
are not taken, accidents may happen and the project then stopped for investigation,
rework, and other measures.
A is incorrect. Rework is an example of the cost of nonconformance to quality. When
work is unacceptable, it has to be corrected. B is incorrect. Corrective actions are
part of the cost of nonconformance to quality. When work, performance, and other components
are unacceptable, corrective actions steer the project back online. D is also incorrect
because when customers get disgusted due to quality issues, they will find other providers.
Q151: Monitoring and Controlling the Project
151. As a project manager and a PMP candidate, you should be able to discern quality
assurance and quality control. Which of the following statements about quality control
is true?
A. Quality control is the process of the project customer accepting the project deliverables.
B. Quality control is the process of ensuring the project deliverables are in alignment
with the project scope.
C. Quality control is the process of obtaining customer acceptance of the work.
D. Quality control is concerned with the correctness of the work.
Answer: D
Hint: The work must be exact for it to be accepted by the customer.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct. Quality control is focused on the correctness of the work.
A, B, and C are incorrect because these statements describe scope validation.
Q152: Monitoring and Controlling the Project
152. Monitoring and controlling the project is the process of ensuring the project
plans are executed accurately. The quality management plan must be understood in order
to track its effectiveness in the project. Which one of the following do the quality
management plans not dictate?
A. Quality control
B. Quality assurance
C. Quality improvement
D. Six Sigma programs
Answer: D
Hint: Not all companies have this.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct. Not all companies will use a quality management program like Six Sigma.
A is incorrect because quality control is detailed in the quality management plan.
B is incorrect because quality assurance is also detailed in the quality management
plan. C is incorrect as well. Quality improvement is detailed in the quality management
plan.
Q153: Monitoring and Controlling the Project
153. What is the difference between quality control and scope validation?
A. Quality control is done by the customer after the project has been completed.
B. Scope validation is done by the project team to ensure that the project has been
completed according to the project scope.
C. Both are inspection-driven, but the project manager facilitates quality control
while the project team does scope validation.
D. Both are inspection-driven, but the project manager facilitates quality control
without the customer, and then scope validation with the customer.
Answer: D
Hint: The processes are slightly different.
Study Guide Objective: Ensure Project Deliverables Conform to Quality Standards
D is correct. Quality control is concerned with the correctness of the work, while
scope validation is concerned with the customer accepting the work.
A, B, and C are incorrect because all of these statements are false.
Q154: Monitoring and Controlling the Project
154. You are the project manager of the Sales Automation Project. Jennifer, a project
team member, has learned that the vendor you are purchasing a phone system from as
part of this project will likely be two months late on half of the order. Which subsidiary
plan should be updated?
A. The risk management plan
B. The risk response plan
C. The procurement management plan
D. The scope management plan
Answer: B
Hint: Manage the problem.
Study Guide Objective: Monitor All Risks
B is correct. Responses to risks are identified and documented in the risk response
plan.
A is incorrect because the risk management plan details how risk analysis, risk identification,
and other risk-related management activities will proceed. It does not include the
responses to individual risk. C is incorrect. The procurement management plan does
not need to be updated based on this scenario. The question does not indicate that
a different vendor is needed. D is incorrect. The scope management plan does not need
to be changed because there is no indication of changes, or threats of changes, to
the project scope.
Q155: Monitoring and Controlling the Project
155. Risks are identified, monitored, tracked, and responded to. One element which
must also be identified is a risk trigger. What is a risk trigger?
A. A risk trigger is a risk that causes a secondary risk.
B. A risk trigger is a risk that causes a residual risk.
C. A risk trigger is a plan to respond to risk events.
D. A risk trigger is a sign or symptom that risks have occurred or are about to occur.
Answer: D
Hint: Triggers are like hints.
Study Guide Objective: Monitor All Risks
D is correct. These are warning signs or symptoms that a risk has occurred or is about
to occur.
A is incorrect because a secondary risk can be created by solutions to a different
risk in the project. B is incorrect. Residual risks are smaller risks caused by response
to other risks. C is incorrect because a risk trigger is not a plan to respond to
the risk event.
Q156: Monitoring and Controlling the Project
156. You are the project manager for a construction project. One of the identified
risks within the project has a 20 percent chance of happening. If the risk occurs,
it will cost your project an additional $150,000. Given this, what is the contingency
amount you’ll need for this risk event?
A. $150,000
B. $30,000
C. $75,000
D. Zero. The risk is not real until it occurs.
Answer: B
Hint: Find the likelihood of the risk happening.
Study Guide Objective: Monitor All Risks
B is correct. The risk has a 20 percent chance of happening and will cost the project
$150,000. Twenty percent of $150,000 is $30,000—the expected amount of contingency.
A is incorrect. $150,000 is 100 percent of the risk event occurring. C is incorrect.
$75,000 is based on a 50 percent likelihood of the risk occurring. D is incorrect
because the risk is real even if the risk event does not occur.
Q157: Monitoring and Controlling the Project
157. You are the project manager for a large project that spans several of your organization’s
sites. There are many risks identified throughout the project in each of the sites
of the project. Which one of the following is the most effective method of dealing
with the project risks?
A. Create risk owners for each of the project risks.
B. Buy insurance for each of the identified risks.
C. The project manager will need to travel to each of the sites as the risk event
is coming into the project schedule.
D. The project manager will need to schedule the risk events so that no risk events
overlap at any one time.
Answer: A
Hint: Own the risk event.
Study Guide Objective: Monitor All Risks
A is correct. Risk owners can monitor, respond, and communicate on risk events.
B is incorrect. Buying insurance, also known as transference, may not be an affordable
or available solution for all the risks within the project. C is incorrect. This is
not feasible because multiple risks may overlap each other in the schedule. In addition,
the project manager’s presence won’t address the risk event itself. D is incorrect.
This also is not a feasible option. A project may have multiple risks on multiple
paths. It would be highly unlikely for the project manager to schedule activities
so that activities with risks do not overlap.
Q158: Monitoring and Controlling the Project
158. You are the project manager of a large construction project. There are several
pieces of work within the project that you have procured to a vendor. The smaller
contracted work is completed through a time and materials contract. What stipulation
must exist within the contract in order to prevent inherent risks in the project?
A. A deadline
B. It should not exceed specifications.
C. The costs per hour
D. The total costs for the procured work
Answer: B
Hint: Amounts over this point are a risk trigger.
Study Guide Objective: Monitor All Risks
B is correct. A time and materials (T–M) contract needs a Not to Exceed (NTE) stipulation.
A is incorrect because not all T–M contracts have deadlines. C is incorrect because
the costs per hour is a prerequisite for this type of contract. D is incorrect. Not
all T–M contracts have a total costs for the projected work. This is why the NTE clause
is needed.
Q159: Monitoring and Controlling the Project
159. You are the project manager of a project to install new wireless devices at more
than 900 retail stores throughout North America. One of the identified risks in the
project is that some of the stores may receive interference from other outlets in
the shopping area. Mary, an installer of the wireless devices, has identified a store
she is working on that is receiving interference from other signals in the area. The
risk response you have planned is to install a slightly higher-cost radio device.
This risk response that Mary should now implement is which one of the following?
A. A countermeasure
B. A mitigation
C. A transference
D. A contingency plan
Answer: D
Hint: Requires planning and funds set aside to respond to the risk event.
Study Guide Objective: Monitor All Risks
D is correct. Contingency planning requires additional funding and time set aside
for the risk event.
A is incorrect because a countermeasure is an action to neutralize the risk event.
B is incorrect because mitigation is steps taken to reduce the impact and likelihood
of the risk event. C is also incorrect. Transference moves the risk ownership to a
third party.
Q160: Monitoring and Controlling the Project
160. Not all risk responses are managed internally because some risks can be solved
through purchases and outsourcing. For example, errors and omission insurance is an
example of which risk response?
A. Trigger
B. Threshold
C. Transference
D. Countermeasure
Answer: C
Hint: Someone else owns the risk.
Study Guide Objective: Monitor All Risks
C is correct. Transference transfers the risk to someone else.
A is incorrect because a trigger is a sign that a risk event has occurred or is about
to occur. B is incorrect because thresholds are metrics that mean a risk event is
occurring as conditions pass the preset mark. D is also incorrect because countermeasures
are actions to neutralize the risk event.
Q161: Monitoring and Controlling the Project
161. You are the project manager of the GHY Project for your company. This project
is scheduled to last two years and has a budget of $1,250,000. You have identified
a new risk in your project. What must be updated?
A. The risk response plan
B. The work breakdown structure
C. The risk register
D. The scope statement
Answer: C
Hint: Record the risk.
Study Guide Objective: Monitor All Risks
C is correct. When a new risk has been identified, the risk register must be updated.
A is incorrect. The risk response may need to be updated—if there is to be a response
to the identified risk. The first step is to update the risk register. B is incorrect
because the WBS does not need to be updated since the project scope has not changed.
D is also incorrect because the scope statement is not updated as a result of risk
discovery.
Q162: Monitoring and Controlling the Project
162. As a PMP, you should be somewhat familiar with the project management processes
and their components. Which one of the following is NOT an input to risk control?
A. The project management plan
B. The work breakdown structure
C. The risk register
D. Work performance data
Answer: B
Hint: Decompose
Study Guide Objective: Monitor All Risks
B is correct. The WBS is not an input to risk monitoring and control.
A is incorrect because the project management plan, specifically its risk management
plan, is an input to risk monitoring and control. C is incorrect. The risk register
is an input to risk monitoring and control. D is incorrect because work performance
data is also an input to risk monitoring and control.
Q163: Monitoring and Controlling the Project
163. Your project is moving toward closure and several risks that have been identified
did not come into fruition. What should be updated?
A. The historical records
B. The work breakdown structure
C. The risk register
D. The risk response plan
Answer: C
Hint: It’s the center of all risk documentation.
Study Guide Objective: Monitor All Risks
C is correct. When a risk has been identified, it is documented in the risk register.
The risk is then tracked through the risk register.
A is incorrect. Historical records are records that have occurred before this project
began. Your project is creating future historical records. B is incorrect because
the WBS is not updated. D is incorrect because the risk response is not updated.
Q164: Monitoring and Controlling the Project
164. Controlling project risks is an ongoing activity to ensure that the risk status
has not changed and to react properly and quickly should it change. Which of the following
is
NOT a valid reason for risk control?
A. To determine if project assumptions are still valid
B. To identify trends within risk identification
C. To determine if the contingency reserve is adequate
D. To determine if vendor contracts are valid
Answer: D
Hint: Don’t buy it.
Study Guide Objective: Monitor All Risks
D is correct. The contract type is determined as part of the procurement process.
A, B, and C are incorrect because these are not valid reasons for risk monitoring
and control. Project managers will need to test assumptions for risks, identify risk
trends, and evaluate the contingency reserve of risk events.
Q165: Closing the Project
165. You and your project team have just completed the Warehouse Construction Project.
For the project to be officially complete, what must happen next?
A. Quality inspections
B. You must sign off on the project mechanisms
C. Scope validation
D. Contract closeout
Answer: C
Hint: The project manager needs more than just quality.
Study Guide Objective: Obtain Final Acceptance for the Project
C is correct. Scope validation is the process of obtaining formal acceptance.
A is incorrect. While scope validation uses inspections, it is not only concerned
with quality, but with the fulfillment of the requirements. B is incorrect because
the sign-off of the project mechanisms is not an applicable choice. D is incorrect
because contract closeout can happen throughout the project when vendors have completed
their project obligations, not just at the project’s conclusion.
Q166: Closing the Project
166: Scope validation must be documented and communicated with the project team and
project stakeholders to ensure the timing and scheduling of the event. When does scope
validation happen?
A. Only at the end of the project
B. At the end of each project phase
C. With each deliverable
D. As the customer sees fit
Answer: B
Hint: These are scheduled inspections.
Study Guide Objective: Obtain Final Acceptance for the Project
B is correct. Scope validation is the assurance that the project deliverables have
met the project scope.
A is incorrect because scope validation does not happen only at the end of a project.
C is incorrect because each deliverable does not demand a scope validation. D is also
incorrect. Scope validation happens as phases or projects are completed, not only
when the customer sees fit.
Q167: Closing the Project
167. You are the project manager of the GDS project. The project is in month seven
and is scheduled to last 15 months. Management has decided to cancel the project altogether
due to circumstances outside of your control and does not hold you responsible for
the project cancellation. Which of the following statements best describes scope validation
in this case?
A. Scope validation should be measured against the deliverables that were created
up to the point of the project’s cancellation.
B. Scope validation should be deemed successful because management canceled the project
due to circumstances outside of your control.
C. Scope validation is not needed because the scope was never fulfilled.
D. Scope validation is not needed unless the project is more than 50 percent complete.
Answer: A
Hint: Some scope validation is needed.
Study Guide Objective: Obtain Final Acceptance for the Project
A is correct. Although the project has been canceled, scope validation should take
place for the deliverables up to the point the project was canceled.
B is incorrect. Scope validation is still needed although management canceled the
project due to outside circumstances. C is also incorrect. Although the scope was
never completed, scope validation is still needed. D is incorrect because this is
not a valid option for the question.
Q168: Closing the Project
168. Which one of the following is NOT a component of administrative closure?
A. Activities needed to satisfy project completion
B. Rework
C. Operational transfer of the project’s product
D. Lessons learned
Answer: B
Hint: Closure happens when the work is complete.
Study Guide Objective: Obtain Financial, Legal, and Administrative Closure
B is correct. Rework is not an output of administrative closure. If rework is needed,
the project or phase cannot be closed.
A is incorrect. You’ll need to complete all of the planned activities in order to
do administrative closure. C is incorrect. Once the project is completed, the operational
transfer of the product must happen so the project can be closed and resources released.
D is incorrect because lessons learned are also part of administrative closure.
Q169: Closing the Project
169. You are the project manager of the NHX Project. The project has several vendors.
Vendor ABC has completed their work according to the terms of the contract. What should
happen next?
A. Whatever the terms of the contract call for
B. Scope validation
C. Project closure
D. Lessons learned
Answer: A
Hint: A deal is a deal.
Study Guide Objective: Obtain Financial, Legal, and Administrative Closure
A is correct. The terms of the contract should be followed here since they may have
provisions for an audit, payment procedures, and forms that the vendor may have to
complete to be paid.
B is incorrect. Just because a vendor has completed work on the project does not mean
the project needs scope validation at this point. C is incorrect. The question does
not state that the entire project is finished so this answer is not valid. D is incorrect.
Lessons learned are important, but this is not the best choice for the question.
Q170: Closing the Project
170. You and the vendor are in a dispute about the work within the project. The vendor
is demanding payment for work they completed. You disagree with their demands.
What is the likely outcome of this scenario?
A. Unresolved claims may be subject to litigation
B. Scope validation
C. Project closure
D. Procurement audits
Answer: A
Hint: Lawsuits are not fun.
Study Guide Objective: Obtain Financial, Legal, and Administrative Closure
A is correct. Unresolved claims may result in litigation.
B is incorrect. Just because you and a vendor have a disagreement about the completed
work on the project does not mean the project needs scope validation at this point.
C is incorrect. The question does not state that the entire project is finished, so
this answer is not valid. D is incorrect. A procurement audit may show your internal
process for procurement, but it does not resolve the issue between you and the vendor.